Home / Browse projects / Mumbai Suburban, Maharashtra / MUBARAK MANZIL CHSL

Registered No litigation declared Residential / Group Housing project

MUBARAK MANZIL CHSL

By RAJ BUILDERS

RG-MH-29554 · RERA P51800029665 · Last updated on MahaRERA portal: 21 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 25 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedmoved 25 months from the original
11 of 11Construction stages doneevery applicable stage filed complete
25 of 71Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

MUBARAK MANZIL CHSL is a Residential / Group Housing project by RAJ BUILDERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029665 on 14 Jun 2021. Possession is promised by 31 Oct 2026. The completion date has moved by 25 months from the original filing. 46 of the 71 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameMUBARAK MANZIL CHSL
  • TypeResidential / Group Housing
  • Location
    • SAIFEE PARK CHURCH ROAD
    • MAROL ANDHERI EAST
    • Andheri
    • Mumbai Suburban
    • 400059
  • Pincode400059
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800029665
  • ReraGenie IDRG-MH-29554

Builder

  • NameRAJ BUILDERS
  • Entity typePartnership
  • PartnersSAIFUDDIN S RAMPURWALA, TAHA SAIFUDDIN RAMPURWALA
  • Other registrations5 more →
  • Completed3 of 6
  • Declared earlier projects2 →

Key dates

this monthRegisteredJun 2021First promiseSep 2024Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Jun 2021
  • Promised completion31 Oct 2026
  • Revised completionRevised to 31 Oct 2026 (originally 30 Sep 2024)
  • Buildings1 building record
  • Documents filed54 files

Current status

65%46 of 71 units booked
100.0%Work done, per cost certificate

Figures as on 21 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MUBARAK MANZIL CHSLNA141471071

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

MUBARAK MANZIL CHSL: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Closed/Covered1
Open Space10

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,883 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
MUBARAK MANZIL CO-OPERATIVE HOUSING SOCIETY LTDAndheriMumbai Suburban

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI5591.91
Proposed, not sanctioned5,591 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAROL MAROSHI ROAD ANDHER EAST MUMBAI 59
Estimated costRs 24.00 cr
Cost incurredRs 24.00 cr
Work done100.0%
BuildingWingEstimatedIncurred
MUBARAK MANZIL CHSLNARs 24.00 crRs 24.00 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHIJIT A MEHTA
EngineerABHIJIT V PHATARPEKAR
EngineerHUZEFA MADRASWALA
Chartered AccountantBANWAT & CO
Chartered AccountantMULRAJ D GALA
PartnerRole in project
RAJ BUILDERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800024933Sep 2024 → Sep 2025

Reason as filed by the promoterDear Sir/Madam, Kindly allow us the extention. The details regarding delay and current status of project is attached herewith. The project is 98% complete and in the process of obtaining occupancy certificate.

EA16052620990Sep 2024 → Oct 2026

Reason as filed by the promoterDear Sir, The OC is being received on 03/11/2025, however we need extention beyond OC and current date as there some correction some project information required. Kindly allow us the extention, so as to allow us correction and filing of completion of application.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Apr 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2026

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Engineers Certificate Form 2A 2025-26.pdf21 Aug 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 Signed.pdf13 Aug 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 Signed.pdf13 Aug 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 Signed.pdf13 Aug 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 Signed.pdf13 Aug 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 Signed.pdf13 Aug 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 Signed.pdf13 Aug 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 Mubarak Manzil Signed.pdf13 Aug 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 Mubarak Manzil Signed.pdf13 Aug 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 Mubarak Manzil Signed.pdf13 Aug 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 Signed.pdf16 May 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 Signed.pdf16 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 Signed.pdf16 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 Signed.pdf16 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 Mubarak Manzil Signed.pdf16 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 Mubarak Manzil Signed.pdf16 May 2026
Form 5 (FY 2025-2026)File: Form 5 FY 2025-26 Mubarak Manzil SIGNED.pdf15 May 2026
Form 2A (FY 2024-2025)File: EC 2A.pdf22 Apr 2026
Form 2A (FY 2021-2022)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) .pdf27 Mar 2026
Form 2A (FY 2022-2023)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf27 Mar 2026
Form 2A (FY 2023-2024)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf27 Mar 2026
Form 5 (FY 2024-2025)File: form5 2425.pdf13 Mar 2026
Form 5 (FY 2021-2022)File: Form 2A 2022.pdf23 Feb 2026
Form 5 (FY 2022-2023)File: Form 5 2022-23 Sign.pdf23 Feb 2026
Form 5 (FY 2023-2024)File: Form 5 2023-24 Sign.pdf23 Feb 2026
Declaration about Commencement CertificateFile: RERA MUBARAK.pdf5 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22 Sign.pdf5 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23 Sign.pdf5 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24 Sign.pdf5 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3_compressed.pdf30 Oct 2024
Declaration in FORM BFile: Affidavit FORM B.pdf29 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1.pdf29 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2.pdf29 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: FULL CC_merged.pdf29 Oct 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf29 Oct 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD 1.pdf29 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2022.pdf21 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023.pdf21 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2024.pdf21 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: 2395482_FurtherCC_signed.pdf5 Oct 2023
Copy of the legal title reportFile: Title Certificate A.pdf3 Jun 2021
Copy of the legal title reportFile: UPLOADED FLOW OF THE TITLE.pdf3 Jun 2021
Copy of the legal title reportFile: UPLOADED TITLE REPORT.pdf3 Jun 2021
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf20 May 2021
PAN CardFile: Scan May 17, 2021.pdf17 May 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Certificate - 12-05-2021 (1).pdf13 May 2021
Commencement Certificates / NA Order for plotted developmentFile: 2276144_FirstCC_signed.pdf3 May 2021
Layout approvalFile: MAROL LAYOUT PLAN.pdf28 Apr 2021
Copy of Layout Approval (in case of layout)File: MAROL LAYOUT PLAN.pdf28 Apr 2021
Declaration in FORM BFile: RERA FORM B.pdf28 Apr 2021
Proforma of Allotment letterFile: SALE AGREEMENT DRAFT.pdf28 Apr 2021
Building plan approvalFile: IOD.pdf27 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: IOD.pdf27 Apr 2021
Details of encumbrancesFile: NON-ENCUMBRANCE CERTIFICATE.pdf9 Mar 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
ALTAHERISAIFEE PARK CHURCH ROAD MAROL ANDHERI EAST MUMBAI-40005965CompletedDec 2016Dec 2016

How this compares with Mumbai Suburban

65%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 25 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MUBARAK MANZIL CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAROL ANDHERI EAST6,700+ in Mumbai Suburban

2 kmMUBARAK MANZIL CHSLCompleted 113Lapsed / revoked 56Other 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 237 registered projects within 2 km.

Builder: RAJ BUILDERS

RAJ BUILDERS has 6 registrations on MahaRERA, including SAFAVI CHS LTD and RAJ HEIGHTS. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if MUBARAK MANZIL CHSL is delayed beyond 31 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MUBARAK MANZIL CHSL?

The registered promoter entity is RAJ BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MUBARAK MANZIL CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MUBARAK MANZIL CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MUBARAK MANZIL CHSL?

The professionals named in the filing: Architect: ABHIJIT A MEHTA; Engineer: ABHIJIT V PHATARPEKAR; Engineer: HUZEFA MADRASWALA; Chartered Accountant: BANWAT & CO; Chartered Accountant: MULRAJ D GALA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MUBARAK MANZIL CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MUBARAK MANZIL CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MUBARAK MANZIL CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.