Home / Browse projects / Pune, Maharashtra / Marvel Ribera A Building
Marvel Ribera A Building
RG-MH-09874 · RERA P52100002377 · Last updated on MahaRERA portal: 28 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 9 complaints at MahaRERA
- Completion date moved by 78 months
- 4 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Marvel Ribera A Building is a Residential / Group Housing project by RIBERA PROJECTS LLP in Pune, Maharashtra, registered with MahaRERA as P52100002377 on 31 Jul 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 78 months from the original filing. 19 of the 37 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 9 complaints are on record with the regulator.
At a glance
Project
- NameMarvel Ribera A Building
- TypeResidential / Group Housing
- Location
- -
- Pune (M Corp.)
- Pune City
- Pune
- 411001
- Pincode411001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100002377
- ReraGenie IDRG-MH-09874
Builder
- NameRIBERA PROJECTS LLP
- Entity typePartnership
- PartnersSURESH BHANWARLAL GATTANI, MEGHARAJ PROPERTIES PRIVATE LIMITED
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Jul 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2019)
- Buildings1 building record
- Documents filed138 files
Current status
Figures as on 28 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 20 | 16 | 37 | 0 | 37 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 95%.
A: 78% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 95% |
| Plinth | 90% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 28 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 20% |
| Water Supply | Yes | 10% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 20% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 30% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 30% |
| Energy managemcnt | Yes | 20% |
| Fire protection and fire safety requirements | Yes | 35% |
| Electrical meter room, sub-station, receiving station | Yes | 30% |
| Aggregate area of recreational Open Space | Yes | 20% |
| Open Parking | No | Not applicable |
Parking filed168
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 36.94 cr | Rs 34.99 cr |
| - | NA | Rs 7.55 cr | Rs 2.18 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SUMIT VERMA |
| Engineer | Nitin Mohanlal Jain |
| Chartered Accountant | AKSHAY SUNIL KHANDALE |
| Partner | Role in project |
|---|---|
| RIBERA PROJECTS LLP | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to impact of COVID 2019 Project has been delayed.
Reason as filed by the promoterAdverse market condition and money dismemberment issue form bank
Reason as filed by the promoter80% OF THE CONSTRUCTION IS COMPLETED. WE NEED EXTENSION TO COMPLETE THE REMAINING CONSTRUCTION OF THE PROJECT.
Reason as filed by the promoterThe construction work for the project has been completed up to 90%. Completion Certificate has already been received for 7 flats. To complete the balance 10% of the work and obtain the Completion Certificate for the remaining units, we request an extension of time.
Complaints filed with MahaRERA9
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000010505 | CHEMRON TEXCHEM PRIVATE LIMITED | MARVEL SIGMA HOMES PRIVATE LIMITED | 08/11/2017 |
| CC005000000010528 | Rustam Phiroze Mehta | Marvel Dwellings Private Limited | 06/11/2017 |
| CC005000000022205 | Zarin Watson | MARVEL DWELLINGS PRIVATE LIMITED | 16/11/2018 |
| CC005000000054016 | Zarin Watson | ISIS CONSULTANCY SERVICES | 07/02/2020 |
| CC12400357 | Farah Zaheer Vakil | RIBERA PROJECTS LLP | 07/10/2024 |
| CC12400340 | Dilrez Gopal | RIBERA PROJECTS LLP | 05/10/2024 |
| SM12500093 | Ram Gawali | RIBERA PROJECTS LLP | 28/08/2025 |
| SM12500107 | Ram Gawali | RIBERA PROJECTS LLP | 02/09/2025 |
| CC12601617 | Wadhwa Group Holdings Private Limited | RIBERA PROJECTS LLP | 23/03/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed138
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 138 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A -25-26.PDF | 28 Jul 2026 |
| Form 5 (FY 2025-2026)File: Form 5 - Ribera Projects LLP - Final Signed.pdf | 28 Jul 2026 |
| Form 2A (FY 2023-2024)File: Form 2A_Signed.pdf | 26 Jun 2026 |
| Form 5 (FY 2022-2023)File: Ribera Form 5 -2022-23.PDF | 26 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Dec25.pdf | 7 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Dec25.pdf | 7 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Dec25.pdf | 7 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Dec25.pdf | 7 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Dec25.pdf | 7 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Dec25.pdf | 7 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Sept25.pdf | 11 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 - Sept25.pdf | 11 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 - Sept25.pdf | 11 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 - Sept25.pdf | 11 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 - Sept25.pdf | 11 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 - Sept25.pdf | 11 Dec 2025 |
| Withdrawal Update Form 3File: CA Certificate Form 3_RERA_Sept 25.pdf | 11 Dec 2025 |
| Withdrawal Update Form 3File: CA Certificate Form 3_RERA_Sept 25.pdf | 11 Dec 2025 |
| Withdrawal Update Form 3File: CA Certificate Form 3_RERA_Sept 25.pdf | 11 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 - Sept25.pdf | 18 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 - Sept25.pdf | 18 Nov 2025 |
| Withdrawal Update Form 3File: CA Certificate Form 3_RERA_Sept 25.pdf | 18 Nov 2025 |
| Withdrawal Update Form 1File: Ribera - Form 1 - Junu002725.pdf | 11 Nov 2025 |
| Withdrawal Update Form 2File: Ribera - Form 2 - Junu002725.pdf | 11 Nov 2025 |
| Withdrawal Update Form 3File: Ribera - Form 3 - Junu002725.pdf | 11 Nov 2025 |
| Form 5 (FY 2024-2025)File: Ribera Projects LLP - Form 5 (Signed).pdf | 7 Oct 2025 |
| Form 1File: Form 1- March 25.pdf | 23 Sep 2025 |
| Form 2File: Form 2-March 25.pdf | 23 Sep 2025 |
| Form 3File: Form 3 - March 25.pdf | 23 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Inventory - March 25.pdf | 23 Sep 2025 |
| OthersFile: Form 2A - March 25.pdf | 23 Sep 2025 |
| Form 2A (FY 2024-2025)File: Form 2A - March 25.pdf | 23 Sep 2025 |
| Form 1File: Form 1 - Dec24.pdf | 26 May 2025 |
| Form 2File: Form 2 - Dec24.pdf | 26 May 2025 |
| Form 3File: Form 3 - Dec24.pdf | 26 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory - Dec24.pdf | 26 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Qtr Sept24.pdf | 27 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Qtr Sept24.pdf | 27 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: RPLLP - Sold Unsold Inventory 30 Sept 2024_FINAL.pdf | 27 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 CA CERTIFICATE.pdf | 21 Oct 2024 |
| Declaration in FORM BFile: Form B - Notarised.pdf | 19 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ARCHITECT.pdf | 19 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 ENGINEER CERTIFICATE.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 19 Oct 2024 |
| PAN CardFile: PAN - Ribera Projects LLP.pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Details_Mar-24.pdf | 10 Aug 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf | 10 Aug 2024 |
| Certificates of CA (Form 3)File: Declaration_CA Certificate.pdf | 8 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 22 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 22 Jul 2024 |
| Proforma of Agreement for saleFile: Ribera Draft Agreement.pdf | 1 Jun 2024 |
| Details of encumbrancesFile: MSHPL_NDC_ICICIHFC.pdf | 15 May 2024 |
| Details of encumbrancesFile: MSHPL_NDC_ICICI Bank.pdf | 15 May 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Sold Unsold format 31-12-2023.pdf | 10 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Sold Unsold format 31-12-2023 (1).pdf | 10 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold 31 03 2023_24012024123241.PDF | 27 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold 30 06 2023_24012024152102.PDF | 27 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold 30 09 2023_24012024152144.PDF | 27 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold 31 12 2023_24012024152214.PDF | 27 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31 03 2020_22012024125756.PDF | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31 03 2021_22012024130302.PDF | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 21 12 2021_22012024130335.PDF | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31 03 2022_22012024130439.PDF | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30 06 2022_22012024130536.PDF | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30 09 2022_22012024130622.PDF | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31 12 2022_22012024130128.PDF | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31 03 2023_22012024130214.PDF | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30 06 2023_22012024125933.PDF | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30 09 2023_22012024130039.PDF | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31 12 2023_22012024125843.PDF | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31 03 2018_22012024120119.PDF | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31 03 2019_22012024120224.PDF | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31 03 2020_22012024120318.PDF | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31 03 2021_22012024120415.PDF | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 21 12 2021_22012024120530.PDF | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31 03 2022_22012024120659.PDF | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30 06 2022_22012024120951.PDF | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30 09 2022_22012024121537.PDF | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31 12 2022_22012024121636.PDF | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31 03 2023_22012024121730.PDF | 25 Jan 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 138 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Marvel Ribera A Building on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pune (M Corp.)13,700+ in Pune
Filed coordinates, straight-line distance. 36 registered projects within 2 km.
HUES OF SKY
Bramhacorp Limited
Birla Punya Phase II
Birla Estates Private Limited
Birla Punya Phase 1
Birla Estates Private Limited
BOULEVARD TOWER A2
Bramhacorp Limited
One Place-Bund Garden Road
TOPSPACE LANDMARKS LLP
Eternia Phase 2
VENTURESPRO PROJECTS LLP
Builder: RIBERA PROJECTS LLP
RIBERA PROJECTS LLP has 1 registration on MahaRERA, including Marvel Ribera A Building. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Marvel Ribera A Building shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Marvel Ribera A Building is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Marvel Ribera A Building?
The registered promoter entity is RIBERA PROJECTS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Marvel Ribera A Building?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Marvel Ribera A Building?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Marvel Ribera A Building?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Marvel Ribera A Building?
The professionals named in the filing: Architect: SUMIT VERMA; Engineer: Nitin Mohanlal Jain; Chartered Accountant: AKSHAY SUNIL KHANDALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Marvel Ribera A Building?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback