Home / Browse projects / Thane, Maharashtra / MAYURESH SHRUSHTI PHASE-1

Registration lapsed No litigation declared Plotted project

MAYURESH SHRUSHTI PHASE-1

By J. K. INFRA

RG-MH-73702 · RERA P51700012835 · Last updated on MahaRERA portal: 4 Aug 2017

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 85 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2019Possession promised85 months past this date
19 of 101Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 22 documents Report an error

MAYURESH SHRUSHTI PHASE-1 is a Plotted project by J. K. INFRA in Thane, Maharashtra, registered with MahaRERA as P51700012835 on 7 Sep 2017. Possession was promised by 30 Sep 2019 and is now 85 months past that date. 82 of the 101 units on this registration are recorded sold or booked.

At a glance

Project

  • NameMAYURESH SHRUSHTI PHASE-1
  • TypePlotted
  • Location
    • Vashala Bk
    • Shahapur
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700012835
  • ReraGenie IDRG-MH-73702

Builder

  • NameJ. K. INFRA
  • Entity typePartnership
  • PartnersNILESH PARDESHI, RAJAN JADHAV
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

85 months past promisethis monthRegisteredSep 2017PromisedSep 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Sep 2017
  • Promised completion30 Sep 2019
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed22 files

Current status

81%82 of 101 units booked

Figures as on 4 Aug 2017, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Aug 2017, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 4 Aug 2017, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes30%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes30%
Street LightingYes30%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes20%
Water conservation /Rain water harvestingYes30%
Energy managemcntYes20%
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceYes20%
Open ParkingYes10%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area38,840 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI38840.0
Proposed, not sanctioned38,840 sq m

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAMAN SMRUTI,KARANI ROAD,NEAR TELEPHONE EXCHANGE 400086

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMONIK AJAY SHAH
PartnerRole in project
J. K. INFRA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed22

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Copy of the legal title reportFile: gutno89.pdf4 Aug 2017
Copy of the legal title reportFile: rajan 88.pdf4 Aug 2017
Proforma of Allotment letterFile: model.pdf4 Aug 2017
Proforma of Allotment letterFile: gut98.pdf4 Aug 2017
Layout approvalFile: PLAN LAYOUT PIC.pdf31 Jul 2017
Building plan approval or NA orderFile: iod.pdf31 Jul 2017
PAN CardFile: J K INFRA PAN CARD.pdf31 Jul 2017
Copy of the legal title reportFile: gut no98.pdf31 Jul 2017
Copy of the legal title reportFile: gut no 76 title search.pdf31 Jul 2017
Copy of the legal title reportFile: gut no 88 title.pdf31 Jul 2017
Copy of the legal title reportFile: 89.pdf31 Jul 2017
Copy of the legal title reportFile: gut no 90.pdf31 Jul 2017
Copy of the legal title reportFile: gut no91.pdf31 Jul 2017
Details of encumbrancesFile: litigation.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: PLAN LAYOUT PIC.pdf31 Jul 2017
Building Plan Approval (IOD)File: iod.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf31 Jul 2017
Declaration in FORM BFile: FORM NO B.pdf31 Jul 2017
Declaration in FORM BFile: autho sign.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM NO1.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: ca cert form3.pdf31 Jul 2017

How this compares with Thane

81%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAYURESH SHRUSHTI PHASE-1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vashala Bk7,600+ in Thane

Builder: J. K. INFRA

J. K. INFRA has 2 registrations on MahaRERA, including MAYURESH SHRUSHTI PHASE-1 and J K KASTURI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that MAYURESH SHRUSHTI PHASE-1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MAYURESH SHRUSHTI PHASE-1 is delayed beyond 30 Sep 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAYURESH SHRUSHTI PHASE-1?

The registered promoter entity is J. K. INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAYURESH SHRUSHTI PHASE-1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MAYURESH SHRUSHTI PHASE-1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAYURESH SHRUSHTI PHASE-1?

The professionals named in the filing: Architect: MONIK AJAY SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAYURESH SHRUSHTI PHASE-1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAYURESH SHRUSHTI PHASE-1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAYURESH SHRUSHTI PHASE-1 to a free account