NAKSHATRA CLASSIC
By LEVEL UP ERANDAVANE PROMOTERS & BUILDERS
RG-MH-64675 · RERA P52100052628 · Last updated on MahaRERA portal: 28 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 21 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NAKSHATRA CLASSIC is a Residential / Group Housing project by LEVEL UP ERANDAVANE PROMOTERS & BUILDERS in Pune, Maharashtra, registered with MahaRERA as P52100052628 on 15 Sep 2023. Possession is promised by 30 Nov 2026. The completion date has moved by 21 months from the original filing. 3 of the 10 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameNAKSHATRA CLASSIC
- TypeResidential / Group Housing
- Location
- PLOT NO 4/27
- ERANWANE
- ERANDWANE
- Pune (M Corp.)
- Pune City
- Pune
- 411004
- Pincode411004
- RERA no.P52100052628
- ReraGenie IDRG-MH-64675
Builder
- NameLEVEL UP ERANDAVANE PROMOTERS & BUILDERS
- Entity typePartnership
- PartnersNILESH MOHAN MORE, PRIYANKA VASANT SONDKAR
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Sep 2023
- Promised completion30 Nov 2026
- Revised completionRevised to 30 Nov 2026 (originally 28 Feb 2025)
- Buildings1 building record
- Documents filed53 files
Current status
Figures as on 28 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NAKSHATRA CLASSIC | NA | 5 | 5 | 10 | 0 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
NAKSHATRA CLASSIC: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 28 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| RAGHUVANSH APARTMENT CONDOMINIUM | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| NAKSHATRA CLASSIC | NA | Rs 2.15 cr | Rs 2.15 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VIINOD & ASSOCIATES |
| Engineer | NIKHIL CHOUGULE |
| Engineer | SHREERAM SHINDE |
| Chartered Accountant | VIPIN KHOBRAGADE & CO |
| Partner | Role in project |
|---|---|
| LEVEL UP ERANDAVANE PROMOTERS & BUILDERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. LABOUR SHORTAGE 2. MATERIAL NON AVAILIBILITY 3. RAINY SEASON 4. LOW BOOKING RATE 5. DELAY IN PAPERWORK NOC ETC
Reason as filed by the promoterOC is received for the project applying for an extension to complete the project procedures
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000340695 | Unity spaces LLP through Swapnil shahaji Ranawade | LEVEL UP ERANDAVANE PROMOTERS & BUILDERS | 07/04/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Aug 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Mar 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Mar 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Nov 2026
Documents filed53
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: ARCH FORM 1 JUNE 2026.pdf | 28 Sep 2026 |
| Withdrawal Update Form 1File: ARCH FORM 1 JUNE 2026.pdf | 28 Sep 2026 |
| Withdrawal Update Form 2File: ENGINEER FORM 2 MARCH 2026(1).pdf | 28 Sep 2026 |
| Withdrawal Update Form 2File: ENGINEER FORM 2 MARCH 2026(1).pdf | 28 Sep 2026 |
| Withdrawal Update Form 3File: CA FORM 3 2026-1(1).pdf | 28 Sep 2026 |
| Withdrawal Update Form 3File: CA FORM 3 2026-1(1).pdf | 28 Sep 2026 |
| Withdrawal Update Form 1File: ARCH FORM 1 JUNE 2026.pdf | 25 Aug 2026 |
| Withdrawal Update Form 2File: ENGINEER FORM 2 MARCH 2026(1).pdf | 25 Aug 2026 |
| Withdrawal Update Form 3File: CA FORM 3 2026-1(1).pdf | 25 Aug 2026 |
| Withdrawal Update Form 1File: ARCH FORM 1 JUNE 2026.pdf | 11 Aug 2026 |
| Withdrawal Update Form 1File: ARCH FORM 1 JUNE 2026.pdf | 11 Aug 2026 |
| Withdrawal Update Form 1File: ARCH FORM 1 JUNE 2026.pdf | 11 Aug 2026 |
| Withdrawal Update Form 2File: ENGINEER FORM 2 MARCH 2026(1).pdf | 11 Aug 2026 |
| Withdrawal Update Form 2File: ENGINEER FORM 2 MARCH 2026(1).pdf | 11 Aug 2026 |
| Withdrawal Update Form 2File: ENGINEER FORM 2 MARCH 2026(1).pdf | 11 Aug 2026 |
| Withdrawal Update Form 3File: CA FORM 3 2026-1(1).pdf | 11 Aug 2026 |
| Withdrawal Update Form 3File: CA FORM 3 2026-1(1).pdf | 11 Aug 2026 |
| Withdrawal Update Form 3File: CA FORM 3 2026-1(1).pdf | 11 Aug 2026 |
| Form 2A (FY 2025-2026)File: ENGINEER FORM 2 PERIOD 2025-26(1).pdf | 11 Aug 2026 |
| Form 1File: FORM 1.pdf | 13 Jun 2025 |
| Form 2File: FORM 2.pdf | 13 Jun 2025 |
| Form 3File: FORM 3.pdf | 13 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf | 13 Jun 2025 |
| Form 2A (FY 2023-2024)File: FORM 2A PERIOD 2023-24.pdf | 13 Jun 2025 |
| Form 2A (FY 2024-2025)File: FORM 2A PERIOD 2024-25.pdf | 13 Jun 2025 |
| Other - TechnicalFile: IMG-20230912-WA0001.pdf | 12 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCES.pdf | 8 Sep 2023 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCES.pdf | 8 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT.pdf | 8 Sep 2023 |
| Declaration about Commencement CertificateFile: COMMENCEMENT CERTIFICATE.pdf | 8 Sep 2023 |
| CERSAI detailsFile: CERSAI.pdf | 8 Sep 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: NILESH SIR.pdf | 21 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: PRIYANKA MADAM.pdf | 21 Aug 2023 |
| Copy of the legal title reportFile: FINAL TITLE REPORT.pdf | 19 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 LEVELUP NAKSHATRA.pdf | 19 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: OTHER ORGANIZATION DECLARATION.pdf | 19 Aug 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DECLARATION.pdf | 19 Aug 2023 |
| Building plan approvalFile: HPSC0707_compressed.pdf | 30 Mar 2023 |
| Building plan approvalFile: 1.pdf | 30 Mar 2023 |
| Layout approvalFile: HPSC0708_compressed.pdf | 30 Mar 2023 |
| PAN CardFile: PAN Firm.pdf | 30 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: no encum legal.pdf | 30 Mar 2023 |
| Details of encumbrances concerned to LegalFile: no encum legal.pdf | 30 Mar 2023 |
| Copy of Layout Approval (in case of layout)File: HPSC0708_compressed.pdf | 30 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSC0707_compressed.pdf | 30 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 1.pdf | 30 Mar 2023 |
| Declaration in FORM BFile: formb developer.pdf | 30 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1.pdf | 30 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 30 Mar 2023 |
| Proforma of Allotment letterFile: allotment letter.pdf | 30 Mar 2023 |
| Proforma of Agreement for saleFile: sale agreement RERA.pdf | 30 Mar 2023 |
| Deviation Report with respect to Allotment letterFile: no deviation allotment.pdf | 30 Mar 2023 |
| Deviation Report with respect to model copy of AgreementFile: no deviation agreeement.pdf | 30 Mar 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| MANGALNIL RESIDENCY | BARAMATI | 17 | Completed | Mar 2018 | Mar 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- All 53 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep NAKSHATRA CLASSIC on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near ERANDWANE13,700+ in Pune
VENKATESH ERANDWANE CENTRAL - BUILDING-B1 - PH
SHREE VENKATESH BUILDCON PVT LTD
One Place-F.C. Road Phase 3
PALASH REALTORS LLP
45 NIRVAANA HILL - C2 WING
SINEW DEVELOPERS PRIVATE LIMITED
VENKATESH ERANDWANE CENTRAL - BUILDING-B2 - PH
SHREE VENKATESH BUILDCON PVT LTD
VENKATESH ERANDWANE CENTRAL - BUILDING-B3 - PH
SHREE VENKATESH BUILDCON PVT LTD
One Place-F.C Road Phase 2
PALASH REALTORS LLP
Builder: LEVEL UP ERANDAVANE PROMOTERS & BUILDERS
LEVEL UP ERANDAVANE PROMOTERS & BUILDERS has 1 registration on MahaRERA, including NAKSHATRA CLASSIC. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if NAKSHATRA CLASSIC is delayed beyond 30 Nov 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NAKSHATRA CLASSIC?
The registered promoter entity is LEVEL UP ERANDAVANE PROMOTERS & BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NAKSHATRA CLASSIC?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against NAKSHATRA CLASSIC?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for NAKSHATRA CLASSIC?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NAKSHATRA CLASSIC?
The professionals named in the filing: Architect: VIINOD & ASSOCIATES; Engineer: NIKHIL CHOUGULE; Engineer: SHREERAM SHINDE; Chartered Accountant: VIPIN KHOBRAGADE & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NAKSHATRA CLASSIC?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback