MOHAN HEIGHTS PHASE-II

By BHAVANI ENTERPRISES

RG-MH-24928 · RERA P51700004772 · Last updated on MahaRERA portal: 20 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 81 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 81 months from the original
14 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 90%
41 of 99Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

MOHAN HEIGHTS PHASE-II is a Others project by BHAVANI ENTERPRISES in Thane, Maharashtra, registered with MahaRERA as P51700004772 on 9 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 81 months from the original filing. 58 of the 99 units on this registration are recorded sold or booked, and 14 of 33 construction stages are filed complete.

At a glance

Project

  • NameMOHAN HEIGHTS PHASE-II
  • TypeOthers
  • Location
    • TITWALA
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700004772
  • ReraGenie IDRG-MH-24928

Builder

  • NameBHAVANI ENTERPRISES
  • Entity typePartnership
  • PartnersDHIRAJ SUNDERLAL JAIN, DILIP MADANLAL JAIN, DHANSUKH DAYARAM THAKKAR
  • Other registrations5 more →
  • Completed3 of 6

Key dates

this monthRegisteredAug 2017First promiseMar 2020Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Mar 2020)
  • Buildings3 building records
  • Documents filed99 files

Current status

59%58 of 99 units booked
89.9%Work done, per cost certificate

Figures as on 20 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING CNA8716016
WING ANA8730535
WING BNA8748048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 20 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 90%.

WING C77%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
WING A79%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
WING B77%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 20 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes20%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes20%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,180 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 May 2025
LandownerVillageDistrict
PRABHAT DEVELOPERSKalyan-Dombivali (M Corp.)Thane

Approvals and building plan

Sanctioning authorityKALYAN DOMBIVLI MUNICIPAL CORPORATION
Permissible FSI2891.27
Proposed, not sanctioned2,091 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSUBHASH ROAD, DOMBIVLI WEST 421202
Estimated costRs 3.94 cr
Cost incurredRs 3.54 cr
Work done89.91%
BuildingWingEstimatedIncurred
WING ANARs 1.62 crRs 1.57 cr
WING BNARs 1.50 crRs 1.38 cr
WING CNARs 55.38 lakhRs 49.84 lakh
-NARs 26.74 lakhRs 9.36 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARC VIJAY PANDEY
EngineerKB CONSULTANTS PATEL
Chartered AccountantMAYUR K JAIN AND CO
Chartered AccountantANKIT PARAS JAIN AND CO
PartnerRole in project
BHAVANI ENTERPRISES-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019396Mar 2020 → Mar 2025

Reason as filed by the promoterAs per Attachmenbt

EXT51700010673Mar 2020 → Sep 2023

Reason as filed by the promoterWe, Bhavani Enterprises, have registered for our real estate project " MOHAN HEIGHTS PHASE II " bearing registration no P51700004772. The date of completion of the project was given as 31.03.2020 at the time of registration. An extension was applied under Section 7(1) till 31.03.2021 and the same was granted to us. The said date got extended till 30.09.2021 as per relief given under Covid-19 pandemic. However, we couldn’t complete said project within the stipulated period due to shortage of sand, inadequate labour supply and changes in policies. The finishing work, fire-fighting NOC, electrici

EXT51700005854Mar 2020 → Mar 2021

Reason as filed by the promoterWe, Bhavani Enterprises, have registered for our real estate project " Mohan Heights Phase ­II " bearing registration no. P51700004772. The date of completion of the project was given as 31.03.2020 at the time of registration. However, we couldn’t complete said project within the stipulated period due to shortage of sand, inadequate labour supply and changes in policies. The finishing work, fire-fighting NOC, electricity main line connection and solar work are yet to be completed. We request to kindly accept our application and grant us the extension till 30.03.2021.

EA17052501171Mar 2020 → Dec 2026

Reason as filed by the promoterWe, M/s Bhavani Enterprises ("Bhavani"), and we are writing you with regards to our application for extension of time till 31st December, 2026; 1) As you are aware that the company is engaged in the constructing a real estate project at Kalyan, Maharashtra on its plot of land comprising of 3 Building A wing, B wing and C wing.”. [hereinafter collectively referred to as "the Proiect"). 2) We say that we obtained the Rera registration number P51700004772 on 09.08.2017 for Project Mohan Heights Phase II at Titwala in Kalyan, Thane. 3. We say that we have obtained development rights of the said pr

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 31-03-2026 Bhavani Enterprises_compressed.pdf20 Jun 2026
Withdrawal Update Form 2File: Form 2 31-03-2026 Bhavani Enterprises.pdf20 Jun 2026
Withdrawal Update Form 3File: Form 3 FInal 31-03-2026 Bhavani Enterprises.pdf20 Jun 2026
Withdrawal Update Form 1File: form 1 30-9-25.pdf27 Mar 2026
Withdrawal Update Form 1File: Form 1 31-12-25.pdf27 Mar 2026
Withdrawal Update Form 2File: form 2 30-9-25.pdf27 Mar 2026
Withdrawal Update Form 2File: form 2 31-12-25.pdf27 Mar 2026
Withdrawal Update Form 3File: form 3 final.pdf27 Mar 2026
Withdrawal Update Form 3File: Form 3 31-12-2025.pdf27 Mar 2026
Withdrawal Update Form 1File: form 1 30-6-2025.pdf26 Mar 2026
Withdrawal Update Form 2File: form 2 30-6-2025.pdf26 Mar 2026
Withdrawal Update Form 3File: form 3 signed_compressed.pdf26 Mar 2026
Form 1File: March 2025.pdf19 May 2025
Form 2File: March 2025.pdf19 May 2025
Form 3File: Form-3.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: March 2025.pdf19 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 2025.pdf21 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: March 2025.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 31-03-2023.pdf12 Mar 2025
Disclosure of sold/ booked inventoryFile: 30-06-2023.pdf12 Mar 2025
Disclosure of sold/ booked inventoryFile: 30-09-2023.pdf12 Mar 2025
Disclosure of sold/ booked inventoryFile: 30-06-2024.pdf12 Mar 2025
Disclosure of sold/ booked inventoryFile: 30-09-2024.pdf12 Mar 2025
Disclosure of sold/ booked inventoryFile: 31-12-2024.pdf12 Mar 2025
Certificates of CA (Form 3)File: form 03 bhawani enterprises_compressed.pdf20 Feb 2025
Certificates of CA (Form 3)File: Form 3 compressed 36-06-2024_0001_.pdf14 Feb 2025
Certificates of CA (Form 3)File: Form 3 compressed 36-06-2024_0001_.pdf14 Feb 2025
Certificates of CA (Form 3)File: Form 3 compressed 36-06-2024_0001_.pdf14 Feb 2025
Certificates of CA (Form 3)File: Form 3 (c) Bhavani Enterprises 39-09-2024_0001_compressed.pdf14 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 30-06-2024.pdf13 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 30-09-2024.pdf13 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- 31-12-2024.pdf13 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31-12-2024.pdf12 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 30-06-2024.pdf28 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 30-09-2024.pdf28 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: Phase 2 CC - 2021.pdf6 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 31-03-2024.pdf20 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mar 2024.pdf26 Apr 2024
Certificates of CA (Form 3)File: Form 3 Signed by Promoter_compressed.pdf26 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 21-22.pdf13 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 22-23.pdf13 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold 31-12-2023.pdf10 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold List 31-03-2024.pdf10 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 2023.pdf20 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sept 2023.pdf20 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 2023.pdf20 Mar 2024
Certificates of CA (Form 3)File: Form 3 June 2023.pdf20 Mar 2024
Certificates of CA (Form 3)File: Form 3 Sept2023.pdf20 Mar 2024
Certificates of CA (Form 3)File: Form 3 Dec 2023.pdf20 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 2020.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: June 2020.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 2020.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 2020.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 2021.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: June 2021.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 2021.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 2021.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 2022.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: June 2022.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 2022.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 2022.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 2023.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: June 2023.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 2023.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 2023.pdf1 Mar 2024
Certificates of CA (Form 3)File: form 3 Mar23_compressed.pdf14 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form-5 22-23.pdf14 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Fy22-23.pdf14 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf28 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf28 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf19 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A-Quality Assurance-Mar 20.pdf4 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold and Unsold Value Final.pdf4 Aug 2021
Declaration about Commencement CertificateFile: Formate D.pdf2 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form2A-310302021.pdf2 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold and Unsold List_compressed (1).pdf2 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold and Unsold List_compressed (1).pdf2 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold and Unsold List.pdf22 Jun 2021
Certificates of CA (Form 3)File: FORM 3 30-06-2019.pdf22 May 2021
Certificates of CA (Form 3)File: FORM 3 30-09-2019.pdf22 May 2021

How this compares with Thane

59%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 81 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MOHAN HEIGHTS PHASE-II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TITWALA7,600+ in Thane

Builder: BHAVANI ENTERPRISES

BHAVANI ENTERPRISES has 6 registrations on MahaRERA, including MOHAN HEIGHTS PHASE-II and MOHAN HEIGHTS -PHASE 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if MOHAN HEIGHTS PHASE-II is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MOHAN HEIGHTS PHASE-II?

The registered promoter entity is BHAVANI ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MOHAN HEIGHTS PHASE-II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MOHAN HEIGHTS PHASE-II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MOHAN HEIGHTS PHASE-II?

The professionals named in the filing: Architect: ARC VIJAY PANDEY; Engineer: KB CONSULTANTS PATEL; Chartered Accountant: MAYUR K JAIN AND CO; Chartered Accountant: ANKIT PARAS JAIN AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MOHAN HEIGHTS PHASE-II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MOHAN HEIGHTS PHASE-II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MOHAN HEIGHTS PHASE-II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.