Red flags

  • Litigation declared, 1 case

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Aug 2027Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Podiums (if any), 95%
0Complaints at MahaRERAon this registration
Jump to the 95 documents Report an error

Naman Xana is a Residential / Group Housing project by Shree Naman Residency Pvt. Ltd. in Mumbai City, Maharashtra, registered with MahaRERA as P51900018769 on 4 Dec 2018. Possession is promised by 28 Aug 2027.

At a glance

Project

  • NameNaman Xana
  • TypeResidential / Group Housing
  • Location
    • Khan Abdul Gaffar Khan Road
    • Worli Sea Face
    • Ward GSouth
    • Mumbai City
    • 400018
  • Pincode400018
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900018769
  • ReraGenie IDRG-MH-46378

Builder

  • NameShree Naman Residency Pvt. Ltd.
  • Entity typeCompany
  • DirectorPriyadarshi Mehta

Key dates

this monthRegisteredDec 2018PromisedAug 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Dec 2018
  • Promised completion28 Aug 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed95 files

Current status

65.3%Work done, per cost certificate

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Naman XanaNA410000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 95%.

Naman Xana: 69% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)85%
Podiums (if any)95%
Plinth85%
Stilt Floor95%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.35%

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes40%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes15%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes10%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes35%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed50

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots50
Closed/Covered50

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,584 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Jul 2025
LandownerVillageDistrict
Karp Estate Pvt. Ltd.Mumbai CityMumbai City

Approvals and building plan

Sanctioning authoritymcgm
Permissible FSI13955.65
Proposed, not sanctioned7,551 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch36 Crystal Building Kemps Corner Altamount Road / Tardeo Mumbai Maharashtra 400026
Estimated costRs 298.38 cr
Cost incurredRs 194.96 cr
Work done65.34%
BuildingWingEstimatedIncurred
Naman XanaNARs 298.38 crRs 194.96 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSaurabh Jadhav
ArchitectPhiroze J Panthaki
EngineerRavindra Pawar
EngineerSirajuddin Chaudhary
Chartered AccountantManmal Khapra
Chartered AccountantSanjeev Shah
PartnerRole in project
Shree Naman Residency Pvt. Ltd.-

Litigation declared1

CaseCourtStatus
1502/2015Bombay High CourtOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Aug 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Aug 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 28 Aug 2027

Documents filed95

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Final Form 1 - 31 March 2026 - Xana Signed.pdf20 Apr 2026
Withdrawal Update Form 2File: Naman Xana RERA Form 2 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Final Form 3 March 2026 - Xana Signed.pdf20 Apr 2026
Form 5 (FY 2022-2023)File: SNRPL Form 5 FY 2022-23.pdf13 Mar 2026
Form 5 (FY 2023-2024)File: SNRPL-NAMAN XANA FORM 5 2023-24.pdf13 Mar 2026
Form 5 (FY 2021-2022)File: Shree Naman Residency Pvt Ltd- Form 5 2021-22.pdf13 Mar 2026
Withdrawal Update Form 1File: Naman Xana RERA Form 1 2026.pdf21 Jan 2026
Withdrawal Update Form 2File: Naman Xana RERA Form 2 2026.pdf21 Jan 2026
Withdrawal Update Form 3File: Form-3 Naman Xana RERA 03-09-2025.pdf21 Jan 2026
Withdrawal Update Form 1File: Form - 1 Sept205 Architect Rera Letter.pdf17 Nov 2025
Withdrawal Update Form 2File: Form - 2 Sept2025 Annexure-B_Engineers Certificate.pdf17 Nov 2025
Withdrawal Update Form 3File: Form-3 Naman Xana RERA 03-09-2025.pdf17 Nov 2025
Form 1File: Form 1 RERA CERTIFICATE 22 05 2025 (1).pdf18 Oct 2025
Form 2File: Form 2 Revised Engineers Certificate.pdf18 Oct 2025
Form 3File: Form 3 Xana.pdf18 Oct 2025
Disclosure of Sold and Booked InventoryFile: Xana Sold Unsold 30 Sept 2025.pdf18 Oct 2025
Form 1File: Form 1 - 09 01 2025 Rera Certificate.pdf18 Oct 2025
Form 2File: Form-2_Engineers Certificate.pdf18 Oct 2025
Form 3File: Form 3 Naman Xana RERA Form 3 Q-3 24-25.pdf18 Oct 2025
Disclosure of Sold and Booked InventoryFile: XANA DISCOLSURE OF SOLD UNSOLD.pdf18 Oct 2025
Form 1File: Form 1 Architect certificte sept2024.pdf18 Oct 2025
Form 2File: Form-2_Engineers Certificate.pdf18 Oct 2025
Form 3File: Form 3 New RERA Certificate.pdf18 Oct 2025
Disclosure of Sold and Booked InventoryFile: XANA DISCOLSURE OF SOLD UNSOLD.pdf18 Oct 2025
Disclosure of Sold and Booked InventoryFile: XANA DISCOLSURE OF SOLD UNSOLD.pdf18 Oct 2025
Form 1File: Form 1 RERA Architect Certificte March2024.pdf18 Oct 2025
Form 2File: Form-2_Engineers Certificate.pdf18 Oct 2025
Form 3File: Form 3 Naman Xana- RERA Q-4.pdf18 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 - SNRPL Naman Xana 24-25.pdf18 Oct 2025
Withdrawal Update Form 1File: Form - 1 Sept205 Architect Rera Letter.pdf17 Oct 2025
Withdrawal Update Form 2File: Form - 2 Sept2025 Annexure-B_Engineers Certificate.pdf17 Oct 2025
Withdrawal Update Form 3File: Form-3 Naman Xana RERA 03-09-2025.pdf17 Oct 2025
Building plan approvalFile: Ammended plan letter2025 07 22.pdf23 Aug 2025
Layout approvalFile: Drawing 2025 07 22_compressed.pdf23 Aug 2025
Building plan approvalFile: Amend letter_signed.pdf22 May 2025
Building plan approvalFile: 2478489_FurtherCC_signed.pdf21 May 2025
Certificates of CA (Form 3)File: RERA Form 3 Naman Xana Q 4_compressed (1)_compressed (1).pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure-B_Form-2_Engineers Certificate.pdf28 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA AREA 22 04 2025 (1).pdf24 Apr 2025
Certificates of CA (Form 3)File: 09 04 2025 Rera Certificate.pdf24 Apr 2025
Proforma of Agreement for saleFile: Draft Agreement for Sale - Naman Xana.pdf26 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 09 01 2025 Rera Certificate.pdf12 Feb 2025
Certificates of CA (Form 3)File: Naman Xana RERA Form 3 Q-3 24-25_compressed_compressed.pdf12 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure-B_Form-2_Engineers Certificate (002) (002) (002).pdf12 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Naman Xana Rera Form 3 Sep 24.pdf26 Nov 2024
Certificates of CA (Form 3)File: CA Certificate form3 .pdf26 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Naman Xana Eng Certificate.pdf26 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure-B_Form-2_Engineers Certificate .pdf20 Aug 2024
Certificates of CA (Form 3)File: Naman Xana- Form 3 30-06-2024.pdf20 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Worli-Arch certifcateRERA June24.pdf19 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SNRPL-NAMAN XANA FORM 5 2023-24.pdf8 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Architect Certificte March2024.pdf17 Apr 2024
Certificates of CA (Form 3)File: Naman Xana- RERA Q-4 .pdf15 Apr 2024
Certificates of CA (Form 3)File: XANA RERA CERT 31122023.pdf12 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Architect Certificte Dec2023.pdf18 Jan 2024
Certificates of CA (Form 3)File: NAMAN XANA- RERA FOR 3 SEPTEMBER 2023.pdf21 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sept 2023 Form -1-Annexure-1 (Architect certificate).pdf11 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: 1772023_FurtherCC_signed.pdf18 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect certificatejun23.pdf6 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SNRPL Form 5 FY 2022-23.pdf28 Jun 2023
Details of encumbrancesFile: Revised Joint Self Certified Encumbrances_Certificate .pdf21 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Revised Architect certificate.pdf19 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Revised Engineer certificate.pdf19 Apr 2023
Certificates of CA (Form 3)File: FORM 3 Naman Xana.pdf19 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 3 Naman Xana.pdf14 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure-B_Form-2_Engineers Certificate (002) (002) (002).pdf14 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate form 1 Naman xana.pdf12 Apr 2023
Details of encumbrancesFile: Self certified Encumbrance certificate.pdf1 Apr 2023
Declaration in FORM BFile: FORM B2932023.pdf1 Apr 2023
Building plan approvalFile: 2219753Amendletter_signed.pdf20 Mar 2023
Building Plan Approval (IOD)File: 2219753Amendletter_signed.pdf20 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: 2328619_FurtherCC_signed.pdf20 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: WorliArch certificate RERA 301222pdf.pdf17 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Shree Naman Residency Pvt Ltd- Form 5 2021-22.pdf17 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: WorliArch certificate RERA 301222pdf.pdf12 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Shree Naman Residency Pvt Ltd Form5 2021-22.pdf26 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Shree Naman Residency Form 5 20-21.pdf30 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 CERTIFICATE 2019-20.pdf21 Jul 2021
Details of Restarting of Construction work post lockdownFile: NX Details of Restarting 15 07 2020.pdf16 Jul 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SNRPL Naman Xana Quality Assurance Certificate Form 2 A 12032020.pdf12 Mar 2020

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one has not
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Naman Xana on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Worli Sea Face780+ in Mumbai City

2 kmNaman XanaCompleted 13Lapsed / revoked 12Other 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 42 registered projects within 2 km.

Builder: Shree Naman Residency Pvt. Ltd.

Shree Naman Residency Pvt. Ltd. has 1 registration on MahaRERA, including Naman Xana. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if Naman Xana is delayed beyond 28 Aug 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Naman Xana?

The registered promoter entity is Shree Naman Residency Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Naman Xana?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Naman Xana?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Naman Xana?

The professionals named in the filing: Architect: Saurabh Jadhav; Architect: Phiroze J Panthaki; Engineer: Ravindra Pawar; Engineer: Sirajuddin Chaudhary; Chartered Accountant: Manmal Khapra; Chartered Accountant: Sanjeev Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Naman Xana?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Naman Xana. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Naman Xana to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.