Home / Browse projects / Mumbai Suburban, Maharashtra / Mulund Ravi Kailash
Mulund Ravi Kailash
By M PATANKAR BUILD CONS PRIVATE LIMITED
RG-MH-27059 · RERA P51800009931 · Last updated on MahaRERA portal: 16 Oct 2020
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 54 months past the filed date
- 14 complaints at MahaRERA
- Completion date moved by 30 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mulund Ravi Kailash is a Others project by M PATANKAR BUILD CONS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009931 on 22 Aug 2017. Possession was promised by 30 Apr 2022 and is now 54 months past that date. The completion date has moved by 30 months from the original filing. 14 complaints are on record with the regulator.
At a glance
Project
- NameMulund Ravi Kailash
- TypeOthers
- Location
- Navghar Road
- Tata Colony Junction
- Kurla
- Mumbai Suburban
- 400081
- Pincode400081
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800009931
- ReraGenie IDRG-MH-27059
Builder
- NameM PATANKAR BUILD CONS PRIVATE LIMITED
- Entity typeCompany
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Aug 2017
- Promised completion30 Apr 2022
- Revised completionRevised to 30 Apr 2022 (originally 31 Oct 2019)
- Buildings1 building record
- Documents filed36 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Mulund Ravi Kailash | NA | 18 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 Oct 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.
Mulund Ravi Kailash: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
Progress on shared amenities15
As on 16 Oct 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed56
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mulund Ravi Kailash CHS Ltd. | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NIRMITY ARCHITECTS |
| Partner | Role in project |
|---|---|
| M PATANKAR BUILD CONS PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We had already obtained part OC for the project and completed 85% of the construction work and are hopeful that once we receive project extension of only six months, we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects.
Reason as filed by the promoterThe work has got delayed because of the implication of GST rules, which made the billing and accounts procedure slower because of the lack of proper understanding, thus affecting the work flow. Addition to this, demonetisation have slowed the payment resulting in the delay of work. Further, there was also a shortage of the material and labour in the project vicinity area. Thus, we request you to kindly grant us the extension for a period of 9 months. Also, we hereby declare that, the work won’t be delayed thereafter and we ensure to provide the possession within the revised date of completion
Complaints filed with MahaRERA14
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000055627 | VIJAY FULE | MANOJ PATANKAR | 02/08/2018 |
| CC006000000055630 | BALKRISHNA NARAYAN NADKARNI | MANOJ PATANKAR | 02/08/2018 |
| CC006000000055640 | SHANTI AMARPAL SINGH | MANOJ PATANKAR | 03/08/2018 |
| CC006000000194440 | M Patankar Buildcon Pvt Ltd through its Director Mr Manoj Patankar | Mr Mehul Parekh & Mrs Yogini Parekh | 17/10/2020 |
| CC006000000196052 | M/s. M Patankar Buildcon Private Limited through its director Mr. Manoj Manohar Patankar | Mr. Nikhil Nandkumar Prabhu & Mrs.Niyati Nandkumar Prabhu | 11/03/2021 |
| CC006000000196055 | M/s. M Patankar Buildcon Private Limited through its director Mr. Manoj Manohar Patankar | Mr. Mahendra Mohan Kamat | 11/03/2021 |
| CC006000000196056 | M/s. M Patankar Buildcon Private Limited through its director Mr. Manoj Manohar Patankar | Mr. Atikurahman Kittur | 11/03/2021 |
| CC006000000196057 | M/s. M Patankar Buildcon Private Limited through its director Mr. Manoj Manohar Patankar | Mrs/Ms Hemla Karthika | 11/03/2021 |
| CC006000000196058 | M/s. M Patankar Buildcon Private Limited through its director Mr. Manoj Manohar Patankar | Mr. Maxwel Crasta | 11/03/2021 |
| CC006000000196669 | Nikhil Nandkumar Prabhu | Manoj Patankar | 07/04/2021 |
| CC006000000196708 | Mahendra Kamat | Manoj Patankar | 14/04/2021 |
| CC006000000209629 | Maxwel Felix Crasta | M/s. M Patankar Buldcon Pvt Ltd | 06/01/2022 |
| CC006000000209630 | Hemla Karthika | M/s M Patankar Buildcon Private Limited | 06/01/2022 |
