ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDING

Registered No litigation declared Residential / Group Housing project

MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDING

By THE UNITED GROUP OF BUILDERS AND DEVELOPERS

RG-MH-30834 · RERA P52000079172 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 4 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Staircases, 90%
20 of 36Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDING is a Residential / Group Housing project by THE UNITED GROUP OF BUILDERS AND DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000079172 on 12 Feb 2025. Possession is promised by 31 Dec 2027. 16 of the 36 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameMRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDING
  • TypeResidential / Group Housing
  • Location
    • NA
    • Ambeghar
    • Pen
    • Raigarh
    • 402107
  • Pincode402107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000079172
  • ReraGenie IDRG-MH-30834

Builder

  • NameTHE UNITED GROUP OF BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersMAHESH JANARDHAN ATHAWALE, DHARMENDRA JANARDAN POTE, JAYANT SHRIKANT MHATRE, UDAY VISHNU SATHE, SACHIN KAMLAKANT SHRINGARPURE
  • Other registrations4 more →
  • Completed4 of 5
  • Declared earlier projects7 →

Key dates

this monthRegisteredFeb 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Feb 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed55 files

Current status

44%16 of 36 units booked
54.8%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D TYPENA5536036

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

D TYPE: 47% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,430 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Oct 2025

Approvals and building plan

Sanctioning authorityTAHSILDAR DISTRICT RAIGAD
Permissible FSI1326.42
Proposed, not sanctioned1,326 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHASHINIL, OPP. ST STAND, GROUND FLOOR, NEAR URDU SHALA, CHINCHPADA, PEN - 402107
Estimated costRs 4.21 cr
Cost incurredRs 2.31 cr
Work done54.75%
BuildingWingEstimatedIncurred
D TYPENARs 3.71 crRs 1.86 cr
-NARs 50.00 lakhRs 45.00 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHINAY JOGI
EngineerASSOCIATED CONSULTING ENGINEERS
EngineerMAHESH J ATHAVALE
Chartered AccountantCA RUPESH JOSHI
Chartered AccountantAMIT DHAVALE & ASSOCIATES LLP
PartnerRole in project
THE UNITED GROUP OF BUILDERS AND DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Dec 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Dec 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1_ MARCH 26_ RAJESHREE D TYPE BUILDING.pdf24 Apr 2026
Withdrawal Update Form 2File: FORM 2_ MARCH 26_ RAJESHREE D TYPE BUILDING.pdf24 Apr 2026
Withdrawal Update Form 3File: FORM 3_ MARCH 26_ RAJESHREE D TYPE BULDG_compressed.pdf24 Apr 2026
Form 2A (FY 2025-2026)File: FORM 2A_ MARCH 26_ RAJESSHREE BUILDING D TYPE.pdf24 Apr 2026
Withdrawal Update Form 1File: FORM 1_ DEC 25_ RAGESHREE D TYPE BULDG.pdf6 Feb 2026
Withdrawal Update Form 2File: FORM 2_ DEC 25_ RAGESHREE D TYPE BULDG.pdf6 Feb 2026
Withdrawal Update Form 3File: FORM 3_ DEC 25_ RAGESHREE D TYPE BULDG.pdf6 Feb 2026
Form 5 (FY 2024-2025)File: FORM 5_UNITED GROUP_24-25.pdf27 Nov 2025
Withdrawal Update Form 1File: FORM 1_ SEP 25_ RAGESHREE D TYPE BULDG (1).pdf11 Nov 2025
Withdrawal Update Form 2File: FORM 2_ SEP 25_ REGESHREE D TYPE BULDG.pdf11 Nov 2025
Withdrawal Update Form 3File: FORM 3_ SEP 25_ REGESHREE D TYPE BULDG.pdf11 Nov 2025
Form 1File: FORM 1_ JUNE 25_ RAGESHREE D TYPE BULDG.pdf11 Aug 2025
Form 2File: FORM 2_ JUNE 25_ RAGESHREE D TYPE BULDG.pdf11 Aug 2025
Form 3File: FORM 3_ JUNE 25_ RAGESHREE D TYPE BUILDING.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_JUNE 25 RAGESHREE,D-TYPE BUILDING.pdf11 Aug 2025
Form 2A (FY 2024-2025)File: FORM 2A_ MARCH 2025.pdf11 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_ MARCH 25.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_ MARCH 25_merged_compressed.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_ MARCH 25.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ MARCH 2025.pdf18 Apr 2025
Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement.pdf3 Feb 2025
Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale.pdf3 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2_merged.pdf15 Jan 2025
Building plan approvalFile: PLAN FINAL.pdf13 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN FINAL.pdf13 Jan 2025
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf12 Jan 2025
Other - TechnicalFile: 1 Other - Technical (1).pdf10 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 1 Declaration about all RERA Designated Bank Accounts (Format A) (1).pdf30 Dec 2024
Copy of the legal title reportFile: ilovepdf_merged.pdf28 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf28 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf28 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: 2 Commencement Certificates _ NA Order for plotted development.pdf28 Dec 2024
Declaration about Commencement CertificateFile: CC DECLARATION.pdf28 Dec 2024
Layout approvalFile: 5 Copy of Layout Approval (in case of layout).pdf5 Dec 2024
Building plan approvalFile: 6 Building Plan Approval.pdf5 Dec 2024
PAN CardFile: 1 PAN CARD.pdf5 Dec 2024
Details of encumbrances concerned to FinanceFile: 3 a Details of encumbrances concerned to Finance.pdf5 Dec 2024
Details of encumbrances concerned to FinanceFile: 4 b Details of encumbrances concerned to Legal.pdf5 Dec 2024
Copy of Layout Approval (in case of layout)File: 5 Copy of Layout Approval (in case of layout).pdf5 Dec 2024
Declaration in FORM BFile: 9 Declaration in FORM B.pdf5 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: 7 Commencement Certificates NA Order for plotted development.PDF5 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: 6 Building Plan Approval.pdf5 Dec 2024
Other - LegalFile: 26 Other - Legal- Partnership Deed_compressed.pdf5 Dec 2024
Other - LegalFile: 24 Other - Legal- Sale Deed_compressed_compressed.pdf5 Dec 2024
Other - LegalFile: 25 Other - Legal- 7_12.pdf5 Dec 2024
CERSAI detailsFile: 12 CERSAI details.pdf5 Dec 2024
Deviation Report with respect to Allotment letterFile: 20 Deviation Report with respect to Allotment letter.pdf5 Dec 2024
Details of encumbrances concerned to LegalFile: 3 a Details of encumbrances concerned to Finance.pdf5 Dec 2024
Details of encumbrances concerned to LegalFile: 4 b Details of encumbrances concerned to Legal.pdf5 Dec 2024
Other - FinanceFile: 27 Other - Finance - Partnership Deed_compressed.pdf5 Dec 2024
Other - TechnicalFile: 27 Other - Technical Annexure A.pdf5 Dec 2024
Other - TechnicalFile: 28 Other - Technical - Partnership Deed_compressed.pdf5 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 15 Disclosure of Interest in Other Real Estate Organizations.pdf5 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: 19 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B).5 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: 13 Disclosure for secured_unsecured finance availed for the project.pdf5 Dec 2024

