ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / MUMBRA LANDMARK

Registration lapsed No litigation declared Residential / Group Housing project

MUMBRA LANDMARK

By JYOTI INDUSTRIES

RG-MH-71768 · RERA P51700015369 · Last updated on MahaRERA portal: 1 Feb 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
13 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 80%
0 of 65Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

MUMBRA LANDMARK is a Residential / Group Housing project by JYOTI INDUSTRIES in Thane, Maharashtra, registered with MahaRERA as P51700015369 on 20 Feb 2018. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 65 of the 65 units on this registration are recorded sold or booked, and 13 of 33 construction stages are filed complete.

At a glance

Project

  • NameMUMBRA LANDMARK
  • TypeResidential / Group Housing
  • Location
    • MUMBAI-PUNE ROAD
    • AMRUT NAGAR
    • MUMBRA
    • Thane (M Corp.)
    • Thane
    • 400612
  • Pincode400612
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700015369
  • ReraGenie IDRG-MH-71768

Builder

  • NameJYOTI INDUSTRIES
  • Entity typePartnership
  • GSTIN27AABFJ0061D1ZZ
  • PartnersCHIMANLAL PREMJI THAKKAR, ATIQUER REHMAN ABUTALIB SHAIKH, BHAWANJI KHIMJI SHAH

Key dates

22 months past promisethis monthRegisteredFeb 2018PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on20 Feb 2018
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings3 building records
  • Documents filed42 files

Current status

100%65 of 65 units booked

Figures as on 1 Feb 2022, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA9831031
BUILDING BNA9831031
BUILDING CNA94033

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 1 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 80%.

BUILDING A76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
BUILDING B74%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
BUILDING C28%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed31

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots31
Closed/Covered31
BuildingClosed/CoveredTotal
BUILDING A2929
BUILDING B11
BUILDING C11

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,000 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Mar 2026

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI3585.66
Proposed, not sanctioned3,586 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, SHOP NO 9-10, DOST APARTMENT, KAUSA, MUMBAI-PUNE ROAD, THANE - 400612

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGODBOLE MUKADAM & ASSOCIATES
EngineerYateesh Tare
Chartered AccountantShamim Esmail Shaikh
PartnerRole in project
JYOTI INDUSTRIES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Feb 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Feb 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Feb 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Feb 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20200115_ARCHITECT'S CERTIFICATE_FORM 1.pdf1 Feb 2022
Certificates of CA (Form 3)File: FORM 3_1-5.pdf1 Feb 2022
Certificates of CA (Form 3)File: FORM 3_6-12.pdf1 Feb 2022
Annual Audit Report of Statutory CA (Form 5)File: 20210923_Rera Annual Report 2019-20.pdf23 Sep 2021
Annual Audit Report of Statutory CA (Form 5)File: 20210923_Rera Annual Report 2020-21.pdf23 Sep 2021
Declaration about Commencement CertificateFile: 20210915_Declaration of CC.pdf15 Sep 2021
Certificates of CA (Form 3)File: 20201215_FORM 3_1ST QUARTER.pdf15 Dec 2020
Certificates of CA (Form 3)File: 20201215_FORM 3_2ND QUARTER.pdf15 Dec 2020
Certificates of CA (Form 3)File: 20201215_FORM 3_3RD QUARTER.pdf15 Dec 2020
Certificates of CA (Form 3)File: 20200128_C A CERTIFICATE_DEC 2019.pdf28 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20191107_ARCHITECT'S CERTIFICATE_FORM 1.pdf7 Nov 2019
Certificates of CA (Form 3)File: 20191107_C A CERTIFICATE_JUNE 2019.pdf7 Nov 2019
Certificates of CA (Form 3)File: 20191107_C A CERTIFICATE_SEPT 2019.pdf7 Nov 2019
Annual Audit Report of Statutory CA (Form 5)File: 20190917_FORM 5.pdf17 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20190725_ARCHITECT'S CERTIFICATE_FORM 1.pdf25 Jul 2019
Certificates of CA (Form 3)File: 20190725_C A CERTIFICATE_FORM 3.pdf25 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20180821_ARCHITECT'S CERTIFICATE_FORM 1.pdf21 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 201808121_ENGINEER CERTIFICATE_FORM 2.pdf21 Aug 2018
Building plan approvalFile: PERMISSION.pdf5 Feb 2018
Layout approvalFile: SHEET 1.pdf5 Feb 2018
Layout approvalFile: SHEET 2.pdf5 Feb 2018
Layout approvalFile: SHEET 3.pdf5 Feb 2018
Layout approvalFile: SHEET 4.pdf5 Feb 2018
Layout approvalFile: SHEET 5.pdf5 Feb 2018
PAN CardFile: COMPANY PAN CARD.pdf5 Feb 2018
Copy of the legal title reportFile: TITLE REPORT.pdf5 Feb 2018
Details of encumbrancesFile: ENCUMBRANCE LETTER.pdf5 Feb 2018
Copy of Layout Approval (in case of layout)File: SHEET 1.pdf5 Feb 2018
Copy of Layout Approval (in case of layout)File: SHEET 2.pdf5 Feb 2018
Copy of Layout Approval (in case of layout)File: SHEET 3.pdf5 Feb 2018
Copy of Layout Approval (in case of layout)File: SHEET 4.pdf5 Feb 2018
Copy of Layout Approval (in case of layout)File: SHEET 5.pdf5 Feb 2018
Building Plan Approval (IOD)File: PERMISSION.pdf5 Feb 2018
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf5 Feb 2018
Declaration in FORM BFile: DECLARATION (FORM B).pdf5 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE.pdf5 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE.pdf5 Feb 2018
Certificates of CA (Form 3)File: C A CERTIFICATE 1.pdf5 Feb 2018
Certificates of CA (Form 3)File: C A CERTIFICATE 2.pdf5 Feb 2018
Proforma of Allotment letterFile: SALE AGREEMENT DRAFT Pg 1-16.pdf5 Feb 2018
Proforma of Allotment letterFile: SALE AGREEMENT DRAFT Pg 17-32.pdf5 Feb 2018
Proforma of Allotment letterFile: ALLOTMENT LETTER DRAFT.pdf5 Feb 2018

How this compares with Thane

100%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MUMBRA LANDMARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AMRUT NAGAR, MUMBRA7,600+ in Thane

2 kmMUMBRA LANDMARKCompleted 35Lapsed / revoked 21Other 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 93 registered projects within 2 km.

Builder: JYOTI INDUSTRIES

JYOTI INDUSTRIES has 1 registration on MahaRERA, including MUMBRA LANDMARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that MUMBRA LANDMARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MUMBRA LANDMARK is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MUMBRA LANDMARK?

The registered promoter entity is JYOTI INDUSTRIES, a partnership as per the filing. Its GSTIN 27AABFJ0061D1ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MUMBRA LANDMARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MUMBRA LANDMARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MUMBRA LANDMARK?

The professionals named in the filing: Architect: GODBOLE MUKADAM & ASSOCIATES; Engineer: Yateesh Tare; Chartered Accountant: Shamim Esmail Shaikh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MUMBRA LANDMARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MUMBRA LANDMARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MUMBRA LANDMARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.