ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Marvel Cascada E Building

Registration lapsed No litigation declared Residential / Group Housing project

Marvel Cascada E Building

By MARVEL SIGMA HOMES PRIVATE LIMITED

RG-MH-09531 · RERA P52100002242 · Last updated on MahaRERA portal: 16 Feb 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 54 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 40 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2022Possession promised54 months past this date
7 of 11Construction stages donefurthest along: Stilt Floor, 90%
3Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

Marvel Cascada E Building is a Residential / Group Housing project by MARVEL SIGMA HOMES PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100002242 on 31 Jul 2017. Possession was promised by 30 Apr 2022 and is now 54 months past that date. The completion date has moved by 40 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameMarvel Cascada E Building
  • TypeResidential / Group Housing
  • Location
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002242
  • ReraGenie IDRG-MH-09531

Builder

  • NameMARVEL SIGMA HOMES PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorVISHWAJEET SUBHASH JHAVAR
  • Other registrations11 more →
  • Completed5 of 12
  • No longer live6 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

54 months past promisethis monthRegisteredJul 2017First promiseDec 2018Revised toApr 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Jul 2017
  • Promised completion30 Apr 2022
  • Revised completionRevised to 30 Apr 2022 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ENA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 90%.

E: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 16 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes60%
Solid Waste Management And DisposalYes70%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed38

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots38
Closed/Covered38

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,509 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
RUNAL DEVELOPERSPune (M Corp.)Pune

Approvals and building plan

Permissible FSI3484.81
Proposed, not sanctioned3,035 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKOREGAON PARK

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAHUL MALWADKAR
EngineerRAJESH VASUDEV MANKANI
PartnerRole in project
MARVEL SIGMA HOMES PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100001113Dec 2018 → Apr 2020

Reason as filed by the promoterBuilding is almost complete, we are waiting for fire NOC for which we have already applied. As soon as we get the required NOC we will apply for completion.

EXT52100008636Dec 2018 → Oct 2021

Reason as filed by the promoterAs per enclosed Application.

Litigation declared2

CaseCourtStatus
1103/2004CIVIL JUDGE SENIOR DIVISION PUNEEVIDENCE
362/2012CIVIL JUDGE SENIOR DIVISION PUNEEXHIBIT FIVE HERING

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000000271Mona PandeMarvel Sigma Homes Pvt Ltd29/09/2017
CC005000000000316MOHAN DINKAR SATHEMARVEL SIGMA HOMES PVT. LTD.25/09/2017
CC005000000000364Vinod Tukaram AdaskarMarvel Sigma Homers Pvt Ltd10/10/2017

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Feb 2024

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate - Marvel Cascada D and E Bld.pdf16 Feb 2024
OtherFile: Completion E.pdf13 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CASCADA E BUILDING.pdf1 Dec 2018
Copy of the legal title reportFile: Cascada Add Title Report.pdf26 Apr 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate.pdf13 Apr 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Bank Stetment.pdf13 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CASCADA E.pdf31 Mar 2018
Layout approvalFile: CASCADA BUILDING E.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: CASCADA BUILDING E.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate E Building 280717.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate E Building.pdf28 Jul 2017
Certificates of CA (Form 3)File: C A Certificate E Building.pdf28 Jul 2017
Proforma of Allotment letterFile: Allotment Letter and Unit Agreement E Building.pdf24 Jul 2017
Declaration in FORM BFile: Affidevit E Building.pdf20 Jul 2017
Building plan approvalFile: E Building.pdf14 Jul 2017
Building plan approvalFile: E Building 1.pdf14 Jul 2017
Building plan approvalFile: E Building 2.pdf14 Jul 2017
Layout approvalFile: Layout.pdf14 Jul 2017
Layout approvalFile: Layout 1.pdf14 Jul 2017
PAN CardFile: pan Card.PDF14 Jul 2017
Copy of the legal title reportFile: Title Report.pdf14 Jul 2017
Details of encumbrancesFile: Mortgage Deed Index II.pdf14 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf14 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout 1.pdf14 Jul 2017
Building Plan Approval (IOD)File: E Building.pdf14 Jul 2017
Building Plan Approval (IOD)File: E Building 1.pdf14 Jul 2017
Building Plan Approval (IOD)File: E Building 2.pdf14 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf14 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
MARVEL SUFLAMFINAL PLOT NO 322 GHORPADE PETH PUNE4CompletedSep 2015Aug 2015
MARVEL CRESTFINAL PLOT NO 362 -2 GHORPADI PUNE12CompletedMar 2015Late, Apr 2015

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 40 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Marvel Cascada E Building on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pune (M Corp.)13,700+ in Pune

2 kmMarvel Cascada E BuildinCompleted 115Lapsed / revoked 39Other 95Dot size: filed unitsN

Filed coordinates, straight-line distance. 249 registered projects within 2 km.

Builder: MARVEL SIGMA HOMES PRIVATE LIMITED

MARVEL SIGMA HOMES PRIVATE LIMITED has 12 registrations on MahaRERA, including MARVEL SERA A,B,C BUILDING and Marvel Kyra A AND B Building. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Marvel Cascada E Building shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Marvel Cascada E Building is delayed beyond 30 Apr 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Marvel Cascada E Building?

The registered promoter entity is MARVEL SIGMA HOMES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Marvel Cascada E Building?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Marvel Cascada E Building?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Marvel Cascada E Building?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Marvel Cascada E Building?

The professionals named in the filing: Architect: RAHUL MALWADKAR; Engineer: RAJESH VASUDEV MANKANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Marvel Cascada E Building?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Marvel Cascada E Building. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Marvel Cascada E Building to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.