Home / Browse projects / Palghar, Maharashtra / MRIDA HOMES

Registered No litigation declared Residential / Group Housing project

MRIDA HOMES

By FIN WHALES LIFESTYLE LLP

RG-MH-28152 · RERA P99000026476 · Last updated on MahaRERA portal: 31 Dec 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedno revision filed
21 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 123 documents Report an error

MRIDA HOMES is a Residential / Group Housing project by FIN WHALES LIFESTYLE LLP in Palghar, Maharashtra, registered with MahaRERA as P99000026476 on 25 Sep 2020. Possession is promised by 30 Jun 2027.

At a glance

Project

  • NameMRIDA HOMES
  • TypeResidential / Group Housing
  • Location
    • NEAR NARANGI RAILWAY PHATAK
    • VIRAR EAST
    • Vasai
    • Palghar
    • 401305
  • Pincode401305
  • RERA no.P99000026476
  • ReraGenie IDRG-MH-28152

Builder

  • NameFIN WHALES LIFESTYLE LLP
  • Entity typePartnership
  • GSTIN27AAGFF4173K1Z6
  • PartnersANKUR DEVDAS BHOGESARA, SWAPNIL JITENDRA SHAH, CHETAN ASHOK LONKAR, PRATIK CHANDRAKANT THAKUR, MAHESHWAR HASHA PATIL

Key dates

this monthRegisteredSep 2020PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Sep 2020
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed123 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HASHA HEIGHTSNA160000
KUNTI HEIGHTSNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 31 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

21 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

HASHA HEIGHTS91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
KUNTI HEIGHTS100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 31 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes0%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed118

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots118
Closed/Covered25
Open Space93
BuildingClosed/CoveredOpen SpaceTotal
HASHA HEIGHTS24024
KUNTI HEIGHTS19394

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,950 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Sep 2024
LandownerVillageDistrict
MAHESHWAR HASHA PATIL & OTHERSVasai-Virar City (M Corp)Palghar
MAHESHWAR HASHA PATILVasai-Virar City (M Corp)Palghar
RANJAN HASHA PATILVasai-Virar City (M Corp)Palghar

Approvals and building plan

Permissible FSI9648.52
Proposed, not sanctioned9,649 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGR FLR SURVEY NO 265 MHATRE WADI NEAR VIRAR RAILWAY STATION VIRAR WEST 401303

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUMESH KEKRE KEKRE
EngineerJAY SHREE KRISHNA
Chartered AccountantSANKHALA AND CO
Chartered AccountantRAVEENA VIVEK SANKHALA
PartnerRole in project
FIN WHALES LIFESTYLE LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Jun 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 Apr 2024

Documents filed123

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: form 1.pdf31 Dec 2025
Form 2File: form 2.pdf31 Dec 2025
Form 3File: form 3.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf31 Dec 2025
Form 1File: form 1.pdf31 Dec 2025
Form 2File: form 2.pdf31 Dec 2025
Form 3File: form 3.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf31 Dec 2025
Form 1File: form 1.pdf31 Dec 2025
Form 2File: form 2.pdf31 Dec 2025
Form 3File: form 3.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf31 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 Fy24-25.pdf26 Sep 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf18 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KUNTI FORM 1.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf16 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 23-24 sgned.pdf15 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf13 Oct 2024
Form 5 (FY 2023-2024)1 Oct 2024
Form 1File: FORM 1 .pdf26 Sep 2024
Form 2File: FORM 2 .pdf26 Sep 2024
Form 3File: FORM 3.pdf26 Sep 2024
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf26 Sep 2024
Layout approvalFile: 5692 rdp sht_compressed (2)-1_rotated (1)_compressed.pdf7 Jul 2024
Building plan approvalFile: 5692 rdp sht_compressed (3)-2_compressed.pdf7 Jul 2024
Building plan approvalFile: 5692 rdp sht_compressed (3)-3_compressed.pdf7 Jul 2024
Building plan approvalFile: 5692 rdp sht_compressed (3)-4_compressed.pdf7 Jul 2024
Copy of Layout Approval (in case of layout)File: 5692 rdp sht_compressed (2)-1_rotated (1)_compressed.pdf7 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 5692 rdp sht_compressed (3)-2_compressed.pdf7 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 5692 rdp sht_compressed (3)-3_compressed.pdf7 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 5692 rdp sht_compressed (3)-4_compressed.pdf7 Jul 2024
Disclosure of sold/ booked inventoryFile: sold unsold.pdf2 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3_compressed.pdf2 Jul 2024
Layout approvalFile: 1_compressed.pdf1 Jul 2024
Building plan approvalFile: 2_compressed.pdf1 Jul 2024
Building plan approvalFile: 3_compressed.pdf1 Jul 2024
Building plan approvalFile: 4 kunti_new1_compressed.pdf1 Jul 2024
Building plan approvalFile: 5 kunti_new2_compressed.pdf1 Jul 2024
Copy of Layout Approval (in case of layout)File: 1_compressed.pdf1 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 2_compressed.pdf1 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 3_compressed.pdf1 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 4 kunti_new1_compressed.pdf1 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 5 kunti_new2_compressed.pdf1 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: First CC building no 1.pdf1 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: Second CC building no 1.pdf1 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: third CC building no 2_compressed.pdf1 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf1 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf1 Jul 2024
Disclosure for secured/unsecured finance availed for the projectFile: disclosure of interest.pdf1 Jul 2024
Disclosure for secured/unsecured finance availed for the projectFile: disclosure of interest 2.pdf1 Jul 2024
Disclosure for secured/unsecured finance availed for the projectFile: disclosure of interest 2.pdf1 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf1 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest.pdf1 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf7 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf25 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf25 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf12 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf12 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 finwhales.pdf28 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf29 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf29 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 21-22.pdf29 Jun 2023
Details of encumbrances concerned to FinanceFile: legal encumbrance.pdf19 May 2023
Details of encumbrances concerned to LegalFile: legal encumbrance.pdf19 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format A bank accont.pdf19 May 2023
Deviation Report with respect to Allotment letterFile: no devaition.pdf19 May 2023
Deviation Report with respect to model copy of AgreementFile: no devaition.pdf19 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf29 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2A.pdf29 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf29 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH CERT.pdf28 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE_compressed.pdf28 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT_compressed.pdf8 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG_compressed.pdf8 Aug 2022

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MRIDA HOMES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIRAR EAST3,200+ in Palghar

Builder: FIN WHALES LIFESTYLE LLP

FIN WHALES LIFESTYLE LLP has 1 registration on MahaRERA, including MRIDA HOMES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if MRIDA HOMES is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MRIDA HOMES?

The registered promoter entity is FIN WHALES LIFESTYLE LLP, a partnership as per the filing. Its GSTIN 27AAGFF4173K1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MRIDA HOMES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MRIDA HOMES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MRIDA HOMES?

The professionals named in the filing: Architect: UMESH KEKRE KEKRE; Engineer: JAY SHREE KRISHNA; Chartered Accountant: SANKHALA AND CO; Chartered Accountant: RAVEENA VIVEK SANKHALA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MRIDA HOMES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MRIDA HOMES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MRIDA HOMES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.