Registered No litigation declared Residential / Group Housing projectRedevelopment

Mayura

By Badhekar Properties

RG-MH-16393 · RERA P52100025819 · Last updated on MahaRERA portal: 22 Oct 2026

Why this is marked a redevelopment: this filing shows 23 flats filed as rehab units, MahaRERA's column for homes returned to existing occupants or owners. MahaRERA has no redevelopment field, so this is ReraGenie's reading of the filing. Redevelopment across Pune.

Source: official MahaRERA filing

Red flags

  • Completion date moved by 23 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 23 months from the original
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
35 of 61Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 385 documents Report an error

Mayura is a Residential / Group Housing project by Badhekar Properties in Pune, Maharashtra, registered with MahaRERA as P52100025819 on 18 Jul 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 23 months from the original filing. 26 of the 61 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameMayura
  • TypeResidential / Group Housing
  • Location
    • Paud Road
    • Kothrud
    • Haveli
    • Pune
    • 411038
  • Pincode411038
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100025819
  • ReraGenie IDRG-MH-16393

Builder

  • NameBadhekar Properties
  • Entity typePartnership
  • GSTIN27AATFB0231F1ZP
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerHrishikesh Shivajirao Dhobale Patil
  • Other registrations6 more →
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2020First promiseJan 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Jul 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Jan 2025)
  • Buildings1 building record
  • Documents filed385 files

Current status

43%26 of 61 units booked
55.6%Work done, per cost certificate

Figures as on 22 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MayuraNA191561061

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Mayura: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed157

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots157
Closed/Covered40
Open Space117

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,000 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Nov 2025

Approvals and building plan

Sanctioning authorityPune Muncipal Corporation
Permissible FSI3159.0
Proposed, not sanctioned965 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSargam Apartment, Near Vanaz Corner, Gujrath colony, Kothrud, Pune 411038
Estimated costRs 27.49 cr
Cost incurredRs 15.30 cr
Work done55.63%
BuildingWingEstimatedIncurred
MayuraNARs 24.54 crRs 13.86 cr
-NARs 2.96 crRs 1.43 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectParas Netragaonkar
ArchitectSHILPI ARCHITECTS AND PLANNERS
EngineerG A Bhilare
EngineerDipali Kulkarni
Chartered AccountantShrikant Mantri
Chartered AccountantDinesh Gandhi
Chartered AccountantD.B.GANDHI & ASSOCIATES
Chartered AccountantSHRIKANT MANTRI AND CO.
PartnerRole in project
Badhekar Properties-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025293Jan 2025 → Jan 2026

Reason as filed by the promoterThis is to confirm that we have already almost completed our project. There were some changes on site due to which we need to take revised sanction as per actual site conditions, for which we need to apply for RERA Extension. Please grant us extension for our above project. If necessary, we can share pictures of our project current status via mail with you. Let us know if we need to share the same.

EA07102639045Jan 2025 → Dec 2026

Reason as filed by the promoterOur Project is already completed and we have received full completion on 04/08/2025. However, as our project is lapsed, we are instructed to apply for extension, then correction, after which our Completion application will be accepted.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Jul 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Feb 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Oct 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Oct 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed385

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 385 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: 1-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 2-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 3-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 4-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 5-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 6-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 7-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 8-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 9-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 10-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 11-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 12-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 13-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 14-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 15-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 16-17_compressed.pdf22 Oct 2026
Building plan approvalFile: 17-17_compressed.pdf22 Oct 2026
Commencement certificateFile: CC.pdf22 Oct 2026
Withdrawal Update Form 1File: Architect Certificate Mayura Mar 25.pdf22 Oct 2026
Withdrawal Update Form 1File: Architect Certificate Mayura Mar 25.pdf22 Oct 2026
Withdrawal Update Form 1File: Architect Certificate Mayura Mar 25.pdf22 Oct 2026
Withdrawal Update Form 2File: Engineers Certificate Mayura site Mar-25.pdf22 Oct 2026
Withdrawal Update Form 2File: Engineers Certificate Mayura site Mar-25.pdf22 Oct 2026
Withdrawal Update Form 2File: Engineers Certificate Mayura site Mar-25.pdf22 Oct 2026
Withdrawal Update Form 3File: Mayura RERA Form 3 Mar-25 Scan_compressed (1).pdf22 Oct 2026
Withdrawal Update Form 3File: Mayura RERA Form 3 Mar-25 Scan_compressed (1).pdf22 Oct 2026
Withdrawal Update Form 3File: Mayura RERA Form 3 Mar-25 Scan_compressed (1).pdf22 Oct 2026
Form 2A (FY 2026-2027)File: Form 2A-Engineers Certificate 26-27 - scan.pdf22 Oct 2026
Form 5 (FY 2025-2026)File: Tungbhadra FY 24-25 RERA 5 Scan.pdf2 Oct 2026
Withdrawal Update Form 1File: Architect Certificate Mayura Mar 25.pdf25 Jul 2026
Withdrawal Update Form 1File: Architect Certificate Mayura Mar 25.pdf25 Jul 2026
Withdrawal Update Form 2File: Engineers Certificate Mayura site Mar-25.pdf25 Jul 2026
Withdrawal Update Form 2File: Engineers Certificate Mayura site Mar-25.pdf25 Jul 2026
Withdrawal Update Form 3File: Mayura RERA Form 3 Mar-25 Scan_compressed (1).pdf25 Jul 2026
Withdrawal Update Form 3File: Mayura RERA Form 3 Mar-25 Scan_compressed (1).pdf25 Jul 2026
Withdrawal Update Form 1File: Architect Certificate Mayura Mar 25.pdf24 Jul 2026
Withdrawal Update Form 1File: Architect Certificate Mayura Mar 25.pdf24 Jul 2026
Withdrawal Update Form 2File: Engineers Certificate Mayura site Mar-25.pdf24 Jul 2026
Withdrawal Update Form 2File: Engineers Certificate Mayura site Mar-25.pdf24 Jul 2026
Withdrawal Update Form 3File: Mayura RERA Form 3 Mar-25 Scan_compressed (1).pdf24 Jul 2026
Withdrawal Update Form 3File: Mayura RERA Form 3 Mar-25 Scan_compressed (1).pdf24 Jul 2026
Form 5 (FY 2020-2021)File: Form 5 Mayura 20-21.pdf26 Mar 2026
Form 5 (FY 2023-2024)File: Mayura Form 5 - 23-24.pdf26 Mar 2026
Form 5 (FY 2024-2025)File: Mayura FY 24-25 RERA Form 5 Scan.pdf26 Mar 2026
Form 2A (FY 2025-2026)File: Form 2A Engineers certificate Mayura 25-26.pdf21 Jan 2026
Building plan approvalFile: 1.pdf26 Nov 2025
Building plan approvalFile: 2.pdf26 Nov 2025
Building plan approvalFile: 3.pdf26 Nov 2025
Building plan approvalFile: 4.pdf26 Nov 2025
Building plan approvalFile: 5.pdf26 Nov 2025
Building plan approvalFile: 6.pdf26 Nov 2025
Building plan approvalFile: 7.pdf26 Nov 2025
Building plan approvalFile: 8.pdf26 Nov 2025
Building plan approvalFile: 9.pdf26 Nov 2025
Building plan approvalFile: 10.pdf26 Nov 2025
Building plan approvalFile: 11.pdf26 Nov 2025
Building plan approvalFile: 12.pdf26 Nov 2025
Building plan approvalFile: 13.pdf26 Nov 2025
Building plan approvalFile: 14.pdf26 Nov 2025
Building plan approvalFile: 15.pdf26 Nov 2025
Building plan approvalFile: 16.pdf26 Nov 2025
Building plan approvalFile: 17.pdf26 Nov 2025
Form 1File: Architect’s Certificate - Mayura May 2021.pdf26 Nov 2025
Form 1File: Architect’s Certificate - Mayura May 2021.pdf26 Nov 2025
Form 1File: Architect’s Certificate - Mayura May 2021.pdf26 Nov 2025
Form 1File: Engineer’s Certificate - Mayura Jul 2020.pdf26 Nov 2025
Form 1File: Engineer’s Certificate - Mayura Jul 2020.pdf26 Nov 2025
Form 1File: Engineer’s Certificate - Mayura Jul 2020.pdf26 Nov 2025
Form 1File: Disclosure of sold_ booked inventory Dec 22.pdf26 Nov 2025
Form 2File: Architect’s Certificate - Mayura May 2021.pdf26 Nov 2025
Form 2File: Architect’s Certificate - Mayura May 2021.pdf26 Nov 2025
Form 2File: Architect’s Certificate - Mayura May 2021.pdf26 Nov 2025
Form 2File: Engineer’s Certificate - Mayura Jul 2020.pdf26 Nov 2025
Form 2File: Engineer’s Certificate - Mayura Jul 2020.pdf26 Nov 2025
Form 2File: Engineer’s Certificate - Mayura Jul 2020.pdf26 Nov 2025
Form 2File: Disclosure of sold_ booked inventory Dec 22.pdf26 Nov 2025
Form 3File: Architect’s Certificate - Mayura May 2021.pdf26 Nov 2025
Form 3File: Architect’s Certificate - Mayura May 2021.pdf26 Nov 2025
Form 3File: Architect’s Certificate - Mayura May 2021.pdf26 Nov 2025
Form 3File: CA Certificate - Mayura Jun 2020.pdf26 Nov 2025

How this compares with Pune

43%of this project is bookeddistrict median 29%
28%of Pune projects moved their completion datethis one moved by 23 months
25%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mayura on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kothrud14,000+ in Pune

2 kmMayuraCompleted 84Lapsed / revoked 42Other 186Dot size: filed unitsN

Filed coordinates, straight-line distance. 312 registered projects within 2 km.

Builder: Badhekar Properties

Badhekar Properties has 7 registrations on MahaRERA, including Mayura and Keshar. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 4 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Mayura is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mayura?

The registered promoter entity is Badhekar Properties, a partnership as per the filing. Its GSTIN 27AATFB0231F1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mayura?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mayura?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mayura?

The professionals named in the filing: Architect: Paras Netragaonkar; Architect: SHILPI ARCHITECTS AND PLANNERS; Engineer: G A Bhilare; Engineer: Dipali Kulkarni; Chartered Accountant: Shrikant Mantri; Chartered Accountant: Dinesh Gandhi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mayura?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mayura. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mayura to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.