Home / Browse projects / Thane, Maharashtra / MOTI MAHAL

Registration lapsed No litigation declared Mixed project

MOTI MAHAL

By MAJESTIC CONSTRUCTION

RG-MH-02981 · RERA P51700020436 · Last updated on MahaRERA portal: 12 Jul 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 58 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2021Possession promised58 months past this date
6 of 11Construction stages doneacross 2 buildings; furthest along: Staircases, 90%
0Complaints at MahaRERAon this registration
Jump to the 23 documents Report an error

MOTI MAHAL is a Mixed project by MAJESTIC CONSTRUCTION in Thane, Maharashtra, registered with MahaRERA as P51700020436 on 10 Apr 2019. Possession was promised by 30 Dec 2021 and is now 58 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameMOTI MAHAL
  • TypeMixed
  • Location
    • THANA ROAD
    • CHUDI MOHALLA
    • Bhiwandi (M Corp.)
    • Bhiwandi
    • Thane
    • 421302
  • Pincode421302
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700020436
  • ReraGenie IDRG-MH-02981

Builder

  • NameMAJESTIC CONSTRUCTION
  • Entity typeOthers
  • Named personSHAHNAWAZ FAROOQUE AHMED MOMIN

Key dates

58 months past promisethis monthRegisteredApr 2019First promiseDec 2020Revised toDec 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 Apr 2019
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 30 Dec 2020)
  • Buildings1 building record
  • Documents filed23 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MOTI MAHALNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 12 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.

MOTI MAHAL75%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 12 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes85%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Open Space5

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area702 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
MOTI MASJIDBhiwandi (M Corp.)Thane

Approvals and building plan

Permissible FSI2132.57
Proposed, not sanctioned1,933 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMUMBAI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJALAL ANSARI AND ASSOCIATES
EngineerSADIQUE ZAKIR HUSAIN SHAIKH
Chartered AccountantMOHD BILAL CHAUHAN
PartnerRole in project
MAJESTIC CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700010093Dec 2020 → Dec 2021

Reason as filed by the promoterCONSTRUCTION SCHEDULE WAS DELAYED DUE TO OUTBREAK OF COVID-19 PANDEMIC

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Apr 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed23

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: DISCOLURE OF SOLD-UNSOLD.pdf12 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A_2019-20-1-8.pdf10 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A_2019-20-9-16.pdf10 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A_2020-21-1-8.pdf10 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A_2020-21-9-16.pdf10 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5_Majestic_19-20.pdf10 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Certificate No 1.pdf7 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Certificate No 2.pdf7 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Certificate No 3.pdf7 Jul 2021
Declaration about Commencement CertificateFile: Format-D.pdf6 Jul 2021
Building plan approval or NA orderFile: Plan Approval.pdf7 Apr 2019
Layout approvalFile: Layout.pdf7 Apr 2019
PAN CardFile: PAN.pdf7 Apr 2019
Copy of the legal title reportFile: Title Report.pdf7 Apr 2019
Details of encumbrancesFile: Form B.pdf7 Apr 2019
Copy of Layout Approval (in case of layout)File: Layout.pdf7 Apr 2019
Building Plan Approval (IOD)File: Plan Approval.pdf7 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf7 Apr 2019
Declaration in FORM BFile: Form B.pdf7 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf7 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf7 Apr 2019
Certificates of CA (Form 3)File: Form 3.pdf7 Apr 2019
Proforma of Allotment letterFile: Allotment and Agreement.pdf7 Apr 2019

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MOTI MAHAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHUDI MOHALLA7,600+ in Thane

2 kmMOTI MAHALCompleted 5Lapsed / revoked 8Other 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 39 registered projects within 2 km.

Builder: MAJESTIC CONSTRUCTION

MAJESTIC CONSTRUCTION has 1 registration on MahaRERA, including MOTI MAHAL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that MOTI MAHAL shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MOTI MAHAL is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MOTI MAHAL?

The registered promoter entity is MAJESTIC CONSTRUCTION, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MOTI MAHAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MOTI MAHAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MOTI MAHAL?

The professionals named in the filing: Architect: JALAL ANSARI AND ASSOCIATES; Engineer: SADIQUE ZAKIR HUSAIN SHAIKH; Chartered Accountant: MOHD BILAL CHAUHAN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MOTI MAHAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MOTI MAHAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MOTI MAHAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.