Home / Browse projects / Mumbai Suburban, Maharashtra / Milan Bliss

Completed No litigation declared Residential / Group Housing project

Milan Bliss

By Milan Interbuilt Private Limited

RG-MH-34139 · RERA P51800046482 · Last updated on MahaRERA portal: 15 Mar 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Aug 2025Possession promisedregistration recorded completed
3 of 11Construction stages donefurthest along: Internal walls, 95%
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

Milan Bliss is a Residential / Group Housing project by Milan Interbuilt Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800046482 on 5 Aug 2022. The registration is recorded completed; possession was promised by 31 Aug 2025. The completion date has moved by 6 months from the original filing.

At a glance

Project

  • NameMilan Bliss
  • TypeResidential / Group Housing
  • Location
    • New Nagardas Cross Road
    • Andheri East
    • Andheri
    • Mumbai Suburban
    • 400069
  • Pincode400069
  • RERA no.P51800046482
  • ReraGenie IDRG-MH-34139

Builder

  • NameMilan Interbuilt Private Limited
  • Entity typeCompany
  • DirectorsBharat Tulsidas Amlani, Nikhil Dhirajlal Samani, Hiten Jagmohan Pabari
  • Other registrations5 more →
  • Completed3 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2022First promiseFeb 2025Revised toAug 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2022
  • Promised completion31 Aug 2025
  • Revised completionRevised to 31 Aug 2025 (originally 28 Feb 2025)
  • Buildings1 building record
  • Documents filed74 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Milan Bliss - Arunodaya CHS A and B WingNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

Milan Bliss - Arunodaya CHS A and B Wing: 60% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes85%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Closed/Covered30
Open Space3

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area821 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
The Arunodaya Co Operative Housing Society LtdAndheriMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2215.15
Proposed, not sanctioned1,856 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHubtown Solaris Branch Ground Floor, Building No-1, Hubtown Solaris, Gundavali, Saiwadi, Andheri Eas

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Milan Interbuilt Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800027879Feb 2025 → Aug 2025

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-08-2025 to complete the project and fulf

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Affdavit cum Declaration Notarised.pdf15 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: HM JHAVERI MB.pdf15 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Milan Bliss as on Dec 2024 Promoter signed.pdf15 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SK MB.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Circular 29.pdf15 Mar 2025
Declaration about Commencement CertificateFile: CC Declaration.pdf15 Mar 2025
Other - TechnicalFile: PERT CHART MB-1.pdf15 Mar 2025
Other - TechnicalFile: PERT Chart for Project Completion.pdf15 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure - A.pdf15 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 2022-23 MB signed.pdf15 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5-Milan Bliss-FY 2022-23.pdf15 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5-Milan Bliss-FY 2022-23 SIGNED.pdf15 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 2023-24 MB signed.pdf15 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-Milan Bliss-FY 2023-24.pdf15 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-Milan Bliss-FY 2023-24 signed.pdf15 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Milan Bliss as on Dec 2024.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Milan Bliss as on Dec 2024.pdf26 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Milan Bliss as on Dec 2024.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Milan Bliss as on Sep 2024.pdf4 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Milan Bliss as on Sep 2024.pdf3 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Milan Bliss Sep 2024.pdf30 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Milan Bliss as on 31-03-2024.pdf30 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Milan Bliss as on 30-06-2024.pdf30 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Milan Bliss as on March 2024.pdf30 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Milan Bliss as on June 2024.pdf30 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Milan Bliss as on June 2024.pdf10 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Milan Bliss as on June 2023.pdf11 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Milan Bliss as on Sep 2023.pdf11 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Milan Bliss as on Dec 2023.pdf11 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Milan Bliss as on 30-06-2023.pdf11 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Milan Bliss as on 30-09-2023.pdf11 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Milan Bliss as on 31-12-2023 Final.pdf11 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Milan Bliss as on March 2024.pdf7 May 2024
Commencement Certificates / NA Order for plotted developmentFile: CC - Milan Bliss.pdf8 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Milan Bliss as on Dec 2023.pdf19 Jan 2024
Details of encumbrances concerned to FinanceFile: Encumberance Cert.pdf18 Nov 2023
Details of encumbrances concerned to LegalFile: Encumberance Cert.pdf18 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Milan Bliss as on March 2023.pdf18 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Milan Bliss as on June 2023.pdf18 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Milan Bliss as on September 2023.pdf18 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Milan Bliss as on Sep 2022.pdf17 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Milan Bliss as on Dec 2022.pdf17 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Milan Bliss as on March 2023.pdf17 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Milan Bliss as on 30th September 2022.pdf17 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Milan Bliss as on 31st December 2022.pdf17 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Milan Bliss as on 31st March 2023.pdf17 Nov 2023
Proforma of Agreement for saleFile: Agreement for Sale - Milan Bliss.pdf8 Nov 2023
Details of encumbrances concerned to FinanceFile: Aruno No Encumbrances 25-10-2023.pdf25 Oct 2023
Details of encumbrances concerned to LegalFile: Aruno No Encumbrances 25-10-2023.pdf25 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- Milan Bliss as on 30-09-2023.pdf25 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Milan Bliss.pdf25 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Milan Bliss.pdf5 Jun 2023
Details of encumbrances concerned to FinanceFile: Encumbrance -Finance -Mialn Bliss.pdf28 Jul 2022
Details of encumbrances concerned to LegalFile: Encumbrance Milan Bliss - Legal.pdf28 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: organized (8)_compressed.pdf28 Jul 2022
Proforma of Allotment letterFile: AFS_ARUNODAYA__21_07_2022.pdf28 Jul 2022
Proforma of Allotment letterFile: Allotment_ARUNODAYA_21_07_2022.pdf28 Jul 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank AC details -Milan Bliss.pdf28 Jul 2022
Deviation Report with respect to Allotment letterFile: Deviation -Allotment -Milan Bliss.pdf28 Jul 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Report Milan Bliss.pdf28 Jul 2022
Building plan approvalFile: Milan bliss plans-2_11zon (1).pdf18 Jun 2022
Building plan approvalFile: 3 Building Plan Approval _ NA Order for plotted development.pdf18 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Milan bliss plans-2_11zon (1).pdf18 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: 3 Building Plan Approval _ NA Order for plotted development.pdf18 Jun 2022
Declaration about Commencement CertificateFile: Declaration about CC Milan Bliss.pdf18 Jun 2022
Declaration in FORM BFile: new (1).pdf18 Jun 2022
Layout approvalFile: Milan bliss plans-1.pdf8 Jun 2022
Building plan approvalFile: Milan bliss plans-1.pdf8 Jun 2022
Copy of Layout Approval (in case of layout)File: Milan bliss plans-1.pdf8 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Milan bliss plans-1.pdf8 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: First CC.pdf4 Jun 2022
CERSAI detailsFile: Milan Bliss.pdf23 May 2022
PAN CardFile: MILANINTERBUILT PAN.pdf20 May 2022
Copy of the legal title reportFile: RERA TITLE 03-05-2022.pdf20 May 2022

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 6 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Milan Bliss on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri East6,700+ in Mumbai Suburban

Builder: Milan Interbuilt Private Limited

MILAN INTERBUILT PRIVATE LIMITED has 6 registrations on MahaRERA, including MEGHDOOT RESIDENCY and NAZARETH NIKETAN. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Milan Bliss is delayed beyond 31 Aug 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Milan Bliss?

The registered promoter entity is Milan Interbuilt Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Milan Bliss?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Milan Bliss?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Milan Bliss?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Milan Bliss. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Milan Bliss to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.