ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / MIRAYA DIVINE

Registered No litigation declared Residential / Group Housing project

MIRAYA DIVINE

By MEXTECH PROPERTY DEVELOPERS LLP

RG-MH-17837 · RERA P51700055585 · Last updated on MahaRERA portal: 11 May 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Rs 125.00 crore secured on the land, in favour of BAJAJ HOUSING FINANCE LTD

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Basement (if any), 25%
113 of 220Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

MIRAYA DIVINE is a Residential / Group Housing project by MEXTECH PROPERTY DEVELOPERS LLP in Thane, Maharashtra, registered with MahaRERA as P51700055585 on 4 Apr 2024. Possession is promised by 15 Dec 2029. 107 of the 220 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMIRAYA DIVINE
  • TypeResidential / Group Housing
  • Location
    • SECTOR 4
    • MAJIWADE
    • Thane (M Corp.)
    • Thane
    • 400601
  • Pincode400601
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700055585
  • ReraGenie IDRG-MH-17837

Builder

  • NameMEXTECH PROPERTY DEVELOPERS LLP
  • Entity typeOthers
  • GSTIN27ABSFM3880H1ZO
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Named personsHIREN HANSRAJ CHHEDA, ANIL NAGRAJ MUTHA, RAJESH RAVJIBHAI PATEL
  • Other registrations3 more →

Key dates

this monthRegisteredApr 2024PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Apr 2024
  • Promised completion15 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed82 files

Current status

49%107 of 220 units booked
37.5%Work done, per cost certificate

Figures as on 11 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No- 3NA44382200220

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 25%.

Building No- 3: 14% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)25%
Podiums (if any)0%
Plinth25%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed529

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots529
Closed/Covered529

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area714 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofBAJAJ HOUSING FINANCE LTD
Secured amountRs 125.00 crore
CERSAI search filedYes
Declared on21 Aug 2025
LandownerVillageDistrict
FERMENTA BIOTECH LIMITED-Mumbai City

Approvals and building plan

Sanctioning authorityTMC
Permissible FSI22850.81
Proposed, not sanctioned22,851 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLR SHOP NO 2 3 MINT NEAR HIRANANDANI MEADOWS THANE MAHARASHTRA 400607
Estimated costRs 126.21 cr
Cost incurredRs 47.36 cr
Work done37.52%
BuildingWingEstimatedIncurred
Building No- 3NARs 117.75 crRs 45.20 cr
-NARs 8.47 crRs 2.15 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSuvarna Ghosh
ArchitectDeepak Mehta
EngineerMAHIMTURA CONSULTANTS PRIVATE LIMITED
EngineerVENTUREX PROJECT SERVICES LLP
Chartered AccountantKartik Jayantilal Patel
Chartered AccountantCA VELANI & POKAR
PartnerRole in project
MEXTECH PROPERTY DEVELOPERS LLP-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600483Hemant KatareMEXTECH PROPERTY DEVELOPERS LLP27/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Oct 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 15 Dec 2029

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: T3 Form 1 31032026.pdf11 May 2026
Withdrawal Update Form 2File: T3 Q4 FORM 2 31032026.pdf11 May 2026
Withdrawal Update Form 3File: FORM 3 31032026 Divine.pdf11 May 2026
Withdrawal Update Form 1File: T3 Form 1 31032026.pdf20 Apr 2026
Withdrawal Update Form 2File: T3 Q4 FORM 2 31032026.pdf20 Apr 2026
Withdrawal Update Form 3File: FORM 3 31032026 Divine.pdf20 Apr 2026
Withdrawal Update Form 1File: BLDG 03_MIRAYA DIVINE 31_12_25.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 - 31122025.pdf20 Jan 2026
Withdrawal Update Form 3File: Withdrawal Application Form3_Uploaded.pdf20 Jan 2026
Building plan approvalFile: Approved Plan_ Miraya Divine..pdf24 Oct 2025
Withdrawal Update Form 1File: Form 1 TOWER 03_MIRAYA 30_09_25 Scanned.pdf20 Oct 2025
Withdrawal Update Form 2File: RERA_Eng Cert_Miraya Divine.pdf20 Oct 2025
Withdrawal Update Form 3File: Withdrawal Application Form3 Scanned.pdf20 Oct 2025
Form 5 (FY 2024-2025)File: Form 5_24_25.pdf1 Sep 2025
Form 1File: BLDG 03_MIRAYA DIVINE_FORM 1 30_06_2025.pdf20 Jul 2025
Form 2File: RERA_Eng Cert_Miraya Divine June 25.pdf20 Jul 2025
Form 3File: Form 3 30_06_25 Miraya Divine.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: Miraya Divine Disclosure of Sold-Unsold Inventory 30062025.pdf20 Jul 2025
Form 1File: BLDG 03_MARCH 2025.pdf19 Jul 2025
Form 2File: Form 2 - 31032025.pdf19 Jul 2025
Form 3File: Form 3 31_03_25 Miraya Divine..pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Miraya Divine Disclosure of Sold Unsold Inventory 31_03_2025.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: BLDG 03_MARCH 2025.pdf30 Apr 2025
Details of encumbrances concerned to FinanceFile: RERA Encumbrance Format.pdf24 Apr 2025
Details of encumbrances concerned to LegalFile: RERA Encumbrance Format.pdf24 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Uploaded.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 31122024.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Miraya Divine Disclosure of Sold-Unsold Inventory 31122024.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Miraya Divine Disclosure of Sold-Unsold Inventory 30062024.pdf27 Dec 2024
Disclosure of sold/ booked inventoryFile: Miraya Divine Disclosure of Sold-Unsold Inventory 30092024.pdf27 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30092024 Miraya Divine RERA Engineer Certificate 041224.pdf13 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30_09_24.pdf15 Nov 2024
Copy of the legal title reportFile: Annexure H - TITLE REPORT.pdf20 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: Cert_RB_385505_407zNk06Sign.pdf20 Jul 2024
Proforma of Agreement for saleFile: Draft AFS Miraya Divine.pdf20 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ilovepdf_merged (17)_11zon.pdf19 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: CC 3.pdf18 Mar 2024
Other - LegalFile: ilovepdf_merged (17)_11zon.pdf18 Mar 2024
Building plan approvalFile: 19-20_11zon.pdf14 Mar 2024
Building plan approvalFile: 20-20_11zon.pdf14 Mar 2024
Building plan approvalFile: 18-20_11zon.pdf14 Mar 2024
Building plan approvalFile: 17-20_11zon.pdf14 Mar 2024
Building plan approvalFile: 14-20_11zon.pdf14 Mar 2024
Building plan approvalFile: 15-20_11zon.pdf14 Mar 2024
Building plan approvalFile: 16-20_11zon.pdf14 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 14-20_11zon.pdf14 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 15-20_11zon.pdf14 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 16-20_11zon.pdf14 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 17-20_11zon.pdf14 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 18-20_11zon.pdf14 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 19-20_11zon.pdf14 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 20-20_11zon.pdf14 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: CC 2.pdf14 Mar 2024
Other - LegalFile: Upload Agreement _ MoU Copy (25).pdf14 Mar 2024
Layout approvalFile: 01-20_11zon (1).pdf6 Mar 2024
Building plan approvalFile: 01-20_11zon (1).pdf6 Mar 2024
Building plan approvalFile: 2 Building Plan Approval _ NA Order for plotted development (11).pdf6 Mar 2024
Building plan approvalFile: 03-20_11zon.pdf6 Mar 2024
PAN CardFile: PAN Card.pdf6 Mar 2024
Copy of the legal title reportFile: Mextech Title Report (1).pdf6 Mar 2024
Details of encumbrances concerned to FinanceFile: Encumbrance to Finance - Miraya Divine.pdf6 Mar 2024
Details of encumbrances concerned to FinanceFile: Encumbrance to Legal - Miraya Divine.pdf6 Mar 2024
Details of encumbrances concerned to LegalFile: Encumbrance to Finance - Miraya Divine.pdf6 Mar 2024
Details of encumbrances concerned to LegalFile: Encumbrance to Legal - Miraya Divine.pdf6 Mar 2024
Copy of Layout Approval (in case of layout)File: 01-20_11zon (1).pdf6 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 01-20_11zon (1).pdf6 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 2 Building Plan Approval _ NA Order for plotted development (11).pdf6 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 03-20_11zon.pdf6 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: CC 1.pdf6 Mar 2024
Declaration about Commencement CertificateFile: Final Format D- Miraya Divine.pdf6 Mar 2024
Declaration in FORM BFile: Form B (1).pdf6 Mar 2024
CERSAI detailsFile: Decalration to Cersai Report - Miraya Divine.pdf6 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3- Miraya Divine.pdf6 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations (24).pdf6 Mar 2024
Proforma of Agreement for saleFile: Final AFS Miraya Divineeeeeeeeee.pdf6 Mar 2024
Proforma of Allotment letterFile: MEXTECH - Miraya Divine - Allotment.pdf6 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration About Separate Bank Account - Miraya Divine.pdf6 Mar 2024
Deviation Report with respect to Allotment letterFile: Miraya Divine - Allotment Deviation Report (1).pdf6 Mar 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report of AFS_Miraya Divine_MEXTECH PROPERTY DEVELOPERS LLP _14032024 (3).pdf6 Mar 2024

How this compares with Thane

49%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MIRAYA DIVINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAJIWADE7,600+ in Thane

2 kmMIRAYA DIVINECompleted 163Lapsed / revoked 56Other 138Dot size: filed unitsN

Filed coordinates, straight-line distance. 357 registered projects within 2 km.

Builder: MEXTECH PROPERTY DEVELOPERS LLP

MEXTECH PROPERTY DEVELOPERS LLP has 4 registrations on MahaRERA, including MIRAYA BUSINESS HUB and MIRAYA DIVINE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if MIRAYA DIVINE is delayed beyond 15 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MIRAYA DIVINE?

The registered promoter entity is MEXTECH PROPERTY DEVELOPERS LLP, an others as per the filing. Its GSTIN 27ABSFM3880H1ZO can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MIRAYA DIVINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MIRAYA DIVINE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MIRAYA DIVINE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MIRAYA DIVINE?

The professionals named in the filing: Architect: Suvarna Ghosh; Architect: Deepak Mehta; Engineer: MAHIMTURA CONSULTANTS PRIVATE LIMITED; Engineer: VENTUREX PROJECT SERVICES LLP; Chartered Accountant: Kartik Jayantilal Patel; Chartered Accountant: CA VELANI & POKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MIRAYA DIVINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MIRAYA DIVINE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MIRAYA DIVINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.