Misty Trails
RG-MH-19703 · RERA P52100012905 · Last updated on MahaRERA portal: 23 Feb 2021
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 43 months past the filed date
- 8 complaints at MahaRERA
- Completion date moved by 36 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Misty Trails is a Others project by Suraj Raman Bhujbal in Pune, Maharashtra, registered with MahaRERA as P52100012905 on 7 Sep 2017. Possession was promised by 30 Mar 2023 and is now 43 months past that date. The completion date has moved by 36 months from the original filing. 8 complaints are on record with the regulator.
At a glance
Project
- NameMisty Trails
- TypeOthers
- Location
- Hadapsar
- Haveli
- Pune
- 411028
- Pincode411028
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100012905
- ReraGenie IDRG-MH-19703
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Sep 2017
- Promised completion30 Mar 2023
- Revised completionRevised to 30 Mar 2023 (originally 30 Mar 2020)
- Buildings4 building records
- Documents filed23 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 14 | 0 | 0 | 0 | 0 |
| B | NA | 13 | 0 | 0 | 0 | 0 |
| C | NA | 14 | 0 | 0 | 0 | 0 |
| D | NA | 13 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 23 Feb 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 90%.
A55%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 80% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B33%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 10% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C60%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 50% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D52%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 50% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 23 Feb 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 25% |
| Street Lighting | Yes | 25% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Alok Kirad |
| Partner | Role in project |
|---|---|
| Suraj Raman Bhujbal | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterOut of the entire Project, the Promoter has completed 60% of work till date and undertakes to complete balance of the remaining work. The Promoter / Developer are slightly in financial crunch hence could not complete the project within stipulated time. The Promoter / Developer assures that the said remaining balance work would be completed within stipulated period, however seeking extension for the period so that there is no hindrances in completing the project as stated herein.
Reason as filed by the promoterDue To the lockdown, the workers could not be available for construction still we are facing this problem till date and now sudden death of one of the Partners of the said Firm namely Mr. Suraj Raman Bhujbal, work got further delayed. Please consider the above problem and extend the date of completion of the project as per the date mentioned hereinabove. At present, almost 70% of work has been completed and the promoter bound to complete the remaining work within the time declared before this Hon’ble Authority under Registration.
Complaints filed with MahaRERA8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000011116 | VIJAYKUMAR HARICHAND GANDHI | Vijaykumar Harichand Gandhi | 16/01/2019 |
| CC005000000054095 | Vijaykumar Gandhi | M/s. Bhujabal Brother Construction Copmpany | 16/03/2020 |
| CC005000000117059 | VIJAY KUMAR GANDHI | M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY | 03/05/2022 |
| CC005000000023127 | Mr Umesh Bhagwan Gaikwad | Bhujbal Brothers construction company | 13/06/2019 |
| CC005000000023128 | Shashikant Kashinath Raskar | M/s Bhujbal Brothers construction company | 13/06/2019 |
| CC005000000064523 | MRS SUJATA SAKET THAKOOR | M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | 18/08/2020 |
| CC005000000106808 | M/s Bhujbal Brothers Construction Company Through Its Partner Mr Dhiraj Raman Bhujbal | Mrs. Sujata Saket Thakoor | 22/03/2022 |
| CC005000000340708 | Savita Savita More | M/S.BHUJBAL BROTHERS CONSTRUCTION COMPANY ThroughPartners- A. Mr. Ramesh Damodar Bhujbal & others 4 | 10/04/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed23
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Certificate.pdf | 23 Feb 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 2017 2018.pdf | 20 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018 2019.pdf | 29 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: M Trails.PDF | 4 Aug 2017 |
| Certificates of CA (Form 3)File: CA Certificate Misty Trails.pdf | 4 Aug 2017 |
| Building plan approvalFile: 4-4.pdf | 31 Jul 2017 |
| Building plan approvalFile: 3-4.pdf | 31 Jul 2017 |
| Building plan approvalFile: 2-4.pdf | 31 Jul 2017 |
| Layout approvalFile: M Trails Layout.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: M Trails.PDF | 31 Jul 2017 |
| Copy of the legal title reportFile: M Trails 1.PDF | 31 Jul 2017 |
| Copy of the legal title reportFile: M Trails 2.PDF | 31 Jul 2017 |
| Details of encumbrancesFile: M Trails 1.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: M Trails Layout.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 2-4.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 3-4.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 4-4.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Document 1.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Document 2.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Document 1.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Document 2.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: M trails Arch.PDF | 31 Jul 2017 |
| Proforma of Allotment letterFile: Blank Format Misty Trails.pdf | 31 Jul 2017 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Silver Crest | Sno16 Wanawadi | 24 | Completed | Dec 2011 | Late, Jul 2012 |
| Bhujbal Township B-9 | Sno67 Bhujbal township kothrud | 40 | Completed | Jun 2011 | Late, Oct 2011 |
| Damodar Residency A-3 | S. no8 Bhujbal Baug Kothrud | 44 | Completed | May 2011 | Late, Mar 2012 |
| Bhujbal Township B-5 Building | S no67 Bhujbal Township | 35 | Completed | Jan 2011 | Late, Mar 2011 |
| Bhujbal Township B-2 Building | S no 67 Bhujbal Township Kothrud | 43 | Completed | Sep 2010 | Late, Mar 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 23 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Misty Trails on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Hadapsar13,700+ in Pune
Filed coordinates, straight-line distance. 118 registered projects within 2 km.
Amanora Arbano Towers 73,74,75 and 76
City Corporation Limited
Astrana
Dilip Baburao Tupe
Leisure Town Phase 1
Sai Proviso Homes
ARV Newtown Phase III
Vedant Infracon
Kumar Parc Residences - A2
Kumar Properties Infratech Developers Pvt
Kumar Parc residences - A1
Kumar Properties Infratech Developers Pvt
Builder: Suraj Raman Bhujbal
Suraj Raman Bhujbal has 3 registrations on MahaRERA, including Valay and Forest Mist. Its filings disclose 5 earlier MahaRERA projects: declares 0 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Misty Trails shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Misty Trails is delayed beyond 30 Mar 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Misty Trails?
The registered promoter entity is Suraj Raman Bhujbal, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Misty Trails?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Misty Trails?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Misty Trails?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Misty Trails?
The professionals named in the filing: Architect: Alok Kirad. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Misty Trails?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback