Home / Browse projects / Mumbai Suburban, Maharashtra / MIDAS-BHAKTI MEADOWS
MIDAS-BHAKTI MEADOWS
RG-MH-57819 · RERA P51800013457 · Last updated on MahaRERA portal: 25 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 5 months past the filed date
- 16 complaints at MahaRERA
- Completion date moved by 83 months
- 7 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MIDAS-BHAKTI MEADOWS is a Residential / Group Housing project by IRENE EDWYN DMELLO in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800013457 on 7 Oct 2017. Possession was promised by 31 May 2026 and is now 5 months past that date. The completion date has moved by 83 months from the original filing. 71 of the 78 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 16 complaints are on record with the regulator.
At a glance
Project
- NameMIDAS-BHAKTI MEADOWS
- TypeResidential / Group Housing
- Location
- Chembur
- Kurla
- Mumbai Suburban
- 400089
- Pincode400089
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800013457
- ReraGenie IDRG-MH-57819
Builder
- NameIRENE EDWYN DMELLO
- Entity typeIndividual
- GSTIN27ABZPD4177F1Z9
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Oct 2017
- Promised completion31 May 2026
- Revised completionRevised to 31 May 2026 (originally 30 Jun 2019)
- Buildings1 building record
- Documents filed141 files
Current status
Figures as on 25 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MIDAS-BHAKTI MEADOWS | NA | 15 | 13 | 78 | 0 | 78 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.
MIDAS-BHAKTI MEADOWS: 76% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Progress on shared amenities15
As on 25 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 10% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Navin Ramji Kothari | Mulund | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| MIDAS-BHAKTI MEADOWS | NA | Rs 19.18 cr | Rs 19.18 cr |
| - | NA | Rs 1.01 cr | Rs 13.88 lakh |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SNS Architects |
| Engineer | SK Consultants & Engineers |
| Engineer | Shriprakash Singh |
| Chartered Accountant | Vikas Abhang & Associates |
| Chartered Accountant | Rutuja Narsingh & Associates |
| Chartered Accountant | NB Sayed & Associates |
| Chartered Accountant | Pranav Bhaskaran |
| Partner | Role in project |
|---|---|
| IRENE EDWYN DMELLO | - |
Extensions applied for7
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterHardships in Building Industry. Delay in approvals due to policy decisions. FINANCIAL DIFFICULTIES.
Reason as filed by the promoterRespected Sir/Madam, Request to kindly consider accepting the Resolution / Consent for Extension uploaded in November 2020, as Stop-work Notice was issued to us in the same month, now as the lock-down situation still persists and the flat purchasers are not accessible, as they are residing in different far flung areas in Maharashtra and also many are senior citizens, who are in home quarantine. Hope you will positively consider the present difficult conditions faced and issue the Time Extension applied till 31.05.2022 at the earliest. We have uploaded scanned copies of stop-work notice dated 0
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 55.32% allottees for purpose of extension of RERA registration period of the said project.
Reason as filed by the promoterAs per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees
Reason as filed by the promoterWe regret the delay in the completion of the project and in submitting this request. The timeline was impacted by a combination of factors beyond our control, including delays in securing requisite permissions from the concerned authorities, logistical challenges in procurement, financial limitations, and on-ground execution hurdles.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.
Reason as filed by the promoterAt the outset, we sincerely regret the delay in completion of the project as well as the delay in submission of the present request for extension. The delay has occurred due to certain unforeseen and unavoidable circumstances beyond the reasonable control of the Promoter. These include, inter alia, disruptions in procurement of construction materials, financial constraints arising during the course of execution, and site-related challenges which impacted the progress of construction. Collectively, these factors adversely affected the planned construction schedule and resulted in a delay in ach
Complaints filed with MahaRERA16
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001616 | Bhupendra Kapasi | Irene Edwyn Dmello | 31/10/2017 |
| CC006000000090048 | GUL SHYAMDAS TOTLANI | NAVINBHAI RAMJI KOTHARI | 10/07/2019 |
| CC006000000171690 | KETAN KANAIYALAL MEHTA | NAVIN RAMJI KOTHARI | 27/11/2019 |
| CC006000000171764 | Dinesh Khimji Bahuva | Navin Ramjibhai Kothari | 04/12/2019 |
| CC006000000182085 | Ramesh Gangabhai Devda and Ganga Ramesh Devda | Irene Edwyn Dmello proprietor of M/s. Midas Builders | 07/01/2020 |
| CC006000000182090 | Hirji Kanjibhai Barwadia and Badhi Hirji Barwadia | Irene Edwyn Dmello properitor of M/s. Midas Builder | 07/01/2020 |
| CC006000000193738 | Manoj Kishanchand Panjabi | Irene Edwyn Dmello Proprietor of M/s. Midas Builders | 17/08/2020 |
| CC006000000193761 | Mohit Sunil Makhija | Irene Edwyn Dmello Proprietor of M/s. Midas Builders | 19/08/2020 |
| CC006000000193762 | Kanayalal Premchand Makhija Karta of Kanayala P. Makhija Hindu Undivided Family | Irene Edwyn Dmello Proprietor of M/s. Midas Builder | 19/08/2020 |
| CC006000000193763 | Megha Ashish Nainani | Irene Edwyn Dmello Proprietor of M/s. Midas Builders | 19/08/2020 |
| CC006000000198829 | DASHRAJ E MODAK | MIDAS BHAKTI MEADOWS | 29/10/2021 |
| CC006000000375266 | Maheshbhai Popatbhai Bhuva | N R CORPORATION AND MIDAS BUIDERS | 14/04/2023 |
| CC12601213 | Maheshbhai Popatbhai Bhuva | IRENE EDWYN DMELLO | 06/03/2026 |
| CC12601226 | Maheshbhai Popatbhai Bhuva | IRENE EDWYN DMELLO | 06/03/2026 |
| CC12602849 | Rajpal Shyamlal Singh | IRENE EDWYN DMELLO | 15/05/2026 |
| CC12602852 | Rajpal Shyamlal Singh | IRENE EDWYN DMELLO | 15/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Sep 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Jan 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Jan 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed141
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 141 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Midas-Bhakti Meadows_Form1_June 2026.pdf | 25 Jul 2026 |
| Withdrawal Update Form 2File: Midas-Bhakti_Meadows_Form2_Q1_2026-27_25-07-2026_11-56.pdf | 25 Jul 2026 |
| Withdrawal Update Form 3File: Midas-Bhakti_Meadows_Form3_Q1_2026-27_21-07-2026_13-01_doc1.pdf | 25 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 - Midas Bhakti Meadows as on March 2026 (Signed).pdf | 3 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - Midas Bhakti Meadows as on March 2026 (Signed).pdf | 3 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 - Midas Bhakti Meadows as on March 2026 (Signed).pdf | 3 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 - Midas Bhakti Meadows as on Dec 2025.pdf | 21 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 - Midas Bhakti Meadows as on Dec 2025.pdf | 21 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 - Midas Bhakti Meadows as on Dec 2025.pdf | 21 Jan 2026 |
| Withdrawal Update Form 1File: Form 1- Midas Bhakti Meadows as on Sep 2025.pdf | 10 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - Midas Bhakti Meadows as on Sep 2025.pdf | 10 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - Midas Bhakti Meadows as on Sep 2025.pdf | 10 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 - Midas Bhakti Meadows For FY 2024-25.pdf | 4 Oct 2025 |
| Withdrawal Update Form 1File: Form 1- Midas Bhakti Meadows as on June 2025.pdf | 30 Sep 2025 |
| Withdrawal Update Form 1File: Form 1- Midas Bhakti Meadows as on June 2025.pdf | 30 Sep 2025 |
| Withdrawal Update Form 2File: Form 2 - Midas Bhakti Meadows as on June 2025.pdf | 30 Sep 2025 |
| Withdrawal Update Form 2File: Form 2 - Midas Bhakti Meadows as on June 2025.pdf | 30 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 - Midas Bhakti meadows as june 2025.pdf | 30 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 - Midas Bhakti meadows as june 2025.pdf | 30 Sep 2025 |
| Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf | 30 Sep 2025 |
| Form 1File: Form 1- Midas Bhakti Meadows as on June 2025.pdf | 18 Jul 2025 |
| Form 2File: Form 2 - Midas Bhakti Meadows as on June 2025.pdf | 18 Jul 2025 |
| Form 3File: Form 3 - Midas Bhakti Meadows as on June 2025.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Midas Bhakti Meadows as on June 2025.pdf | 18 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3 - Midas Bhakti Meadows as on March 2025.pdf | 8 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Midas Bhakti Meadows as on March 2025.pdf | 8 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Midas Bhakti Meadows as on March 2025.pdf | 2 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Midas Bhakti Meadows as on December 2024.pdf | 13 Feb 2025 |
| Layout approvalFile: 202408201640.pdf | 15 Jan 2025 |
| Building plan approvalFile: Plans.pdf | 15 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: 202408201640.pdf | 15 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (Dec 2024).pdf | 15 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 (Dec 2024)_11zon (1).pdf | 15 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 (Dec 2024)_11zon.pdf | 15 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (Dec 2024).pdf | 15 Jan 2025 |
| Building Plan Approval (IOD)File: Plans.pdf | 15 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29 (Dec 2024).pdf | 15 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29 (Dec 2024)_organized.pdf | 15 Jan 2025 |
| Declaration about Commencement CertificateFile: Format D.pdf | 15 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 - Midas Bhakti Meadows as on December 2024.pdf | 10 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Midas Bhakti Meadows as on December 2024.pdf | 10 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Annexure-G1-CC 2024.pdf | 7 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: f.pdf | 30 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5- 17-18.pdf | 29 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A- 2019-20.pdf | 29 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5- 18-19.pdf | 29 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5- 19-20.pdf | 29 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5- 20-21.pdf | 29 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A- 2020-21 (1).pdf | 29 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- 21-22.pdf | 29 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A- 2021-22.pdf | 29 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- 2022-23 (2).pdf | 29 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- 22-23.pdf | 29 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Sept 2024.pdf | 25 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3_compressed.pdf | 25 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 25 Oct 2024 |
| Certificates of CA (Form 3)File: Form-3 June 24_compressed (1).pdf | 18 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 June 24.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24_compressed.pdf | 18 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3- Midas Bhakti Meadows as on 30-09-2024.pdf | 17 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Midas Bhakti Meadows as on Sept 2024.pdf | 17 Oct 2024 |
| Declaration in FORM BFile: Form-B.pdf | 7 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 June 24.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: Form-3 June 24_compressed.pdf | 7 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 June 24.pdf | 7 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 7 Oct 2024 |
| CERSAI detailsFile: Cersai Declaration.pdf | 7 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf | 7 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure-A.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24 (1).pdf | 7 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Midas Bhakti Meadows as on June 2024.pdf | 13 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 - Midas Bhakti Meadows as on June 2024.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SNS Form 1 RER.pdf | 4 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29 - Midas Bhakti.pdf | 23 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Midas Bhakti for FY 2022-23.pdf | 2 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Midas Bhakti as on March 2024.pdf | 10 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 - Midas Bhakti as on March 2024.pdf | 10 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1.pdf | 4 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 - Midas Bhakti as on 29-02-2024.pdf | 1 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29 -Midas Bhakti as on Dec 2023.pdf | 11 Jan 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 141 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MIDAS-BHAKTI MEADOWS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chembur6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 559 registered projects within 2 km.
Atmosphere O2 Tower-G
Atmosphere Realty Pvt Ltd
VARDHAN HEIGHTS
VARDHAN HOUSING
Promesa Midtown
Darshan Properties
ELYSIUM
KRIPA ELITE HOMES
JADE
PRIYA CONSTRUCTIONS
Gami and Jaydeep Elanza
M/S REAL INFRASTRUCTURE CO
See every Mumbai Suburban project, with the district possession charts
Builder: IRENE EDWYN DMELLO
IRENE EDWYN DMELLO has 1 registration on MahaRERA, including MIDAS-BHAKTI MEADOWS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that MIDAS-BHAKTI MEADOWS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if MIDAS-BHAKTI MEADOWS is delayed beyond 31 May 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MIDAS-BHAKTI MEADOWS?
The registered promoter entity is IRENE EDWYN DMELLO, an individual as per the filing. Its GSTIN 27ABZPD4177F1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MIDAS-BHAKTI MEADOWS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against MIDAS-BHAKTI MEADOWS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for MIDAS-BHAKTI MEADOWS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MIDAS-BHAKTI MEADOWS?
The professionals named in the filing: Architect: SNS Architects; Engineer: SK Consultants & Engineers; Engineer: Shriprakash Singh; Chartered Accountant: Vikas Abhang & Associates; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: NB Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MIDAS-BHAKTI MEADOWS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback