Mickey Links
RG-MH-31571 · RERA P51800079906 · Last updated on MahaRERA portal: 12 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 4 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mickey Links is a Residential / Group Housing project by JEETENDRA MURARILAL MODY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800079906 on 29 Mar 2025. Possession is promised by 30 Oct 2027. The completion date has moved by 4 months from the original filing. 1 of the 23 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.
At a glance
Project
- NameMickey Links
- TypeResidential / Group Housing
- Location
- 3rd Dominic Lane
- Malad West
- Valnai
- Borivali
- Mumbai Suburban
- 400064
- Pincode400064
- RERA no.P51800079906
- ReraGenie IDRG-MH-31571
Builder
- NameJEETENDRA MURARILAL MODY
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Mar 2025
- Promised completion30 Oct 2027
- Revised completionRevised to 30 Oct 2027 (originally 30 Jun 2027)
- Buildings1 building record
- Documents filed56 files
Current status
Figures as on 12 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Mickey Links | NA | 8 | 7 | 23 | 0 | 23 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 87%.
Mickey Links: 30% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 87% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 12 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership15
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Mr. Albert Cooper | Valnai | Mumbai Suburban |
| Mrs Verna Marina Louella Dsa | Valnai | Mumbai Suburban |
| Mrs. Lucia Melinda Dsa | Valnai | Mumbai Suburban |
| Mrs. Yvette Maria Dsa | Valnai | Mumbai Suburban |
| Ms. Tripti Domnic John Dsouza | Valnai | Mumbai Suburban |
| Mr. Ivor Christopher Dsa | Valnai | Mumbai Suburban |
| Mr. Duane Cooper | Valnai | Mumbai Suburban |
| Mr. Brendon Cooper | Valnai | Mumbai Suburban |
| Mrs. Samantha Sera Dsa | Valnai | Mumbai Suburban |
| Mr. Tarquin Vianney Joseph Dsa | Valnai | Mumbai Suburban |
| Ms. Ulrica Jacinta Dsa | Valnai | Mumbai Suburban |
| Mr. Reinhard Paul Dsa | Valnai | Mumbai Suburban |
| Mr. Rudolf Roland Dsa | Valnai | Mumbai Suburban |
| Mr. Clyde William Dsa | Valnai | Mumbai Suburban |
| Mr. Brence Savio Dsa | Valnai | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Mickey Links | NA | Rs 3.77 cr | Rs 2.53 cr |
| - | NA | Rs 3.77 cr | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | TEE ARCH |
| Engineer | TRIO CONSULTANTS |
| Chartered Accountant | Rawani and Co |
| Chartered Accountant | STR & ASSOCIATES |
| Partner | Role in project |
|---|---|
| JEETENDRA MURARILAL MODY | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterNA
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Mar 2025 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Jan 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Jan 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Oct 2027
Documents filed56
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1_Q1 (FY 2026-27)_JUNE 26_MICKEY LINKS.pdf | 12 Sep 2026 |
| Withdrawal Update Form 2File: FORM 2_Q1 (FY 2026-27)_JUNE 26_MICKEY LINKS.pdf | 12 Sep 2026 |
| Withdrawal Update Form 3File: FORM 3_MICKEY LINKS-JUNE 2026-SIGNED.pdf | 12 Sep 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A_FY 2024-25.pdf | 15 Jun 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A_FY 2025-26.pdf | 15 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1_Q4 (FY 2025-26)_MAR 26_MICKY LINKS.pdf | 26 May 2026 |
| Withdrawal Update Form 2File: FORM 2_Q4 (FY 2025-26)_MAR 26_MICKY LINKS.pdf | 26 May 2026 |
| Withdrawal Update Form 3File: FORM 3_MICKEY LINKS-MAR 2026-SIGNED.pdf | 26 May 2026 |
| Withdrawal Update Form 1File: FORM 1 - DEC 2025.pdf | 9 May 2026 |
| Withdrawal Update Form 2File: FORM 2 - DEC 2025.pdf | 9 May 2026 |
| Withdrawal Update Form 3File: FORM 3_MICKEY LINKS-DEC 2025-SIGNED.pdf | 9 May 2026 |
| Form 1File: FORM 1.pdf | 29 Jan 2026 |
| Form 2File: FORM 2.pdf | 29 Jan 2026 |
| Form 3File: FORM 3.pdf | 29 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD BOOKED INVENTORY.pdf | 29 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 - SEP 2025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 - SEP 2025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3_MICKEY LINKS-SEP 2025-SIGNED.pdf | 29 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 - JUNE 2025.pdf | 28 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 - JUNE 2025.pdf | 28 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3_MICKEY LINKS-JUNE 2025-SIGNED.pdf | 28 Jan 2026 |
