ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / MARIGOLD

Registered No litigation declared Others project

MARIGOLD

By KRUSHNA SAI BUILDCON LLP

RG-MH-20557 · RERA P52100005283 · Last updated on MahaRERA portal: 22 Jun 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 93 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2027Possession promisedmoved 93 months from the original
14 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 90%
34 of 217Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 283 documents Report an error

MARIGOLD is a Others project by KRUSHNA SAI BUILDCON LLP in Pune, Maharashtra, registered with MahaRERA as P52100005283 on 11 Aug 2017. Possession is promised by 30 Nov 2027. The completion date has moved by 93 months from the original filing. 183 of the 217 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameMARIGOLD
  • TypeOthers
  • Location
    • NEAR HANDEWADI ROAD
    • SASANENAGAR
    • Hadapsar
    • Haveli
    • Pune
    • 411028
  • Pincode411028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100005283
  • ReraGenie IDRG-MH-20557

Builder

  • NameKRUSHNA SAI BUILDCON LLP
  • Entity typeLimited Liability Partnership
  • LLPINAAX-2150
  • GSTIN27AAXFK4121D1ZB
  • PartnersAMIT NAGPAL, RAMESH B NAGPAL

Key dates

this monthRegisteredAug 2017First promiseFeb 2020Revised toNov 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Aug 2017
  • Promised completion30 Nov 2027
  • Revised completionRevised to 30 Nov 2027 (originally 29 Feb 2020)
  • Buildings2 building records
  • Documents filed283 files

Current status

84%183 of 217 units booked

Figures as on 22 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BuildingNA131115621177
B BuildingNA8540040

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

A Building100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B Building54%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed156

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots156
Closed/Covered100
Open Space56

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,036 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Jun 2026

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI14999.7
Proposed, not sanctioned12,695 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSalil Riswadkar
EngineerG A BHILARE CONSULTANTS
Chartered AccountantSNEHA AMARCHAND INDRA SARASWAT
Chartered AccountantPatel & Sharma
Chartered AccountantDipesh Patel
PartnerRole in project
KRUSHNA SAI BUILDCON LLP-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005808Feb 2020 → Feb 2021

Reason as filed by the promoterDue to extreme slow market conditions the sales of the project was affected and also the said project ran into delays due to slow work by Government Authorities in improving the approach roads to the project site. Therefore we were not able to complete the said Project within the said specified time under the Real Estate (Regulation and Development) Act, 2016.

EXT52100011482Feb 2020 → Feb 2024

Reason as filed by the promoterCovid-19 Pandemic Declared by World Health Organization and consequent lockdown by the government further reverse migration of the labours to there native places and break in the supply chain of construction material. Construction of the project is under project we still require twenty four months to complete the project and get the occupancy certificate.

EXT52100019000Feb 2020 → Nov 2024

Reason as filed by the promoterThe project is facing delays due to a severe labour shortage, resulting in the unavailability of skilled workers. Additionally, the contractor’s performance has been adversely affected, leading in inefficiencies and compromised work quality. Given these challenges, requesting an extension becomes imperative to ensure the project’s successful completion while maintaining the desired standards and mitigating the impact of unforeseen workforce constraints.

EXT52100022971Feb 2020 → Nov 2027

Reason as filed by the promoterThe project is facing delay due to severe labour shortage, resulting in unavailiblity of skilled worker. Additionally, the contractor performance has been adverserly affected , leading in inefficiencies and compromised work quality. Given these challenges, requesting an extention become imperative to insure the project successful completion while maintaining the desired standard and mitigating the impact of unforeseen workforce constraints. It is important to note that the promoter has transparently communicated this matter to all allottees, majority of the allottees have agreed to provide the

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12504087mausam preetam batraNirman Bharati Paradise Developers19/11/2025
CC12604291Bhau Jayram PawarKRUSHNA SAI BUILDCON LLP08/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Nov 2027

