Home / Browse projects / Thane, Maharashtra / MY CITY - PHASE I - PART III
MY CITY - PHASE I - PART III
RG-MH-26737 · RERA P51700005477 · Last updated on MahaRERA portal: 10 Oct 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- 5 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MY CITY - PHASE I - PART III is a Residential / Group Housing project by HORIZON PROJECTS PVT LTD in Thane, Maharashtra, registered with MahaRERA as P51700005477 on 11 Aug 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. 5 complaints are on record with the regulator.
At a glance
Project
- NameMY CITY - PHASE I - PART III
- TypeResidential / Group Housing
- Location
- Diva - Manpada Road
- Betavade
- DOMBIVLI
- Kalyan
- Thane
- 400612
- Pincode400612
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700005477
- ReraGenie IDRG-MH-26737
Builder
- NameHORIZON PROJECTS PVT LTD
- Entity typeCompany
- CINU45400MH2011PTC213029
- GSTIN27AAFCR1404F1ZS
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorsSaurabh Natu, Deepak Lohia, Sameer Parasmal Nahar, Saurabh Natu, Sameer Parasmal Nahar, Saurabh Natu
- Other registrations9 more →
- Completed4 of 10
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on11 Aug 2017
- Promised completion30 Dec 2023
- Revised completionNone
- Buildings4 building records
- Documents filed110 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A5 | NA | 34 | 0 | 0 | 0 | 0 |
| B3 | NA | 34 | 0 | 0 | 0 | 0 |
| C5 | NA | 34 | 0 | 0 | 0 | 0 |
| A6 | NA | 33 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 10 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 50%.
A55%
| Activity | Progress |
|---|---|
| Excavation | 50% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B35%
| Activity | Progress |
|---|---|
| Excavation | 50% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C50%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A60%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 10 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed512
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A5 | 80 | 55 | 135 |
| B3 | 80 | 41 | 121 |
| C5 | 11 | 112 | 123 |
| A6 | 13 | 120 | 133 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAAKAR ARCHITECTS |
| Architect | Saakaar Architects |
| Architect | PALLAVI MATKARI |
| Engineer | UTTAM RANGNATH KAWATHANKAR |
| Engineer | ATUL WAMAN BAPAT |
| Chartered Accountant | M B Agarwal and Co |
| Chartered Accountant | Kshirsagar and Associates |
| Partner | Role in project |
|---|---|
| HORIZON PROJECTS PVT LTD | - |
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001278 | DEEPA AMIT KULKARNI | HORIZON PROJECTS PRIVATE LIMITED | 14/10/2017 |
| CC006000000055839 | DEEPA KULKARNI | HORIZON PROJECTS PVT LTD | 17/08/2018 |
| CC006000000056064 | SHRADDHA VIRKAR | RUNWAL GROUP | 01/12/2018 |
| CC006000000110723 | Surinder Singh Gill | Horizon Project Private Limited | 05/09/2019 |
| CC006000000192776 | Surinder singh Gill | Horizon Projects Private Limited | 29/06/2020 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Oct 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Oct 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed110
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Other - LegalFile: Deregistration Application Acknowledgement by Maharera - 1-1-24 - converted.pdf | 10 Oct 2024 |
| Other - LegalFile: Deregistration Application Acknowledgement by Maharera - 1-1-24 - converted.pdf | 10 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate-30-09-22.pdf | 13 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - 31-12-22.pdf | 13 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Cerificate 31-03-23.pdf | 13 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - 30-09-23.pdf | 13 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - 31-12-23.pdf | 13 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - 31-03-24.pdf | 13 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer's Certificate 30-06-23.pdf | 13 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 My City Phase I Part III 08032021- Year 2019-2020.pdf | 13 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 My City Phase I Part III 2020 2021.pdf | 19 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 My City Phase I Part III 2021 2022.pdf | 19 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate My City Phase I Part III 31122021.pdf | 12 Sep 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 My City Ph 1 Pt 3 30 06 21.pdf | 8 Sep 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 My City Ph 1 Pt 3 30 09 21.pdf | 8 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold My City Phase I Part III 30 06 2021.pdf | 6 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold My City Phase I Part III 30 09 2021.pdf | 6 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold My City Phase I Part I 31 12 2021.pdf | 6 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold My City Phase I Part III 31 03 2022.pdf | 6 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold My City Phase I Part III 31 12 2021.pdf | 6 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Usnsold My City Phase I Part III 30062022.pdf | 20 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate My City Phase I Part III 30062022.pdf | 19 Jul 2022 |
| Certificates of CA (Form 3)File: My City Phase I Part III - Form 3 30 06 2022.pdf | 19 Jul 2022 |
| Certificates of CA (Form 3)File: My City Phase I Part III Form 3 30 09 2017.pdf | 30 Jun 2022 |
| Certificates of CA (Form 3)File: My City Phase I Part III Form 3 31 12 2017.pdf | 30 Jun 2022 |
| Certificates of CA (Form 3)File: My City Phase I Part III Form 3 31 03 2018.pdf | 30 Jun 2022 |
| Certificates of CA (Form 3)File: My City Phase I Part III Form 3 30 06 2018.pdf | 30 Jun 2022 |
| Certificates of CA (Form 3)File: My City Phase I Part III Form 3 30 09 2018.pdf | 30 Jun 2022 |
| Certificates of CA (Form 3)File: My City Phase I Part III Form 3 31 12 2018.pdf | 30 Jun 2022 |
| Certificates of CA (Form 3)File: My City Phase I Part III Form 3 31 03 2019.pdf | 30 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 June 2019.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Sep 2019.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Dec 2019.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Mar 2020.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 June 2020.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Sep 2020.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Dec 2020.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Mar 2021.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 June 2021.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CL 03 Form 2 Mar 2022.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 30092017.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 31122017.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 31032018.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 30062018.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 30092018.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 31122018.pdf | 29 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate My City Phase I Part III 31032019.pdf | 29 Jun 2022 |
| Certificates of CA (Form 3)File: C A Cer My City Phase I Part III as on 30 062019.pdf | 29 Jun 2022 |
| Certificates of CA (Form 3)File: C A Cer My City Phase I Part III as on 31 03 2020.pdf | 29 Jun 2022 |
| Certificates of CA (Form 3)File: C A Cer My City Phase I Part III as on 30 06 2020.pdf | 29 Jun 2022 |
| Certificates of CA (Form 3)File: C A Cer My City Phase I Part III as on 30 09 2020.pdf | 29 Jun 2022 |
| Certificates of CA (Form 3)File: C A Cer My City Phase I Part III as on 31 03 2021.pdf | 29 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A My City Phase I Part III Year 2020.pdf | 23 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A My City Phase I Part III Year 2021.pdf | 23 Jun 2022 |
| Certificates of CA (Form 3)File: Form 3 My City Phase I Part III 31122021.pdf | 23 Jun 2022 |
| Certificates of CA (Form 3)File: Form 3 My City Phase I Part III 31032022.pdf | 23 Jun 2022 |
| CERSAI detailsFile: My City Phase I PArt III Report.pdf | 10 Mar 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower A5 Phase I Part 3.pdf | 27 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower A6 Part I part 3.pdf | 27 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower B3 Phase I Part 3.pdf | 27 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower C5 Phase I part 3.pdf | 27 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER A5 _30-09-21_FOR RERA.pdf | 12 Nov 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER A6 _30-09-21_FOR RERA.pdf | 12 Nov 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER B3 _30-09-21_FOR RERA.pdf | 12 Nov 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER C5 _30-09-21_FOR RERA.pdf | 12 Nov 2021 |
| Certificates of CA (Form 3)File: Form 3 My City Phase I Part III.pdf | 2 Nov 2021 |
| Certificates of CA (Form 3)File: Form 3 Phase I Part III 04 09 21.pdf | 13 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase I PART III TOWER A5.pdf | 19 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase I PART III TOWER A6.pdf | 19 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase I PART III TOWER B3.pdf | 19 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase I PART III TOWER C5.pdf | 19 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER A5 PLOT C _31-03-21.pdf | 17 May 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER A6 PLOT C _31-03-21.pdf | 17 May 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER B3 PLOT C_31-03-21.pdf | 17 May 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE TOWER C5 PLOT C _31-03-21.pdf | 17 May 2021 |
| Certificates of CA (Form 5)File: Form 5 My City Phase I Part III 08032021.pdf | 10 Mar 2021 |
| Certificates of CA (Form 3)File: Form -3 HPPL - My City Phase 1 Part III.pdf | 16 Jul 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - My City -Phase I - Part III 09122019.pdf | 16 Dec 2019 |
| Details of encumbrancesFile: Self declaration reg encumbrance.pdf | 5 Jan 2019 |
| Declaration in FORM BFile: FORM - B My City Part - III.pdf | 5 Jan 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 9 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 110 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep MY CITY - PHASE I - PART III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Betavade7,600+ in Thane
Filed coordinates, straight-line distance. 41 registered projects within 2 km.
DOSTI PLANET NORTH - SECTOR 3
CHALAMA INFRAPROPERTIES PRIVATE LIMITED
NICE WORLD 1
NICE BUILDERS
CENTRAL PARK
HARMAIN ENTERPRISES
MUKTA GHARONDA
SKYLARK INFRASTRUCTURES
Palm Riveria
YES REALTY
Trinity Paradise Phase 1
Trinity Builders
See every Thane project, with the district possession charts
Builder: HORIZON PROJECTS PVT LTD
HORIZON PROJECTS PVT LTD has 10 registrations on MahaRERA, including MY CITY - PHASE I - PART I and MY CITY - PHASE I - PART III. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that MY CITY - PHASE I - PART III shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if MY CITY - PHASE I - PART III is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MY CITY - PHASE I - PART III?
The registered promoter entity is HORIZON PROJECTS PVT LTD, a company as per the filing. Its CIN U45400MH2011PTC213029 and GSTIN 27AAFCR1404F1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MY CITY - PHASE I - PART III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against MY CITY - PHASE I - PART III?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for MY CITY - PHASE I - PART III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MY CITY - PHASE I - PART III?
The professionals named in the filing: Architect: SAAKAR ARCHITECTS; Architect: Saakaar Architects; Architect: PALLAVI MATKARI; Engineer: UTTAM RANGNATH KAWATHANKAR; Engineer: ATUL WAMAN BAPAT; Chartered Accountant: M B Agarwal and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MY CITY - PHASE I - PART III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback