Home / Browse projects / Mumbai Suburban, Maharashtra / MINT

Registered No litigation declared Commercial project

MINT

By TULSIANI SUMER ASSOCIATES

RG-MH-06135 · RERA P51800053816 · Last updated on MahaRERA portal: 24 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 5 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Nov 2026Possession promisedmoved 5 months from the original
10 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 0%
99 of 121Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 101 documents Report an error

MINT is a Commercial project by TULSIANI SUMER ASSOCIATES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800053816 on 1 Dec 2023. Possession is promised by 25 Nov 2026. The completion date has moved by 5 months from the original filing. 22 of the 121 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameMINT
  • TypeCommercial
  • Location
    • SIR MATHURADAS VASANJI ROAD
    • SAHAR PLAZA COMPLEX NEXT TO KOHINOOR CONTINENTAL HOTEL
    • Kondivita
    • Andheri
    • Mumbai Suburban
    • 400059
  • Pincode400059
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800053816
  • ReraGenie IDRG-MH-06135

Builder

  • NameTULSIANI SUMER ASSOCIATES
  • Entity typePartnership
  • PartnersMANAKCHAND HAJARIMAL LOONKAR, RAMESH SUMERMAL SHAH, MAHENDRA MANAKCHAND LOONKAR, RAMESH CHANDUMAL TULSIANI, RAGHUVIR SADASHIV KUWELKER, SHRIPAD MUKUND KUVELKER, RANAI MAHENDRA LOONKAR, TULSIANI BUILDER AND TEXTILES PVT LTD REPRESENTED THROUGH RAGHUVIR KUWELKER

Key dates

this monthRegisteredDec 2023First promiseJun 2026Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Dec 2023
  • Promised completion25 Nov 2026
  • Revised completionRevised to 25 Nov 2026 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed101 files

Current status

18%22 of 121 units booked
58.0%Work done, per cost certificate

Figures as on 24 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 3 WING ANA14100121121

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 0%.

BUILDING NO 3 WING A: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed371

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots371
Closed/Covered181
Open Space190

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,756 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on17 Nov 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI24411.21
Proposed, not sanctioned23,711 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTULSIANI CHAMBERS, 101/104, FREE PRESS JOURNAL MARGM, NARIMAN POINT, MUMBAI 400 021
Estimated costRs 216.02 cr
Cost incurredRs 125.32 cr
Work done58.01%
BuildingWingEstimatedIncurred
BUILDING NO 3 WING ANARs 196.02 crRs 125.32 cr
-NARs 20.00 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBREGEES RUSI ITALIA RUSI ITALIA
EngineerKENI & D'SOUZA COUNSULTING CIVIL ENGINEERS RAGHUVIR KENI
EngineerJAYESH D MEHTA DAULATRAI MEHTA
Chartered AccountantNAIK DANAIT & ASSOCIATES
Chartered AccountantS V V & CO
Chartered AccountantNehali Dhaval Doshi
PartnerRole in project
TULSIANI SUMER ASSOCIATES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA25082622386Jun 2026 → Nov 2026

