Home / Browse projects / Pune, Maharashtra / MERAKI LIFE - PHASE I
MERAKI LIFE - PHASE I
RG-MH-20793 · RERA P52100006228 · Last updated on MahaRERA portal: 18 Dec 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MERAKI LIFE - PHASE I is a Residential / Group Housing project by GREENSCAPE REALTY LLP in Pune, Maharashtra, registered with MahaRERA as P52100006228 on 14 Aug 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameMERAKI LIFE - PHASE I
- TypeResidential / Group Housing
- Location
- kune nm
- Kune N.m.
- Mawal
- Pune
- 410401
- Pincode410401
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100006228
- ReraGenie IDRG-MH-20793
Builder
- NameGREENSCAPE REALTY LLP
- Entity typePartnership
- PartnersDIYA SURESHKUMAR WAVIA, SURESH AMBAVI WAVIA
- Other registrations2 more →
- No longer live3 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Aug 2017
- Promised completion30 Dec 2023
- Revised completionRevised to 30 Dec 2023 (originally 30 Dec 2021)
- Buildings1 building record
- Documents filed104 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PHASE 1 | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
PHASE 1: 86% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
Progress on shared amenities15
As on 18 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 65% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 90% |
| Open Parking | Yes | 0% |
Parking filed16
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| GANPAT KONDEEBA GOJE | Kune N.m. | Pune |
| SUNEEL KONDIBA GOJE | Kune N.m. | Pune |
| HARILAL KONDIBA GOJE | Kune N.m. | Pune |
| SANJAY SAMPATKUMAR JAIN | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VASTU DESIGNERS |
| Engineer | STRUCTURAL CONCEPT DESIGNS PVT LTD |
| Chartered Accountant | KRUPA BALIA |
| Chartered Accountant | KRUPA UDAY BALIA |
| Partner | Role in project |
|---|---|
| GREENSCAPE REALTY LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe would like to apply for Time Extension of the Project Meraki life PHASEI. Due to the current COVID 19 pandemic situation we are unable to complete the Project in all respects by 30/12/2022 as mentioned in RERA.
Reason as filed by the promoterThe said plot is notified under Pune Metropolitan Region Development Authority (PMRDA). The process of obtaining CC clearance certificate as per new CC DP/MBA/KUNENAMA/S.NO.117/1/A/2 AND P. NO. 431/21-22 DT 21/09/2021 is time consuming and the current COVID pandemic scenario.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000279771 | Hiren NavinChandra Ganatra | Suresh Ambavi Wavia | 28/11/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed104
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 - April To June 2022 Q1.pdf | 18 Dec 2025 |
| Form 2File: form 2- 30-06-2022.pdf | 18 Dec 2025 |
| Form 3File: rera form 3 phase 1 june 22.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory disclosure jun22.pdf | 18 Dec 2025 |
| Form 1File: Form 1-Q2.pdf | 18 Dec 2025 |
| Form 2File: Form 2 30-09-2022.pdf | 18 Dec 2025 |
| Form 3File: sep 2022 phase 1 rfera form 3.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory disclosure .pdf | 18 Dec 2025 |
| Form 1File: Form 1 -Q3.pdf | 18 Dec 2025 |
| Form 2File: Form-02 31-12-2022.pdf | 18 Dec 2025 |
| Form 3File: Form 3 dec 2022 rera.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory disclosure .pdf | 18 Dec 2025 |
| Form 1File: Form 1.pdf | 18 Dec 2025 |
| Form 2File: from 2 31-03-2023.pdf | 18 Dec 2025 |
| Form 3File: Form 3 march2023 rera.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory disclosure.pdf | 18 Dec 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Phase I ok_compressed.pdf | 29 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 31032022 Phase I-signed.pdf | 21 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 .pdf | 19 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 .pdf | 19 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1.pdf | 19 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 .pdf | 19 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 .pdf | 19 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 .pdf | 19 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 .pdf | 19 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 .pdf | 19 Apr 2023 |
| Proforma of Agreement for saleFile: Agreement of sale.pdf | 18 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2A -2019-20.pdf | 24 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A -2020-21.pdf | 24 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A -2021-22.pdf | 24 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: Certificate - Phase I.pdf | 15 Feb 2023 |
| Details of encumbrances concerned to LegalFile: Certificate - Phase I.pdf | 15 Feb 2023 |
| Certificates of CA (Form 3)File: form 3 final.pdf | 15 Feb 2023 |
