Home / Browse projects / Udupi, Karnataka / Meera Enclave

Registration approved No litigation declared Mixed Development project

Meera Enclave

By NANDITH N PUNJA

RG-KA-53045 · RERA PRM/KA/RERA/1273/319/PR/210323/005800 · Last updated on RERA Karnataka portal: 13 Mar 2023

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Dec 2024Possession promisedmoved 12 months from the original
0 of 15Construction stages donefurthest along: Earth work and other leveling..., 0%
18 of 18Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 105 documents Report an error

Meera Enclave is a Mixed Development project by NANDITH N PUNJA in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/319/PR/210323/005800 on 21 Mar 2023. Possession is promised by 27 Dec 2024. The completion date has moved by 12 months from the original filing. 0 of the 18 units on this registration are recorded sold or booked, and 0 of 15 construction stages are filed complete.

At a glance

Project

  • NameMeera Enclave
  • TypeMixed Development
  • Location
    • Karkala
    • Udupi
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1273/319/PR/210323/005800
  • ReraGenie IDRG-KA-53045

Builder

  • NameNANDITH N PUNJA
  • Entity typeProprietorship Firm
  • GSTIN29CHGPP9045M1ZI
  • Authorized SignatoryNANDITH N PUNJA

Key dates

this monthRegisteredMar 2023First promiseDec 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Mar 2023
  • Promised completion27 Dec 2024
  • Revised completionRevised to 27 Dec 2024 (originally 27 Dec 2023)
  • Buildings2 building records
  • Documents filed105 files

Current status

0%0 of 18 units booked

Figures as on 13 Mar 2023, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block 1-----13
Block 2-----5

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 15 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.

Building: 0% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 13 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes-
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
NANDITH N PUNJA--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.61 cr
BuildingWingEstimatedIncurred
-NARs 2.60 cr-
-NARs 70,183-
-NARs 1,675-
-NARs 100-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYashwanth Kumar Rai
EngineerYashwanth Kumar Rai
Chartered AccountantColine O Rodrigues

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1273/319/PR/241001/005800Dec 2023 → Dec 2024

Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed105

As listed on the registration, under the names the promoter filed them with; the newest 80 of 105 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/319/PR/210323/005800 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
1. CA Certificate for FY 2019-20.File: CA Certificate for FY 2019-20Com.pdf13 Mar 2023
2. AffidavitFile: Affidavit.pdf13 Mar 2023
1. Engineer CertificateFile: PROGRESS REPORT.pdf10 Feb 2023
2. Proforma of Allotment letterFile: ALLOTMENT LETTER AS PER RERA FORMAT- FEB 2023.pdf10 Feb 2023
1. CA Certificate for FY 2019-20File: CA Certificate for FY 2019-20 compressed.pdf19 Jan 2023
2. CA Certificate for FY 2020-21File: Nandith- CA Cert- Turnover 20-21.pdf19 Jan 2023
3. Balance Sheet & Profit & loss account for the FY 2021-22File: BS & P&L- FY 21-22_Up.pdf19 Jan 2023
4. Conversion orderFile: Conversion order.pdf19 Jan 2023
5. Non litigation affidavitFile: NON LITIGATION AFFIDAVIT.pdf19 Jan 2023
6. Single plot layout OrderFile: Layout Order.pdf19 Jan 2023
7. Single layout planFile: Proposed - Single Layout Plan.pdf19 Jan 2023
8. Proforma of Allotment LetterFile: ALLOTMENT LETTER AS PER RERA FORMAT.pdf19 Jan 2023
1. Form -01 CA CertificateFile: FORM 1 certificate-Meera Enclave.pdf22 Dec 2022
2. CA Certificate for the FY 20-21File: Nandith- CA Cert- Turnover 20-21.pdf22 Dec 2022
3. Marriage AffidavitFile: Marriage Affidavit- Name Change.pdf22 Dec 2022
4. Gift deedFile: Gift deed.pdf22 Dec 2022
5. Form bFile: Form B- Non litigation Affidavit.pdf22 Dec 2022
6. Single Plot layout orderFile: Layout Order.pdf22 Dec 2022
7. Building sanction PlanFile: Building Sanction plan- original.jpg22 Dec 2022
8. Building sanction PlanFile: Building Sanction plan- original.jpg22 Dec 2022
9. Proforma of AFSFile: AFS_merged.pdf22 Dec 2022
10. Proforma of Allotment LetterFile: ALLOTEMENT LETTER.pdf22 Dec 2022
1. Form -01- CA CertificateFile: FORM 1 -Pre Registration certificate-Meera Enclave.pdf26 Nov 2022
2. Profit and loss account and balance sheet for the FY 21-22File: CA Certificate with UDIN FY 19-20 to 21-22.pdf26 Nov 2022
3. Certified title deed of nandith .n .panjaFile: Gift deed.pdf26 Nov 2022
4. Form -BFile: Form B.pdf26 Nov 2022
5.a. RTCFile: RTC.pdf26 Nov 2022
5.a. MRFile: Mutation Register- Form 12.pdf26 Nov 2022
5.c conversion order- Gift DeedFile: Gift deed.pdf26 Nov 2022
6. ECFile: Form 16_Form-15_merged- EC.pdf26 Nov 2022
7. AffidavitFile: Affidavit.pdf26 Nov 2022
8. Single plot layout.File: Form 9.pdf26 Nov 2022
9. certified Carpet area calculationFile: Certified Carper area-1.pdf26 Nov 2022
10. village map showing the proposed site.File: Sketchh- Village map.pdf26 Nov 2022
11. Clear and legible Building sanction Plan.File: SKETCH_rotated (1).pdf26 Nov 2022
12. certified Plinth areaFile: Certified Plinth Area_page.pdf26 Nov 2022
13. a. CA certificateFile: FORM 1 -Pre Registration certificate-Meera Enclave.pdf26 Nov 2022
13.b. Engineer certificateFile: Engineer Certificate.pdf26 Nov 2022
14. Engineer Certificate indicating the structural safety for the proposed buildingFile: Structural Safety.pdf26 Nov 2022
15. signed copy of the project specification in the letter headFile: Project Specification.pdf26 Nov 2022
16. notarized affidavitFile: Affidavit.pdf26 Nov 2022
17.a. proforma of Agreement for saleFile: Sale agreement.pdf26 Nov 2022
17.b Proforma of Allotement letterFile: Sale deed.pdf26 Nov 2022
18. NOC issued by Power supply and water supply alongwith the copy of fee receipt paid towards NOCFile: NOC- MESCOM_merged.pdf26 Nov 2022
19. STP/Septic Tank, Soak pit and sewer line system demarcation drawing of the projectFile: Sketchh-Tank_compressed.pdf26 Nov 2022
RTC, survey 60/3-
Mutation, survey 60/3-
Encumbrance Certificate, survey 60/3-
Sale/Title/Gift Deed, survey 60/3-
Khatha, survey 60/3-
Registration CertificateFile: GST Reg certfcte.pdf-
Certificate issued by CA Form 1File: FORM 1 -Pre Registration certificate-Meera Enclave_compressed.pdf-
Certificate issued by Architect Form 2File: Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Legal opinion.pdf-
Certificate from Chartered Account-
Balance Sheet 2021 - 2022File: BS- To upload-1.pdf-
Balance Sheet 2020 - 2021File: BS-20-21.pdf-
Audited Profit and Loss Statement 2021 - 2022File: P&L-To upload.pdf-
Audited Profit and Loss Statement 2020 - 2021File: P&L 20-21.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR V - Acknowlegment.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR- 20-21.pdf-
Building Licence- New-
Layout plan-
Layout plan-
Layout plan-
Layout plan-
Layout plan-
Brochure_compressed-
Brochure-
Layout plan-
Legal opinion-
Form 9_compressed-
merged_compressed-
Sale deed-
Brochure_compressed-
Affidavit-

How this compares with Udupi

0%of this project is bookeddistrict median 0%
22%of Udupi projects moved their completion datethis one moved by 12 months
0%of Udupi registrations have lapsed or been cancelledthis one is on the register

Computed across the 260+ Udupi projects on ReraGenie, from their own filings.

Keep Meera Enclave on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Udupi260+ in Udupi

Builder: NANDITH N PUNJA

NANDITH N PUNJA has 1 registration on RERA Karnataka, including Meera Enclave. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Udupi district page.

Frequently asked questions

What are my rights if Meera Enclave is delayed beyond 27 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Meera Enclave?

The registered promoter entity is NANDITH N PUNJA, a proprietorship firm as per the filing. Its GSTIN 29CHGPP9045M1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Meera Enclave?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Meera Enclave?

The professionals named in the filing: Architect: Yashwanth Kumar Rai; Engineer: Yashwanth Kumar Rai; Chartered Accountant: Coline O Rodrigues. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Meera Enclave?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Meera Enclave. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Meera Enclave to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.