ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Midas Bhoomi Harmony

Registration lapsed No litigation declared Others project

Midas Bhoomi Harmony

By Midas & Bhoomi Associates

RG-MH-02890 · RERA P51800020823 · Last updated on MahaRERA portal: 5 Dec 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 60 months past the filed date
  • 13 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2021Possession promised60 months past this date
29 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
13Complaints at MahaRERAon this registration
Jump to the 26 documents Report an error

Midas Bhoomi Harmony is a Others project by Midas & Bhoomi Associates in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800020823 on 15 May 2019. Possession was promised by 30 Oct 2021 and is now 60 months past that date. The completion date has moved by 12 months from the original filing. 13 complaints are on record with the regulator.

At a glance

Project

  • NameMidas Bhoomi Harmony
  • TypeOthers
  • Location
    • Nehru Nagar
    • Kurla East
    • Kurla
    • Mumbai Suburban
    • 400024
  • Pincode400024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800020823
  • ReraGenie IDRG-MH-02890

Builder

  • NameMidas & Bhoomi Associates
  • Entity typeOthers
  • Named personsMidas Developers Pvt. Ltd., Bhoomi Shashwat Estate Pvt. Ltd.
  • Declared earlier projects1 →

Key dates

60 months past promisethis monthRegisteredMay 2019First promiseOct 2020Revised toOct 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 May 2019
  • Promised completion30 Oct 2021
  • Revised completionRevised to 30 Oct 2021 (originally 30 Oct 2020)
  • Buildings3 building records
  • Documents filed26 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA190000
Wing BNA190000
Wing CNA190000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 5 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

Wing A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities18

As on 5 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
StiltYes100%
PlinthYes100%
BasementYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,249 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI12000.0
Proposed, not sanctioned10,484 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVinay Kumkum Building, Opp Lalit Hotel, Off S V Road, Goregaon West, Mumbai - 400104

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEllora Project Consultants Pvt Ltd
PartnerRole in project
Midas & Bhoomi Associates-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008613Oct 2020 → Oct 2021

Reason as filed by the promoterDue to COVID-19 PANDEMIC the labourers were not available. The work has stopped since the lockdown was imposed in March 2020.

Litigation declared4

CaseCourtStatus
2750/2020Bombay High CourtCase Disposed Off
131/2020Co Operative CourtCase Disposed Off
6029/2021Bombay City Civil CourtPending and no ad interim granted
24/2020Maharashtra Additional District Consumer ForumPending

Complaints filed with MahaRERA13

Case no.ComplainantRespondentFiled
CC006000000231209HEMANT DATTA BHANGLEM/S. MIDAS & BHOOMI ASSOCIATES, 1) EDWYN j D'MELLO, 2)AKSHAY J. DOSHI01/06/2022
CC006000000195100Prathmesh BhorMidas Bhoomi Harmony10/12/2020
CC006000000195201Arundhati R ChavanMr. Edwyn Jerry Demello and Manging Director of Bhoomi Associate11/12/2020
CC006000000197843Javed SayyedMidas & Bhoomi Associates31/07/2021
CC006000000241320AZIZA ABDULLAH SHARIFFMidas bhoomi associates02/06/2022
CC006000000397378zahidunnisha Abdulaziz AnsariMidas Bhoomi Associate06/09/2023
CC006000000500518Hemant Datta BhangleMidas & Bhoomi Associates21/05/2024
CC006000000540750MIDAS & BHOOMI ASSOCIATESAbdul Aziz Yar Mohammed Ansari13/06/2024
CC006000000540751MIDAS & BHOOMI ASSOCIATESShaikh Aashir Shakir14/06/2024
CC006000000540752MIDAS & BHOOMI ASSOCIATESShaikh Aashir Shakir14/06/2024
CC12400578EDWYN & DMELLOAbdul Aziz Yar Mohammed Ansari25/10/2024
CC12400945Prathmesh BhorMidas & Bhoomi Associates30/11/2024
CC12602064Midas & Bhoomi AssociatesShaikh Shakir Sabirali08/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jun 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Dec 2023

Documents filed26

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec,2022.pdf5 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar,23.pdf5 Dec 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full OC.pdf5 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 (20-21) midas and bhoomi.pdf23 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 (21-22) midas and bhoomi.pdf23 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Midas Part OC.pdf2 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: ANNUAL REPORT.pdf24 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: Full CC midas Bhoomi Harmony.pdf15 Jul 2021
Declaration about Commencement CertificateFile: Format D-Declaration for CC Midas and Bhoomi.pdf15 Jul 2021
Building plan approvalFile: Amended IOD Kurla Midas compressed.pdf4 Jun 2019
Building Plan Approval (IOD)File: Amended IOD Kurla Midas compressed.pdf4 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: Full CC Midas Bhoomi Harmony.pdf4 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: CC Revalidation 070519.pdf7 May 2019
Details of encumbrancesFile: Form B_compressed.pdf16 Mar 2019
Declaration in FORM BFile: Form B_compressed.pdf16 Mar 2019
OtherFile: FINAL BASEMENT.pdf16 Mar 2019
Building plan approvalFile: IOD.pdf15 Mar 2019
Layout approvalFile: IOA plans 1st sheet for upload.pdf15 Mar 2019
PAN CardFile: PAN Card.pdf15 Mar 2019
Copy of the legal title reportFile: CERTIFICATE OF TITLE_compressed.pdf15 Mar 2019
Copy of Layout Approval (in case of layout)File: IOA plans 1st sheet for upload.pdf15 Mar 2019
Building Plan Approval (IOD)File: IOD.pdf15 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf15 Mar 2019
Certificates of CA (Form 3)File: CA Certificate.pdf15 Mar 2019
Proforma of Allotment letterFile: AFS MIDAS BHOOMI HARMONY 140319 FINAL.pdf15 Mar 2019
OtherFile: Self Declaration for Redevelopment Project.pdf15 Mar 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
MIDAS-BHAKTI MEADOWSP51800013457Chembur, Mumbai Suburban78Oct 2017OngoingSep 2025Registered original: Jun 2019Not delivered

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Midas Bhoomi Harmony on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla East6,700+ in Mumbai Suburban

2 kmMidas Bhoomi HarmonyCompleted 111Lapsed / revoked 92Other 140Dot size: filed unitsN

Filed coordinates, straight-line distance. 343 registered projects within 2 km.

Builder: Midas & Bhoomi Associates

Midas & Bhoomi Associates has 1 registration on MahaRERA, including Midas Bhoomi Harmony. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Midas Bhoomi Harmony shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Midas Bhoomi Harmony is delayed beyond 30 Oct 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Midas Bhoomi Harmony?

The registered promoter entity is Midas & Bhoomi Associates, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Midas Bhoomi Harmony?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Midas Bhoomi Harmony?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Midas Bhoomi Harmony?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Midas Bhoomi Harmony?

The professionals named in the filing: Architect: Ellora Project Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Midas Bhoomi Harmony?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Midas Bhoomi Harmony. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Midas Bhoomi Harmony to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.