Documents filed283

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 283 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Architect certificate 30-9-25.pdf22 Jun 2026
Form 2File: FORM 2 - 30-09-25.pdf22 Jun 2026
Form 3File: KSB FORM 3 30-09-2025.pdf22 Jun 2026
Disclosure of Sold and Booked InventoryFile: KSB SOLD BOOKED INVENTORY 30-09-2025_.pdf22 Jun 2026
Form 1File: Architect certificate 30-12-25.pdf22 Jun 2026
Form 2File: FORM 2 - 31-12-25.pdf22 Jun 2026
Form 3File: KSB FORM 3 31-12-2025.pdf22 Jun 2026
Disclosure of Sold and Booked InventoryFile: KSB SOLD BOOKED INVENTORY 31-12-2025.pdf22 Jun 2026
Form 1File: Architect certificate 31-3-26.pdf22 Jun 2026
Form 2File: FORM 2 - 31-03-26.pdf22 Jun 2026
Form 3File: KSB FORM 3 31-03-2026.pdf22 Jun 2026
Disclosure of Sold and Booked InventoryFile: KSB SOLD BOOKED INVENTORY 31-03-2026.pdf22 Jun 2026
Form 5 (FY 2021-2022)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf29 May 2026
Form 1File: 2 Architects Certificate 30 sep 22.pdf28 May 2026
Form 2File: Form 2-Sept 2022.pdf28 May 2026
Form 3File: Form 03.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: 1 Sold Unsold 30092022- Uploaded.pdf28 May 2026
Form 1File: 3 Architects Certificate 31 dec 22.pdf28 May 2026
Form 2File: 2 Form 2 dec22.pdf28 May 2026
Form 3File: Form 03.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: 2 Sold Unsold 31122022.pdf28 May 2026
Form 1File: 4 Architects Certificate 31 mar 23.pdf28 May 2026
Form 2File: 3 Form 2 mar23.pdf28 May 2026
Form 3File: Form 03.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: 3 Sold Unsold 31032023- Uploaded.pdf28 May 2026
Form 1File: 5 Architects Certificate 30 june 23.pdf28 May 2026
Form 2File: 4 Form 2 june23.pdf28 May 2026
Form 3File: Form 03.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: 4 Sold Unsold 30062023 - Uploaded.pdf28 May 2026
Form 1File: 6 Architects Certificate 30 sep 23.pdf28 May 2026
Form 2File: 5 Form 2 sept23.pdf28 May 2026
Form 3File: Form 03.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: 5 Sold Unsold 30092023 - Uploaded.pdf28 May 2026
Form 1File: 7 Architects Certificate 31dec 23.pdf28 May 2026
Form 2File: 6 Form 2 dec23.pdf28 May 2026
Form 3File: final form 3.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: 6 Sold Unsold 31122023 - Uploaded.pdf28 May 2026
Form 1File: Form 01.pdf28 May 2026
Form 2File: 10 Mar 24.pdf28 May 2026
Form 3File: fORM 3 fOR MAR 24_0001.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: DECLARATION SOLD UNSOLD MAR 2024.pdf28 May 2026
Form 1File: FORM 1 30june2024.pdf28 May 2026
Form 2File: FORM 2 Jun 24.pdf28 May 2026
Form 3File: Form 3 Signed_.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: DECLARATION SOLD UNSOLD.pdf28 May 2026
Form 1File: FORM 1 30Sept2024.pdf28 May 2026
Form 2File: FORM 2 Sept 24.pdf28 May 2026
Form 3File: From-3 Date-30-09-2024.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: SoldUnsold 30 092024.pdf28 May 2026
Form 1File: Form 01 Dec 24.pdf28 May 2026
Form 2File: FORM 2 Dec 24.pdf28 May 2026
Form 3File: Form 03 Dec 24.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 14 Dec 24.pdf28 May 2026
Form 1File: Form 01 Mar 25.pdf28 May 2026
Form 2File: Form 02 Mar 25.pdf28 May 2026
Form 3File: form 03 March 2025_.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Mar 25.pdf28 May 2026
Form 1File: Form 01.pdf28 May 2026
Form 2File: Form 2.pdf28 May 2026
Form 3File: Form 03 Signed_.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: NBPD SOLD UNSOLD March 2025.pdf28 May 2026
Form 1File: 1 Architects Certificate 30 june 22.pdf28 May 2026
Form 2File: Form 2_.pdf28 May 2026
Form 3File: Form 03.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: 1 Sold Unsold 30092022- Uploaded.pdf28 May 2026
Form 1File: 0 Form 01 31mar 22.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold March 2022.pdf28 May 2026
Form 2File: Form 2_.pdf28 May 2026
Form 3File: Form 03.pdf28 May 2026
Form 2File: FORM 2 30 09 2021.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 2021.pdf28 May 2026
Form 1File: Form 01.pdf28 May 2026
Form 3File: Form 03.pdf28 May 2026
Form 1File: Form 01.pdf28 May 2026
Form 2File: FORM 2 30 09 2021.pdf28 May 2026
Form 3File: Form 03.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Sept 2021.pdf28 May 2026
Form 1File: Architect Certificate 30 june 21.pdf28 May 2026
Form 2File: FORM 2 30 06 2021.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold June 2021.pdf28 May 2026

How this compares with Pune

84%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 93 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MARIGOLD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SASANENAGAR13,700+ in Pune

2 kmMARIGOLDCompleted 46Lapsed / revoked 21Other 73Dot size: filed unitsN

Filed coordinates, straight-line distance. 140 registered projects within 2 km.

Builder: KRUSHNA SAI BUILDCON LLP

KRUSHNA SAI BUILDCON LLP has 1 registration on MahaRERA, including MARIGOLD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if MARIGOLD is delayed beyond 30 Nov 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MARIGOLD?

The registered promoter entity is KRUSHNA SAI BUILDCON LLP, a limited liability partnership as per the filing. Its LLPIN AAX-2150 and GSTIN 27AAXFK4121D1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MARIGOLD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MARIGOLD?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MARIGOLD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MARIGOLD?

The professionals named in the filing: Architect: Salil Riswadkar; Engineer: G A BHILARE CONSULTANTS; Chartered Accountant: SNEHA AMARCHAND INDRA SARASWAT; Chartered Accountant: Patel & Sharma; Chartered Accountant: Dipesh Patel. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MARIGOLD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARIGOLD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARIGOLD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.