ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Mustafa Empire

Registered No litigation declared Residential / Group Housing project

Mustafa Empire

By Mehraj Construction & Co.

RG-MH-07102 · RERA P51700055672 · Last updated on MahaRERA portal: 7 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Internal walls, 85%
42 of 56Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

Mustafa Empire is a Residential / Group Housing project by Mehraj Construction & Co. in Thane, Maharashtra, registered with MahaRERA as P51700055672 on 8 Apr 2024. Possession is promised by 31 Dec 2028. 14 of the 56 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameMustafa Empire
  • TypeResidential / Group Housing
  • Location
    • old mumbai pune road
    • kausa
    • Thane (M Corp.)
    • Thane
    • 400612
  • Pincode400612
  • RERA no.P51700055672
  • ReraGenie IDRG-MH-07102

Builder

  • NameMehraj Construction & Co.
  • Entity typePartnership
  • PartnersRubina Siddiq Sheikh, Mohammad Siddiq Mustafa Sheikh

Key dates

this monthRegisteredApr 2024PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Apr 2024
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed58 files

Current status

25%14 of 56 units booked
89.0%Work done, per cost certificate

Figures as on 7 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Mustafa Empire Building A1NA7156056

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.

Mustafa Empire Building A1: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor75%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%

Progress on shared amenities15

As on 7 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes9%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Open Space3

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,530 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Jul 2025
LandownerVillageDistrict
MEHRAJ CONSTRUCTION & CO.Thane (M Corp.)Thane
Mehraj Constrcution & Co.Thane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityThane Muncipal Corporation
Permissible FSI4079.48
Proposed, not sanctioned4,079 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMUMBRA KAUSA THANE
Estimated costRs 22.40 cr
Cost incurredRs 19.94 cr
Work done89.0%
BuildingWingEstimatedIncurred
Mustafa Empire Building A1NARs 11.20 crRs 9.74 cr
-NARs 11.20 crRs 10.19 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUKATE STUDIO SRCHITECTS
EngineerSSCOS
Chartered AccountantKailash Solanki & Associates
PartnerRole in project
Mehraj Construction & Co.-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form1.pdf7 Apr 2026
Withdrawal Update Form 1File: form1.pdf7 Apr 2026
Withdrawal Update Form 1File: form1.pdf7 Apr 2026
Withdrawal Update Form 2File: form2.pdf7 Apr 2026
Withdrawal Update Form 2File: form2.pdf7 Apr 2026
Withdrawal Update Form 2File: form2.pdf7 Apr 2026
Withdrawal Update Form 3File: form3.pdf7 Apr 2026
Withdrawal Update Form 3File: form3.pdf7 Apr 2026
Withdrawal Update Form 3File: form3.pdf7 Apr 2026
Withdrawal Update Form 1File: archi.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2-Dec 2025 Mustafa Empire DS.pdf20 Jan 2026
Withdrawal Update Form 3File: FORM 3_Dec 25.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1- Oct 25.pdf15 Oct 2025
Withdrawal Update Form 2File: form 2.pdf15 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf15 Oct 2025
Form 1File: FORM 1 DEC 24.pdf22 Sep 2025
Form 2File: FOrm 2 Dec 24.pdf22 Sep 2025
Form 3File: FORM 3 Dec 24.pdf22 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold booked inventory April 24 to Jun 24.pdf22 Sep 2025
Form 1File: FORM 1_ JUNE 24.pdf22 Sep 2025
Form 2File: FORM 2_June 24.pdf22 Sep 2025
Form 3File: FORM 3_June 24.pdf22 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold booked inventory Jul 24 to Sept 24.pdf22 Sep 2025
Form 1File: FORM 1_ SEP 24.pdf22 Sep 2025
Form 2File: FORM 2_SEP 24.pdf22 Sep 2025
Form 3File: FORM 3_Sep 24.pdf22 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold booked inventory Oct 24 to Dec 24.pdf22 Sep 2025
Form 1File: FORM 1 MAR 25.pdf22 Sep 2025
Form 2File: FORM 2_MAR 25.pdf22 Sep 2025
Form 3File: FORM 3_Mar 25.pdf22 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold booked inventory Jan 25 to March 25.pdf22 Sep 2025
Declaration about Commencement CertificateFile: Document 507.pdf8 Apr 2024
Other - TechnicalFile: b1.pdf6 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf2 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure updated.pdf14 Mar 2024
Other - TechnicalFile: Annexure A.pdf14 Mar 2024
Other - LegalFile: deviation sheet_compressed.pdf29 Feb 2024
Declaration in FORM BFile: Form B updated.pdf5 Feb 2024
Other - LegalFile: annexure A.pdf5 Feb 2024
Deviation Report with respect to Allotment letterFile: Allotment ketter.pdf13 Jan 2024
Deviation Report with respect to model copy of AgreementFile: agreement for sale_compressed.pdf13 Jan 2024
Details of encumbrances concerned to FinanceFile: legal .pdf25 Dec 2023
Details of encumbrances concerned to LegalFile: legal .pdf25 Dec 2023
CERSAI detailsFile: Document 179.pdf15 Dec 2023
Details of encumbrances concerned to FinanceFile: finance dec.pdf10 Dec 2023
Details of encumbrances concerned to LegalFile: finance dec.pdf10 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank account dec.pdf10 Dec 2023
Layout approvalFile: layout higlited plan_compressed.pdf30 Nov 2023
Building plan approvalFile: typical floor plan _compressed.pdf30 Nov 2023
Copy of Layout Approval (in case of layout)File: layout higlited plan_compressed.pdf30 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: typical floor plan _compressed.pdf30 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf25 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf24 Nov 2023
Proforma of Agreement for saleFile: Agreement for sale.pdf24 Nov 2023
PAN CardFile: NEW PAN.pdf10 Nov 2023
Copy of the legal title reportFile: TITEL REPORT.pdf10 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf10 Nov 2023
Proforma of Allotment letterFile: ALLOTMENT LATTER.pdf10 Nov 2023

How this compares with Thane

25%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mustafa Empire on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near kausa7,600+ in Thane

Builder: Mehraj Construction & Co.

Mehraj Construction & Co. has 1 registration on MahaRERA, including Mustafa Empire. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Mustafa Empire is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mustafa Empire?

The registered promoter entity is Mehraj Construction & Co., a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mustafa Empire?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mustafa Empire?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mustafa Empire?

The professionals named in the filing: Architect: SUKATE STUDIO SRCHITECTS; Engineer: SSCOS; Chartered Accountant: Kailash Solanki & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mustafa Empire?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mustafa Empire. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mustafa Empire to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.