| Certificates of CA (Form 3)File: final form 3_merged.pdf | 14 Feb 2023 |
| Certificates of CA (Form 3)File: final form 3_merged.pdf | 14 Feb 2023 |
| Certificates of CA (Form 3)File: final form 3_merged.pdf | 14 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 31032022 Phase I.pdf | 14 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 24 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 24 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 24 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 24 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 24 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 24 Jan 2023 |
| Certificates of CA (Form 3)File: final form 3.pdf | 24 Jan 2023 |
| Certificates of CA (Form 3)File: final form 3.pdf | 24 Jan 2023 |
| Certificates of CA (Form 3)File: final form 3.pdf | 24 Jan 2023 |
| Certificates of CA (Form 3)File: final form 3.pdf | 24 Jan 2023 |
| Certificates of CA (Form 3)File: form 3 june 18_.pdf | 4 Jan 2023 |
| Certificates of CA (Form 3)File: form 3_merged.pdf | 4 Jan 2023 |
| Certificates of CA (Form 3)File: form 3_merged.pdf | 4 Jan 2023 |
| Certificates of CA (Form 3)File: FORM 3_merged.pdf | 4 Jan 2023 |
| Certificates of CA (Form 3)File: FORM 3_merged.pdf | 4 Jan 2023 |
| Certificates of CA (Form 3)File: FORM 3_merged.pdf | 4 Jan 2023 |
| Certificates of CA (Form 3)File: FORM 3_merged.pdf | 4 Jan 2023 |
| Certificates of CA (Form 3)File: FORM 3_merged.pdf | 4 Jan 2023 |
| Certificates of CA (Form 3)File: FORM 3_merged.pdf | 4 Jan 2023 |
| Certificates of CA (Form 3)File: FORM 3_merged.pdf | 4 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_compressed.pdf | 2 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_compressed.pdf | 2 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_compressed.pdf | 2 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_compressed.pdf | 2 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_compressed.pdf | 2 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_compressed.pdf | 2 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_compressed.pdf | 2 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_compressed.pdf | 2 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_compressed.pdf | 2 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_compressed.pdf | 2 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 31032022.pdf | 15 Dec 2022 |
| CERSAI detailsFile: Phase II CERSAI.pdf | 28 Feb 2022 |
| Declaration about Commencement CertificateFile: CC Letter.pdf | 25 Feb 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: PHASE-I.pdf | 24 Feb 2022 |
| Certificates of CA (Form 3)File: Green Escape Phase 1 new.pdf | 24 Feb 2022 |
| Declaration about Commencement CertificateFile: CC-compressed.pdf | 17 Feb 2022 |
| CERSAI detailsFile: Phase I CERSAI.pdf | 17 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 17 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 31032021 LH Phase I.pdf | 17 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - 31032019 LH Phase I.pdf | 15 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 31032020 LH Phase I.pdf | 15 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Amended Meraki Life.pdf | 25 Mar 2019 |
| Certificates of CA (Form 3)File: Meraki Life phase 1 form 3.pdf | 15 Mar 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 104 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MERAKI LIFE - PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kune N.m.13,700+ in Pune
Filed coordinates, straight-line distance. 11 registered projects within 2 km.
CANARY FARMS
CANARY FARMS
HRIDAAN HEIGHTS
R SQUARE BUILDERS AND DEVELOPERS
Amoda Reserve - South Park
Kalpataru Properties (Thane) Private Limit
Nakshatra Valley
Hariom Sai Developers
MANTRA DIVINE PHASE 2
MANTRA UNIVERSE PRIVATE LIMITED
EMERALD VILLAS
ASHWIN ARVIND SANGHVI
Builder: GREENSCAPE REALTY LLP
GREENSCAPE REALTY LLP has 3 registrations on MahaRERA, including MERAKI LIFE - PHASE I and MERAKI LIFE - PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that MERAKI LIFE - PHASE I shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if MERAKI LIFE - PHASE I is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MERAKI LIFE - PHASE I?
The registered promoter entity is GREENSCAPE REALTY LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MERAKI LIFE - PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against MERAKI LIFE - PHASE I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for MERAKI LIFE - PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MERAKI LIFE - PHASE I?
The professionals named in the filing: Architect: VASTU DESIGNERS; Engineer: STRUCTURAL CONCEPT DESIGNS PVT LTD; Chartered Accountant: KRUPA BALIA; Chartered Accountant: KRUPA UDAY BALIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MERAKI LIFE - PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback