Home / Browse projects / Satara, Maharashtra / NAKSHTRA

Registered No litigation declared Others project

NAKSHTRA

By PACIFIC ERA

RG-MH-10071 · RERA P52700010708 · Last updated on MahaRERA portal: 20 Jun 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 93 months
  • 7 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
12 of 50Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 146 documents Report an error

NAKSHTRA is a Others project by PACIFIC ERA in Satara, Maharashtra, registered with MahaRERA as P52700010708 on 31 Aug 2017. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 93 months from the original filing. 38 of the 50 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameNAKSHTRA
  • TypeOthers
  • Location
    • Khandala
    • Satara
    • Shindewadi
    • 412801
  • Pincode412801
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700010708
  • ReraGenie IDRG-MH-10071

Builder

  • NamePACIFIC ERA
  • Entity typePartnership
  • PartnersNikhil Prashant DUDHE, VIVEK SURESH KAMAT, Vaishali Dudhe

Key dates

1 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed146 files

Current status

76%38 of 50 units booked
95.9%Work done, per cost certificate

Figures as on 20 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NAKSHTRANA65361450

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

NAKSHTRA: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed68

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots68
Closed/Covered60
Open Space8

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,148 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Nov 2025

Approvals and building plan

Sanctioning authorityTown Planning And Valuation Department Satara
Permissible FSI1491.49
Proposed, not sanctioned1,491 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAMNAGAR, DOMBIVLI
Estimated costRs 3.60 cr
Cost incurredRs 3.45 cr
Work done95.94%
BuildingWingEstimatedIncurred
NAKSHTRANARs 3.60 crRs 3.45 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNITEEN KIRVE
EngineerShri Amod Luman
EngineerDeepak P Khillare
Chartered AccountantMaisha Dhawale
Chartered AccountantJignesh Dedhia & Co. LLP
Chartered AccountantAnand Mukul Associates
PartnerRole in project
PACIFIC ERA-

Extensions applied for7

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52700017471Dec 2018 → Jun 2024

Reason as filed by the promoterDue to unforeseeable circumstances we could not complete the project within the stipulated time, hence requesting to extend the registration of the preoject. hereby attaching the Format B and Form B.

EXT52700023003Dec 2018 → Mar 2025

Reason as filed by the promoterthe Project is in its final stages and not complete yet due to some unenforceable delays and cannot get the OC issued before the due date of validity. Hence, we need more time to complete the Project. Rest assured, we are nearing the completion of the Project, and need some more time to complete the Project work. Therefore, we hereby apply for extension of Project Registration validity till 31-03-2025

EXT52700002304Dec 2018 → Aug 2020

Reason as filed by the promoterFinishing Work Pending

EXT52700012580Dec 2018 → Sep 2023

Reason as filed by the promoterThe project was originally planned to be complete by 30th September 2022 but the construction activity was slowed down due to Covid-19 Pandemic induced economic slowdown causing fund limitations. However, keeping the interests and rights intact of the buyers, and financial viability for completing the project and after detailed discussions with all the allottees, we forecast that the project shall complete within a year's time i.e. by 30th September 2022. Kindly request you to grant us extension, supported by the resolution of allottees in the form of 'Format B'.

EXT52700010883Dec 2018 → Mar 2022

Reason as filed by the promoterUnavailability of Manpower, Material & Covid Conditions the Project is Delayed

EXT52700027938Dec 2018 → Dec 2025

Reason as filed by the promoterExtension is majorly due to significant shortage, which severely have impacted the construction timeline. We are near project completion and preparing to apply for OC

EA24112518419Dec 2018 → Sep 2026

Reason as filed by the promoterThe extension is majorly due to significant Material shortages, which severely have impacted the construction timeline, delaying important stages of project. However, we are nearing the project completion and preparing to apply for OC. Hence, additional time is required to address the delays, requesting you to grant us the same.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed146

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 146 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Nakshtra Q4 Form 1.pdf20 Jun 2026
Withdrawal Update Form 2File: Nakshtra Q4 Form 2.pdf20 Jun 2026
Withdrawal Update Form 3File: Nakshtra Q4 Form 3.pdf20 Jun 2026
Form 2A (FY 2025-2026)File: Nakshtra Form 2A FY 25 26.pdf20 Jun 2026
Form 5 (FY 2025-2026)File: Form 5 FY 25-26 NAKSHTRA.pdf20 Jun 2026
Withdrawal Update Form 1File: Form 1 Q3 Nakshtra ACE Scanner_2026_02_13(2) (1).pdf17 Feb 2026
Withdrawal Update Form 2File: Form 2 ACE Scanner_2026_02_17(1).pdf17 Feb 2026
Withdrawal Update Form 3File: form 3ACE Scanner_2026_02_17.pdf17 Feb 2026
Form 2A (FY 2024-2025)File: form 2A APR Nakshtra correct.pdf28 Nov 2025
Form 2A (FY 2019-2020)File: Form 2A 19-20.pdf25 Nov 2025
Form 2A (FY 2020-2021)File: Form 2A 20-21_compressed (1).pdf25 Nov 2025
Form 2A (FY 2021-2022)File: Form 2A 21-22.pdf25 Nov 2025
Form 2A (FY 2022-2023)File: Form 2A 22-23.pdf25 Nov 2025
Form 2A (FY 2023-2024)File: Form 2A pacific Era.pdf25 Nov 2025
Form 5 (FY 2018-2019)File: Form 5 18-19.pdf25 Nov 2025
Form 5 (FY 2019-2020)File: Form 5 Certificates of CA 19-20.pdf25 Nov 2025
Form 5 (FY 2020-2021)File: Form 5 Certificates of CA 20-21.pdf25 Nov 2025
Form 5 (FY 2021-2022)File: Form 5 21-22.pdf25 Nov 2025
Form 5 (FY 2022-2023)File: Form 5 22 -23.pdf25 Nov 2025
Form 5 (FY 2023-2024)File: Form 5 Nakshtra.pdf25 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 APR 2024-25 correct.pdf25 Nov 2025
Withdrawal Update Form 1File: Form 1 Q2 2025-26.pdf24 Nov 2025
Withdrawal Update Form 2File: Form 2 Q2 2025-26.pdf24 Nov 2025
Withdrawal Update Form 3File: Form 3 Q2 2025-26 Nakshatra (Pacific Era).pdf24 Nov 2025
Form 1File: Form1.pdf20 Nov 2025
Form 2File: Form 2.pdf20 Nov 2025
Form 3File: Form 3.pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold booked inventory Q1 23-24.pdf20 Nov 2025
Form 1File: Form 1 Q2 Architect.pdf20 Nov 2025
Form 2File: Form 2 Q 2.pdf20 Nov 2025
Form 3File: Form 3 CA Q 2.pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold booked inventory Q2 23-24.pdf20 Nov 2025
Form 1File: Form 1 Q3 Architect.pdf20 Nov 2025
Form 2File: Form 2 Q 3.pdf20 Nov 2025
Form 3File: Form 3 CA Q 03.pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold booked inventory Q3 23-24.pdf20 Nov 2025
Form 1File: Form 1 Q4 Architect.pdf20 Nov 2025
Form 2File: Form 2 Q 4.pdf20 Nov 2025
Form 3File: Form 3 CA Q.pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold booked inventory.pdf20 Nov 2025
Form 1File: Q1 Form 1.pdf20 Nov 2025
Form 2File: Q1 Form 2.pdf20 Nov 2025
Form 3File: Q1 Form 3.pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: Q1 Sold Book Inventory.pdf20 Nov 2025
Form 1File: Q2 Form 1.pdf20 Nov 2025
Form 2File: Q2 Form 2.pdf20 Nov 2025
Form 3File: Q2 Form 3.pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: Q2 Sold Book Inventory.pdf20 Nov 2025
Form 1File: Q3 Form 1.pdf20 Nov 2025
Form 2File: Q3 Form 2.pdf20 Nov 2025
Form 3File: Q3 Form 3.pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: Q3 Sold Book Inventory.pdf20 Nov 2025
Form 1File: Form 1 (Q4 2024-25).pdf20 Nov 2025
Form 2File: Form 2 (Q4 2024-25).pdf20 Nov 2025
Form 3File: Form 3 (Q4 2024-25).pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold unsold inventory (Q4 2024-25).pdf20 Nov 2025
Withdrawal Update Form 1File: Form 1 Q1 2025-26.pdf20 Nov 2025
Withdrawal Update Form 2File: Form 2 (Q1 2025-26).pdf20 Nov 2025
Withdrawal Update Form 3File: Form 3 Q1 2025-26.pdf20 Nov 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (Q4 2024-25).pdf21 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (Q4 2024-25).pdf6 May 2025
Certificates of CA (Form 3)File: Form 3 (Q4 2024-25)_compressed.pdf6 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (Q4 2024-25).pdf6 May 2025
Disclosure of sold/ booked inventoryFile: sold unsold inventory (Q4 2024-25).pdf6 May 2025
Disclosure of sold/ booked inventoryFile: Sold Book Inventory.pdf21 Mar 2025
Other - TechnicalFile: PERT Chart Nakshtra.pdf21 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Nakshtra.pdf21 Mar 2025
Declaration in FORM BFile: form B Nakshtra.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q1 Form 1.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q2 Form 1.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q3 Form 1.pdf18 Mar 2025
Certificates of CA (Form 3)File: Q1 Form 3.pdf18 Mar 2025
Certificates of CA (Form 3)File: Q2 Form 3.pdf18 Mar 2025
Certificates of CA (Form 3)File: Q3 Form 3.pdf18 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q3 Form 2.pdf18 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q2 Form 2.pdf18 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q1 Form 2.pdf18 Mar 2025
Disclosure of sold/ booked inventoryFile: Q1 Sold Book Inventory.pdf18 Mar 2025
Disclosure of sold/ booked inventoryFile: Q2 Sold Book Inventory.pdf18 Mar 2025
Disclosure of sold/ booked inventoryFile: Q3 Sold Book Inventory.pdf18 Mar 2025

How this compares with Satara

76%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one moved by 93 months
35%of Satara registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep NAKSHTRA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Satara1,100+ in Satara

2 kmNAKSHTRACompleted 5Lapsed / revoked 1Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: PACIFIC ERA

PACIFIC ERA has 1 registration on MahaRERA, including NAKSHTRA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if NAKSHTRA is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NAKSHTRA?

The registered promoter entity is PACIFIC ERA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NAKSHTRA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NAKSHTRA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NAKSHTRA?

The professionals named in the filing: Architect: NITEEN KIRVE; Engineer: Shri Amod Luman; Engineer: Deepak P Khillare; Chartered Accountant: Maisha Dhawale; Chartered Accountant: Jignesh Dedhia & Co. LLP; Chartered Accountant: Anand Mukul Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NAKSHTRA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NAKSHTRA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NAKSHTRA to a free account