| CC006000000209631 | Atikurahman Kittur | M/s M Patankar Buildcon Private Limited | 06/01/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Oct 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Oct 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 28 May 2020
Documents filed36
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: AMENDED PLAN.pdf | 16 Oct 2020 |
| Building Plan Approval (IOD)File: AMENDED PLAN.pdf | 16 Oct 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: 1396 FurtherCC 15-06-2019.pdf | 16 Oct 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MULUND RAVI KAILASH_compressed.pdf | 12 Oct 2020 |
| Certificates of CA (Form 3)File: Form 3 mulund ravi kailash_compressed.pdf | 12 Oct 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2226527-OC-signed.pdf | 28 May 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Mulund Ravi Kailash.pdf | 8 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Mulund Ravi Kailash_compressed.pdf | 30 Jul 2019 |
| Certificates of CA (Form 5)File: Form 5.pdf | 1 Jul 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 mulund ravi kailash.pdf | 3 Jun 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: M patankar form 2-compressed.pdf | 19 Jan 2019 |
| Certificates of CA (Form 3)File: M patankar form 3.pdf | 19 Jan 2019 |
| Certificates of CA (Form 3)File: Form 3 - 8th Jan 2019.pdf | 9 Jan 2019 |
| Building plan approvalFile: IOD.pdf | 30 Jul 2017 |
| Layout approvalFile: p06.pdf | 30 Jul 2017 |
| Layout approvalFile: p02.pdf | 30 Jul 2017 |
| Layout approvalFile: p03.pdf | 30 Jul 2017 |
| Layout approvalFile: p04.pdf | 30 Jul 2017 |
| Layout approvalFile: p05.pdf | 30 Jul 2017 |
| Layout approvalFile: p01.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: title clear certificate-min.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: p01.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: p02.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: p03.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: p04.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: p05.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: p06.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: IOD.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: FORM B DECLARATION0001.PDF | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.PDF | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eNGINEER CERTIFICATE.PDF | 30 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate Form.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Flat sale Agreement rera act.pdf | 30 Jul 2017 |
| PAN CardFile: PAN CARD.PDF | 29 Jul 2017 |
| Details of encumbrancesFile: 712.pdf | 29 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 29 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 36 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Mulund Ravi Kailash on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Tata Colony Junction6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 280 registered projects within 2 km.
Ekvira and Saishakti
Magnaacasa Infrastructures and Realtors Pr
SENROOFS PHASE - III
PIONEER HOUSING
THE ALTEZZA
M/s. VIPL Varasiddhi Infra Project LLP
SUPREMO PHASE I SALVIA D WING
K V BUILDHOME LLP
SUPREMO PHASE II, WING C known as SAKURA
K V BUILDHOME LLP
Aveza Phase 2
Tata Housing Development Company Limited
See every Mumbai Suburban project, with the district possession charts
Builder: M PATANKAR BUILD CONS PRIVATE LIMITED
M PATANKAR BUILD CONS PRIVATE LIMITED has 2 registrations on MahaRERA, including Mulund Ravi Kailash and Mulund Ravi Kailash 16th, 17th, 18th floor. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Mulund Ravi Kailash shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Mulund Ravi Kailash is delayed beyond 30 Apr 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mulund Ravi Kailash?
The registered promoter entity is M PATANKAR BUILD CONS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mulund Ravi Kailash?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Mulund Ravi Kailash?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Mulund Ravi Kailash?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mulund Ravi Kailash?
The professionals named in the filing: Architect: NIRMITY ARCHITECTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mulund Ravi Kailash?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.