Home / Browse projects / Thane, Maharashtra / MY CITY - PHASE I - PART III

Registration lapsed No litigation declared Residential / Group Housing project

MY CITY - PHASE I - PART III

By HORIZON PROJECTS PVT LTD

RG-MH-26737 · RERA P51700005477 · Last updated on MahaRERA portal: 10 Oct 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • 5 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
0 of 44Construction stages doneacross 4 buildings; furthest along: Excavation, 50%
5Complaints at MahaRERAon this registration
Jump to the 110 documents Report an error

MY CITY - PHASE I - PART III is a Residential / Group Housing project by HORIZON PROJECTS PVT LTD in Thane, Maharashtra, registered with MahaRERA as P51700005477 on 11 Aug 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. 5 complaints are on record with the regulator.

At a glance

Project

  • NameMY CITY - PHASE I - PART III
  • TypeResidential / Group Housing
  • Location
    • Diva - Manpada Road
    • Betavade
    • DOMBIVLI
    • Kalyan
    • Thane
    • 400612
  • Pincode400612
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700005477
  • ReraGenie IDRG-MH-26737

Builder

  • NameHORIZON PROJECTS PVT LTD
  • Entity typeCompany
  • CINU45400MH2011PTC213029
  • GSTIN27AAFCR1404F1ZS
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsSaurabh Natu, Deepak Lohia, Sameer Parasmal Nahar, Saurabh Natu, Sameer Parasmal Nahar, Saurabh Natu
  • Other registrations9 more →
  • Completed4 of 10
  • No longer live1 lapsed, de-registered or revoked

Key dates

34 months past promisethis monthRegisteredAug 2017PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Aug 2017
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings4 building records
  • Documents filed110 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A5NA340000
B3NA340000
C5NA340000
A6NA330000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 10 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 50%.

A55%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B35%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C50%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A60%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed512

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots512
Closed/Covered184
Open Space328
BuildingClosed/CoveredOpen SpaceTotal
A58055135
B38041121
C511112123
A613120133

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,414 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMMRDA
Permissible FSI29404.17
Proposed, not sanctioned11,990 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 9 and 10 MARYLAND CORNER NEAR SION CIRCLE SION EAST MUMBAI MAHARASHTRA 400022

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAAKAR ARCHITECTS
ArchitectSaakaar Architects
ArchitectPALLAVI MATKARI
EngineerUTTAM RANGNATH KAWATHANKAR
EngineerATUL WAMAN BAPAT
Chartered AccountantM B Agarwal and Co
Chartered AccountantKshirsagar and Associates
PartnerRole in project
HORIZON PROJECTS PVT LTD-

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000001278DEEPA AMIT KULKARNIHORIZON PROJECTS PRIVATE LIMITED14/10/2017
CC006000000055839DEEPA KULKARNIHORIZON PROJECTS PVT LTD17/08/2018
CC006000000056064SHRADDHA VIRKARRUNWAL GROUP01/12/2018
CC006000000110723Surinder Singh GillHorizon Project Private Limited05/09/2019
CC006000000192776Surinder singh GillHorizon Projects Private Limited29/06/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Oct 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Oct 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed110

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - LegalFile: Deregistration Application Acknowledgement by Maharera - 1-1-24 - converted.pdf10 Oct 2024
Other - LegalFile: Deregistration Application Acknowledgement by Maharera - 1-1-24 - converted.pdf10 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate-30-09-22.pdf13 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - 31-12-22.pdf13 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Cerificate 31-03-23.pdf13 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - 30-09-23.pdf13 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - 31-12-23.pdf13 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - 31-03-24.pdf13 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer's Certificate 30-06-23.pdf13 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 My City Phase I Part III 08032021- Year 2019-2020.pdf13 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 My City Phase I Part III 2020 2021.pdf19 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 My City Phase I Part III 2021 2022.pdf19 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate My City Phase I Part III 31122021.pdf12 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 My City Ph 1 Pt 3 30 06 21.pdf8 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 My City Ph 1 Pt 3 30 09 21.pdf8 Sep 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold My City Phase I Part III 30 06 2021.pdf6 Sep 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold My City Phase I Part III 30 09 2021.pdf6 Sep 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold My City Phase I Part I 31 12 2021.pdf6 Sep 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold My City Phase I Part III 31 03 2022.pdf6 Sep 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold My City Phase I Part III 31 12 2021.pdf6 Sep 2022
Disclosure of sold/ booked inventoryFile: Sold Usnsold My City Phase I Part III 30062022.pdf20 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate My City Phase I Part III 30062022.pdf19 Jul 2022
Certificates of CA (Form 3)File: My City Phase I Part III - Form 3 30 06 2022.pdf19 Jul 2022
Certificates of CA (Form 3)File: My City Phase I Part III Form 3 30 09 2017.pdf30 Jun 2022
Certificates of CA (Form 3)File: My City Phase I Part III Form 3 31 12 2017.pdf30 Jun 2022
Certificates of CA (Form 3)File: My City Phase I Part III Form 3 31 03 2018.pdf30 Jun 2022
Certificates of CA (Form 3)File: My City Phase I Part III Form 3 30 06 2018.pdf30 Jun 2022
Certificates of CA (Form 3)File: My City Phase I Part III Form 3 30 09 2018.pdf30 Jun 2022
Certificates of CA (Form 3)File: My City Phase I Part III Form 3 31 12 2018.pdf30 Jun 2022
Certificates of CA (Form 3)File: My City Phase I Part III Form 3 31 03 2019.pdf30 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 June 2019.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Sep 2019.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Dec 2019.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Mar 2020.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 June 2020.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Sep 2020.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Dec 2020.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Mar 2021.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 June 2021.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Mar 2022.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 30092017.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 31122017.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 31032018.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 30062018.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 30092018.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 31122018.pdf29 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 31032019.pdf29 Jun 2022
Certificates of CA (Form 3)File: C A Cer My City Phase I Part III as on 30 062019.pdf29 Jun 2022
Certificates of CA (Form 3)File: C A Cer My City Phase I Part III as on 31 03 2020.pdf29 Jun 2022
Certificates of CA (Form 3)File: C A Cer My City Phase I Part III as on 30 06 2020.pdf29 Jun 2022
Certificates of CA (Form 3)File: C A Cer My City Phase I Part III as on 30 09 2020.pdf29 Jun 2022
Certificates of CA (Form 3)File: C A Cer My City Phase I Part III as on 31 03 2021.pdf29 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A My City Phase I Part III Year 2020.pdf23 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A My City Phase I Part III Year 2021.pdf23 Jun 2022
Certificates of CA (Form 3)File: Form 3 My City Phase I Part III 31122021.pdf23 Jun 2022
Certificates of CA (Form 3)File: Form 3 My City Phase I Part III 31032022.pdf23 Jun 2022
CERSAI detailsFile: My City Phase I PArt III Report.pdf10 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower A5 Phase I Part 3.pdf27 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower A6 Part I part 3.pdf27 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower B3 Phase I Part 3.pdf27 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower C5 Phase I part 3.pdf27 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER A5 _30-09-21_FOR RERA.pdf12 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER A6 _30-09-21_FOR RERA.pdf12 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER B3 _30-09-21_FOR RERA.pdf12 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER C5 _30-09-21_FOR RERA.pdf12 Nov 2021
Certificates of CA (Form 3)File: Form 3 My City Phase I Part III.pdf2 Nov 2021
Certificates of CA (Form 3)File: Form 3 Phase I Part III 04 09 21.pdf13 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase I PART III TOWER A5.pdf19 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase I PART III TOWER A6.pdf19 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase I PART III TOWER B3.pdf19 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase I PART III TOWER C5.pdf19 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER A5 PLOT C _31-03-21.pdf17 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER A6 PLOT C _31-03-21.pdf17 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER B3 PLOT C_31-03-21.pdf17 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER C5 PLOT C _31-03-21.pdf17 May 2021
Certificates of CA (Form 5)File: Form 5 My City Phase I Part III 08032021.pdf10 Mar 2021
Certificates of CA (Form 3)File: Form -3 HPPL - My City Phase 1 Part III.pdf16 Jul 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - My City -Phase I - Part III 09122019.pdf16 Dec 2019
Details of encumbrancesFile: Self declaration reg encumbrance.pdf5 Jan 2019
Declaration in FORM BFile: FORM - B My City Part - III.pdf5 Jan 2019

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MY CITY - PHASE I - PART III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Betavade7,600+ in Thane

2 kmMY CITY - PHASE I - PARTCompleted 18Lapsed / revoked 4Other 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 41 registered projects within 2 km.

Builder: HORIZON PROJECTS PVT LTD

HORIZON PROJECTS PVT LTD has 10 registrations on MahaRERA, including MY CITY - PHASE I - PART I and MY CITY - PHASE I - PART III. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that MY CITY - PHASE I - PART III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MY CITY - PHASE I - PART III is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MY CITY - PHASE I - PART III?

The registered promoter entity is HORIZON PROJECTS PVT LTD, a company as per the filing. Its CIN U45400MH2011PTC213029 and GSTIN 27AAFCR1404F1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MY CITY - PHASE I - PART III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MY CITY - PHASE I - PART III?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MY CITY - PHASE I - PART III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MY CITY - PHASE I - PART III?

The professionals named in the filing: Architect: SAAKAR ARCHITECTS; Architect: Saakaar Architects; Architect: PALLAVI MATKARI; Engineer: UTTAM RANGNATH KAWATHANKAR; Engineer: ATUL WAMAN BAPAT; Chartered Accountant: M B Agarwal and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MY CITY - PHASE I - PART III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MY CITY - PHASE I - PART III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MY CITY - PHASE I - PART III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.