Reason as filed by the promoterOC Recived

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 25 Nov 2026

Documents filed101

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A Quality Assurance 31-03-2025.pdf24 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A Quality Assurance 31-03-2026.pdf24 Jul 2026
Withdrawal Update Form 1File: Form 1 (1).pdf16 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf16 Jul 2026
Withdrawal Update Form 3File: Form 3 (1).pdf16 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf27 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf27 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf27 Apr 2026
Withdrawal Update Form 1File: Form1.pdf27 Feb 2026
Withdrawal Update Form 2File: Form2.pdf27 Feb 2026
Withdrawal Update Form 3File: Form 3.pdf27 Feb 2026
Withdrawal Update Form 1File: Tsa ReraForm1 Qtr ending.pdf15 Dec 2025
Withdrawal Update Form 2File: Tsa ReraForm2 Qtr.pdf15 Dec 2025
Withdrawal Update Form 3File: Form 3 Tulsiani Sumer Associates (1).pdf15 Dec 2025
Withdrawal Update Form 1File: new form 1.pdf21 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate.pdf21 Nov 2025
Withdrawal Update Form 3File: Form 3 Tulsiani Sumer Associates (1).pdf21 Nov 2025
Form 5 (FY 2024-2025)File: Form 5.pdf1 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect.pdf14 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA.pdf14 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer.pdf14 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf16 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf16 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf17 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1.pdf9 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2.pdf9 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3.pdf9 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate TSA.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate TSA.pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate TSA.pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate DEC 23.pdf15 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate DEC 23.pdf15 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate DEC 23.pdf15 Jan 2024
Details of encumbrances concerned to FinanceFile: CTS declaration for RERA.pdf20 Nov 2023
Details of encumbrances concerned to FinanceFile: No Encumberance - Finance.pdf20 Nov 2023
Details of encumbrances concerned to FinanceFile: No Encumberance - Legal.pdf20 Nov 2023
Details of encumbrances concerned to LegalFile: CTS declaration for RERA.pdf20 Nov 2023
Details of encumbrances concerned to LegalFile: No Encumberance - Finance.pdf20 Nov 2023
Details of encumbrances concerned to LegalFile: No Encumberance - Legal.pdf20 Nov 2023
Declaration about Commencement CertificateFile: CC Declaration.pdf20 Nov 2023
CERSAI detailsFile: Declaration cersai.pdf20 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Form3_17112023.pdf20 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Diclosure of Interest - Ranai.pdf20 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - Mahendra.pdf20 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - Manakchand.pdf20 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - Ramesh Shah.pdf20 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - RCT.pdf20 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - RSK.pdf20 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - SMK.pdf20 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - TBTL.pdf20 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: latest CC.pdf3 Nov 2023
Declaration about Commencement CertificateFile: Declaration about CC (Format - D).pdf1 Aug 2023
Layout approvalFile: Plan with marking.pdf31 Jul 2023
Copy of Layout Approval (in case of layout)File: Plan with marking.pdf31 Jul 2023
Declaration in FORM BFile: Form-B Revised.pdf31 Jul 2023
CERSAI detailsFile: CTS declaration for RERA.pdf28 Jul 2023
Other - LegalFile: CTS declaration for RERA.pdf28 Jul 2023
Other - FinanceFile: CTS declaration for RERA.pdf28 Jul 2023
Other - TechnicalFile: CTS declaration for RERA.pdf28 Jul 2023
Copy of the legal title reportFile: Title Certificate as per RERA format Final 12-07-2023.pdf12 Jul 2023
Other - LegalFile: Disclaimer.pdf12 Jul 2023
Declaration about Commencement CertificateFile: Declaration about CC (Format - D).pdf11 Jul 2023
Proforma of Agreement for saleFile: Agreement for Sale.pdf11 Jul 2023
Proforma of Allotment letterFile: Draft Allotment Letter.pdf11 Jul 2023
Deviation Report with respect to Allotment letterFile: Deviation Report - Allotment letter.pdf11 Jul 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report- Agreement for Sale-1.pdf11 Jul 2023
Building plan approvalFile: ALL_Part7.pdf10 Jul 2023
Building plan approvalFile: ALL_Part8.pdf10 Jul 2023
Building plan approvalFile: ALL_Part9.pdf10 Jul 2023
Building plan approvalFile: ALL_Part10.pdf10 Jul 2023
Building plan approvalFile: ALL_Part2.pdf10 Jul 2023
Building plan approvalFile: ALL_Part3.pdf10 Jul 2023
Building plan approvalFile: ALL_Part4.pdf10 Jul 2023
Building plan approvalFile: ALL_Part5.pdf10 Jul 2023
Building plan approvalFile: ALL_Part6.pdf10 Jul 2023
Layout approvalFile: Approval letter of Layout 1199.pdf10 Jul 2023

How this compares with Mumbai Suburban

18%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 5 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MINT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SAHAR PLAZA COMPLEX NEXT TO KOHINOOR CONTINENTAL HOTEL6,700+ in Mumbai Suburban

2 kmMINTCompleted 105Lapsed / revoked 62Other 71Dot size: filed unitsN

Filed coordinates, straight-line distance. 238 registered projects within 2 km.

Builder: TULSIANI SUMER ASSOCIATES

TULSIANI SUMER ASSOCIATES has 1 registration on MahaRERA, including MINT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if MINT is delayed beyond 25 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MINT?

The registered promoter entity is TULSIANI SUMER ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MINT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MINT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MINT?

The professionals named in the filing: Architect: BREGEES RUSI ITALIA RUSI ITALIA; Engineer: KENI & D'SOUZA COUNSULTING CIVIL ENGINEERS RAGHUVIR KENI; Engineer: JAYESH D MEHTA DAULATRAI MEHTA; Chartered Accountant: NAIK DANAIT & ASSOCIATES; Chartered Accountant: S V V & CO; Chartered Accountant: Nehali Dhaval Doshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MINT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MINT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MINT to a free account