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
ARUMP52000025472R.P.Nagar Ramwadi, RaigarhJun 2020CompletedDec 2024Dec 2024
Mrudagandhar Phase 2 Devashree E type BuildingP52000028928Ambeghar, RaigarhApr 2021CompletedMar 2024Mar 2024
Mrudagandhar Phase 1P52000000998Ambeghar, RaigarhJul 2017CompletedMar 2022Mar 2022
United Galaxy Phase 4P52000001710Pen (M Cl), RaigarhJul 2017CompletedMar 2019Mar 2019

How this compares with Raigarh

44%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NA5,900+ in Raigarh

2 kmMRUDAGANDHAR PHASE 3 RAGCompleted 5Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: THE UNITED GROUP OF BUILDERS AND DEVELOPERS

The United Group Of Builders And Developers has 5 registrations on MahaRERA, including United Galaxy Phase 4 and Mrudagandhar Phase 1. Its filings disclose 7 earlier MahaRERA projects: declares 7 of 7 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDING is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDING?

The registered promoter entity is THE UNITED GROUP OF BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDING?

The professionals named in the filing: Architect: ABHINAY JOGI; Engineer: ASSOCIATED CONSULTING ENGINEERS; Engineer: MAHESH J ATHAVALE; Chartered Accountant: CA RUPESH JOSHI; Chartered Accountant: AMIT DHAVALE & ASSOCIATES LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MRUDAGANDHAR PHASE 3 RAGESHREE D TYPE BUILDI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.