| Proforma of Agreement for saleFile: Agreement for Sale Mickey Links 15 04 2025 Latest.pdf | 15 Apr 2025 |
| Other - LegalFile: Declaration for Plot 500 sq ft Registration.pdf | 28 Mar 2025 |
| Other - FinanceFile: Declaration for Plot 500 sq ft Registration.pdf | 28 Mar 2025 |
| Other - FinanceFile: New Undertaking (3).pdf | 27 Mar 2025 |
| Other - FinanceFile: 6 (3).pdf | 27 Mar 2025 |
| Copy of the legal title reportFile: SCAN TITLE RERA_compressed.pdf | 11 Mar 2025 |
| Proforma of Agreement for saleFile: Proforma Agreement for Sale-FNL-ML.pdf | 11 Mar 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: 1 Declaration about all RERA Designated Bank Accounts (Format A) (1).pdf | 7 Mar 2025 |
| Other - LegalFile: Corrigendum Letter MCGM -Mickey Links.pdf | 3 Mar 2025 |
| Other - FinanceFile: Corrigendum Letter MCGM -Mickey Links.pdf | 3 Mar 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format-B Bank Account REVISED.pdf | 20 Feb 2025 |
| Declaration in FORM BFile: Form-B Promoter REVISED.pdf | 18 Feb 2025 |
| Proforma of Allotment letterFile: Allotment Letter-Parking-Amenities-REA-Bank-Mickey Mody.pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate.pdf | 4 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: Legal-Finance.pdf | 24 Jan 2025 |
| Details of encumbrances concerned to FinanceFile: Legal Encumbrance-20250118015056.pdf | 24 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 CA-Reg-FINAL_compressed.pdf | 24 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer-Reg.pdf | 24 Jan 2025 |
| Details of encumbrances concerned to LegalFile: Legal-Finance.pdf | 24 Jan 2025 |
| Details of encumbrances concerned to LegalFile: Legal Encumbrance-20250118015056.pdf | 24 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect.pdf | 23 Jan 2025 |
| CERSAI detailsFile: CERSAI Undertaking Report.pdf | 23 Jan 2025 |
| Layout approvalFile: Approved IOD Drawings.pdf | 20 Jan 2025 |
| Building plan approvalFile: IOD Plan.pdf | 20 Jan 2025 |
| PAN CardFile: Jeetendra sir PAN.pdf | 20 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: Approved IOD Drawings.pdf | 20 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: First CC.pdf | 20 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: IOD Plan.pdf | 20 Jan 2025 |
| Declaration about Commencement CertificateFile: CC Declaration-20250118015239.pdf | 20 Jan 2025 |
| Deviation Report with respect to Allotment letterFile: Deviation of Allotment.pdf | 20 Jan 2025 |
| Other - TechnicalFile: Declaration of Standalone building.pdf | 20 Jan 2025 |
| Other - TechnicalFile: Declaration of Standalone building.pdf | 20 Jan 2025 |
| Deviation Report with respect to model copy of AgreementFile: Deviation of AFS-Agreement.pdf | 20 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Intrest.pdf | 20 Jan 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of Finance availed.pdf | 20 Jan 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 56 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Mickey Links on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Malad West6,700+ in Mumbai Suburban
Ruparel Stardom
AMI MODISPACES LLP
Chandak Treesourus
CHANDAK REALTORS PRIVATE LIMITED
ANCHORPOINT AVIARA
YUKTI INFRAPROJECTS LLP
AURIS ILARIA TOWER A
TRANSCON-SHETH CREATORS PRIVATE LIMITED
ADHRIT
MUNDARA DEVELOPERS
IRENE WING B PHASE 1
Sheth Creators and Sunvision Private Limit
See every Mumbai Suburban project, with the district possession charts
Builder: JEETENDRA MURARILAL MODY
JEETENDRA MURARILAL MODY has 1 registration on MahaRERA, including Mickey Links. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Mickey Links is delayed beyond 30 Oct 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mickey Links?
The registered promoter entity is JEETENDRA MURARILAL MODY, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mickey Links?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Mickey Links?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mickey Links?
The professionals named in the filing: Architect: TEE ARCH; Engineer: TRIO CONSULTANTS; Chartered Accountant: Rawani and Co; Chartered Accountant: STR & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mickey Links?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback