ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Mohan Willows Commercial

Completed No litigation declared Commercial project

Mohan Willows Commercial

By MOHAN LIFESPACES LLP

RG-MH-76844 · RERA P51700024089 · Last updated on MahaRERA portal: 3 Nov 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 23 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2022Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 21 documents Report an error

Mohan Willows Commercial is a Commercial project by MOHAN LIFESPACES LLP in Thane, Maharashtra, registered with MahaRERA as P51700024089 on 20 Jan 2020. The registration is recorded completed; possession was promised by 30 Mar 2022.

At a glance

Project

  • NameMohan Willows Commercial
  • TypeCommercial
  • Location
    • BHOSALE NAGAR
    • SHIRGAON
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700024089
  • ReraGenie IDRG-MH-76844

Builder

  • NameMOHAN LIFESPACES LLP
  • Entity typePartnership
  • GSTIN27AASFM8768R1ZS
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersMAMTA AMAR BHATIA, DEEPAK GOBIND MANCHANDYA, DHIRAJ HARI BHATIA, GEETU JEETENDER LALCHANDANI, KUMAR GOBINDRAM VIDHANI, LAKHI RAVI SHRINGI, MANISH PARSRAM BAHRANI, RAJESH CHANDIRAM KISHINSINGHANI, SUNIL MOHANDAS HARCHANDANI, AJIT RAMESHLAL GANDHI, HITESH NARI RAMCHANDANI, CHIRAG MANOHAR MANCHANDYA
  • Other registrations23 more →
  • Completed17 of 24
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects22 →

Key dates

this monthRegisteredJan 2020PromisedMar 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on20 Jan 2020
  • Promised completion30 Mar 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed21 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MOHAN WILLOWS COMMERCIALNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Nov 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

MOHAN WILLOWS COMMERCIAL: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 Nov 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area755 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI434.31
Proposed, not sanctioned434 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKALYAN

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSatish Oak ARCHITECTS Inc.
EngineerVinayak Chopdekar & Associates
Chartered AccountantAmit Janyani
PartnerRole in project
MOHAN LIFESPACES LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Dec 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Sep 2021

Documents filed21

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Willows Commercial.pdf3 Nov 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Formation.pdf20 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Willows Commercial.pdf28 Sep 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf21 Sep 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate_opt.pdf6 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Mohan Willows Commercial.pdf22 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Mohan Willows Commercial.pdf28 Sep 2020
Details of encumbrancesFile: Mohan Willows Commercial Encumbrances.pdf14 Jan 2020
Declaration in FORM BFile: Form B Mohan Willows Commercial.pdf2 Jan 2020
Copy of the legal title reportFile: Title Report.pdf18 Dec 2019
Proforma of Allotment letterFile: SaleAgreement.pdf18 Dec 2019
Layout approvalFile: Layout Plan.pdf17 Dec 2019
Building plan approvalFile: Building Plan.pdf17 Dec 2019
PAN CardFile: PAN.pdf17 Dec 2019
Details of encumbrancesFile: Mohan Willows Commercial.pdf17 Dec 2019
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf17 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf17 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Cetificate.pdf17 Dec 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Dec 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Dec 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Dec 2019

Promoter's earlier projects22

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

21 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Mohan SkyvilleP51700003607Khadakpada, Thane10Aug 2017CompletedJun 2023Registered original: Jun 2019Late, Apr 2024
Mohan GreenwoodsBadlapur627-CompletedApr 2017Apr 2017
Mohan GalleriaAmbernath49-CompletedMar 2017Mar 2017
Mohan HighlandsBadlapur541-CompletedJan 2017Jan 2017
Mohan Suburbia SchoolAmbernath1-CompletedDec 2016Dec 2016
Mohan Suburbia Salisbury Phase IIAmbernath626-CompletedDec 2016Dec 2016
Mohan Palms IIIBadlapur619-CompletedDec 2016Dec 2016
Mohan Suburbia Oxford Phase IAmbernath617-CompletedDec 2014Dec 2014
Mohan Plaza IIWayle Nagar khadakpada Kalyan West24-CompletedDec 2013Dec 2013
Mohan Palms I/IIBadlapur766-CompletedDec 2013Dec 2013
Mohan ValleyGaneshwadi Badlapur West425-CompletedDec 2011Dec 2011
Mohan SrishtiKachore Patri Pull Kalyan East300-CompletedDec 2010Dec 2010
Mohan PrideWayle Nagar khadakpada Kalyan West440-CompletedDec 2009Dec 2009
Mohan PlazaWayle Nagar khadakpada Kalyan West60-CompletedDec 2009Dec 2009
Mohan HeightsBhiwandi Murbad Road Khadakpada Kalyan West270-CompletedDec 2007Dec 2007
Mohan ParadiseWayle Nagar khadakpada Kalyan West250-CompletedDec 2006Dec 2006
Mohan JyotShiv Mandir Road Ambernath East125-CompletedDec 2006Dec 2006
Mohan PuramNear Dr. Gautam Jatale Hospital Kansai Section Ambernath East450-CompletedDec 2005Dec 2005
Mohan RegencyAdarwadi Kalyan West450-CompletedDec 2003Dec 2003
Mohan ParkGodrej Hills Road Khadakpada Kalyan West330-CompletedDec 2002Dec 2002
Mohan GardenRameshwadi Badlapur Gaon Road Badlapur West150-CompletedDec 2002Dec 2002
Manav ParkRameshwadi Badlapur Gaon Road Badlapur West465-CompletedDec 2000Dec 2000

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mohan Willows Commercial on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHIRGAON7,600+ in Thane

2 kmMohan Willows CommercialCompleted 150Lapsed / revoked 56Other 95Dot size: filed unitsN

Filed coordinates, straight-line distance. 301 registered projects within 2 km.

Builder: MOHAN LIFESPACES LLP

MOHAN LIFESPACES LLP has 24 registrations on MahaRERA, including Mohan Areca and Mohan Suburbia IV. Its filings disclose 22 earlier MahaRERA projects: declares 21 of 22 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Mohan Willows Commercial is delayed beyond 30 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mohan Willows Commercial?

The registered promoter entity is MOHAN LIFESPACES LLP, a partnership as per the filing. Its GSTIN 27AASFM8768R1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mohan Willows Commercial?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mohan Willows Commercial?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mohan Willows Commercial?

The professionals named in the filing: Architect: Satish Oak ARCHITECTS Inc.; Engineer: Vinayak Chopdekar & Associates; Chartered Accountant: Amit Janyani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mohan Willows Commercial?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mohan Willows Commercial. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mohan Willows Commercial to a free account