Home / Browse projects / Mumbai Suburban, Maharashtra / MARVEL PRIDE

Registered No litigation declared Residential / Group Housing project

MARVEL PRIDE

By Marvellous Builders Private Limited

RG-MH-97570 · RERA P51800003921 · Last updated on MahaRERA portal: 2 Jun 2026

Source: official MahaRERA filing

Red flags

  • 5 complaints at MahaRERA
  • Completion date moved by 85 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedmoved 85 months from the original
5Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

MARVEL PRIDE is a Residential / Group Housing project by Marvellous Builders Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003921 on 7 Aug 2017. Possession is promised by 31 Oct 2027. The completion date has moved by 85 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameMARVEL PRIDE
  • TypeResidential / Group Housing
  • Location
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003921
  • ReraGenie IDRG-MH-97570

Builder

  • NameMarvellous Builders Private Limited
  • Entity typeCompany
  • DirectorsYuvraj Bhau Kanade, Abhishek Pednekar

Key dates

this monthRegisteredAug 2017First promiseSep 2020Revised toOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Aug 2017
  • Promised completion31 Oct 2027
  • Revised completionRevised to 31 Oct 2027 (originally 30 Sep 2020)
  • Buildings1 building record
  • Documents filed56 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MARVEL PRIDENA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

MARVEL PRIDE:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 2 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed21

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots21
Closed/Covered1
Open Space20

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area767 sq m
Land owned byThe promoter, with other names on the file
Named landownersNone

Approvals and building plan

Permissible FSI2067.36
Proposed, not sanctioned1,013 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCENTRAL PLAZA, GR FLOOR, 166 CST ROAD, KALINA, SANTACRUZ EAST, MUMBAI 400098

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Marvellous Builders Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800028200Sep 2020 → Oct 2027

Reason as filed by the promoterRespected Sir, The project was registered by erstwhile developer who did not complete the project despite getting ample opportunity. Therefore, we as landowners terminated the development agreement and decided to take ahead and complete the project. Accordingly, we have now been appointed as Promoter u/s. 15 of the RERA Act and also received consents from the Allottees in the project. We wish to complete the project at earliest and therefore request you to grant extension to registration of the project so that we can proceed with sales and marketing to monetize the balance inventory and invest

Litigation declared1

CaseCourtStatus
1952/2006BOMBAY HIGH COURTSETTLED OUT OF COURT COPY ATTACHED

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000055901Madhukar V UllalM/s Solitaire Inn Hotel Co04/09/2018
CC006000000197866JITENDRA SHAHM S SOLITAIRE INN HOTEL CO03/08/2021
CC006000000198356NAYNA SHAHM S GCON TECH PRIVATE LIMITED27/09/2021
CC006000000396171YOGESH SURTIMS SOLITAIRE INN HOTEL CO22/06/2023
CC006000000408615SHILPA DESHPANDEM/S MARVELLOUS BUILDERS PRIVATE LIMITED03/01/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2027

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 - Marvel Pride as on March 2026.pdf2 Jun 2026
Form 2File: Form 2 - Marvel Pride as on March 2026.pdf2 Jun 2026
Form 3File: Form 3 - Marvel Pride as on March 2026.pdf2 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Marvel Pride as on March 2026.pdf2 Jun 2026
Form 1File: Form 1 - Marvel Pride as on Dec 2025.pdf13 May 2026
Form 2File: Form 2 - Marvel Pride as on Sep 2025.pdf13 May 2026
Form 3File: Form 3 - Marvel Pride as on Sep 2025.pdf13 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Marvel Pride as on Sep 2025.pdf13 May 2026
Form 1File: Form 1 - Marvel Pride as on Dec 2025.pdf13 May 2026
Form 2File: Form 2 - Marvel Pride as on Sep 2025.pdf13 May 2026
Form 3File: Form 3 - Marvel Pride as on Sep 2025.pdf13 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Marvel Pride as on Sep 2025.pdf13 May 2026
Form 1File: Form 1 - Marvel Pride as on Dec 2025.pdf13 May 2026
Form 2File: Form 2 - Marvel Pride as on Dec 2025.pdf13 May 2026
Form 3File: Form 3 - Marvel Pride as on Dec 2025.pdf13 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Marvel Pride as on Dec 2025.pdf13 May 2026
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Form-5-CA Annual Report for m25-Signed-250522.pdf22 May 2025
Other - TechnicalFile: Marvel Pride_FORM 2A.pdf19 May 2025
Disclosure of sold/ booked inventoryFile: 202503_Sold.pdf6 May 2025
Declaration in FORM BFile: Affidavit.pdf28 Apr 2025
Disclosure of sold/ booked inventoryFile: 202412 Sold.pdf26 Apr 2025
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf22 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202412_Form-1.pdf15 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202503_Form-1.pdf15 Apr 2025
Certificates of CA (Form 3)File: 202412_Form-3.pdf15 Apr 2025
Certificates of CA (Form 3)File: 202503 Form3 compressed.pdf15 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202412_Form-2.pdf15 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202503_Form-2.pdf15 Apr 2025
Building plan approvalFile: Building Plan Approval (IOD).pdf31 Jul 2017
Layout approvalFile: FSI PLAN 1 APPROVED.pdf31 Jul 2017
Layout approvalFile: FSI PLAN 2 APPROVED.pdf31 Jul 2017
Layout approvalFile: FSI PLAN 3 APPROVED.pdf31 Jul 2017
Layout approvalFile: Full FSI Comm 1.pdf31 Jul 2017
Layout approvalFile: Full FSI Comm 2.pdf31 Jul 2017
Layout approvalFile: Full FSI Comm 3.pdf31 Jul 2017
PAN CardFile: PAN OF SOLITAIRE.pdf31 Jul 2017
Copy of the legal title reportFile: Title Report min.pdf31 Jul 2017
Details of encumbrancesFile: Certificate of Encumberance.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: FSI PLAN 1 APPROVED.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: FSI PLAN 2 APPROVED.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: FSI PLAN 3 APPROVED.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Full FSI Comm 1.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Full FSI Comm 2.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Full FSI Comm 3.pdf31 Jul 2017
Building Plan Approval (IOD)File: Building Plan Approval (IOD).pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC min.pdf31 Jul 2017
Declaration in FORM BFile: Form B - Rajeev (2).pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate min.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: Proforma of Sale Agr solitaire.pdf31 Jul 2017
Proforma of Allotment letterFile: Proforma of Sale Agr marvellous.pdf31 Jul 2017
OtherFile: Index II Proof.pdf31 Jul 2017
OtherFile: NOC from Civil Aviation.pdf31 Jul 2017
OtherFile: Litigation Settled Copy.pdf31 Jul 2017
OtherFile: Town Planning Approval min.pdf31 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 85 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MARVEL PRIDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri6,700+ in Mumbai Suburban

2 kmMARVEL PRIDECompleted 139Lapsed / revoked 69Other 135Dot size: filed unitsN

Filed coordinates, straight-line distance. 343 registered projects within 2 km.

Builder: Marvellous Builders Private Limited

Marvellous Builders Private Limited has 1 registration on MahaRERA, including MARVEL PRIDE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if MARVEL PRIDE is delayed beyond 31 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MARVEL PRIDE?

The registered promoter entity is Marvellous Builders Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MARVEL PRIDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MARVEL PRIDE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MARVEL PRIDE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in MARVEL PRIDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARVEL PRIDE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARVEL PRIDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.