Home / Browse projects / Ratnagiri, Maharashtra / MARIGOLD

Completed No litigation declared Others project

MARIGOLD

By Samir Mahamad Ghare

RG-MH-03029 · RERA P52800022149 · Last updated on MahaRERA portal: 5 Jan 2024

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 60 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
1Complaints at MahaRERAon this registration
Jump to the 35 documents Report an error

MARIGOLD is a Others project by Samir Mahamad Ghare in Ratnagiri, Maharashtra, registered with MahaRERA as P52800022149 on 4 Sep 2019. The registration is recorded completed; possession was promised by 31 Dec 2026. The completion date has moved by 60 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMARIGOLD
  • TypeOthers
  • Location
    • Mumbai Goa Highway
    • Lanja
    • Lanja (CT)
    • Ratnagiri
    • 416701
  • Pincode416701
  • RERA no.P52800022149
  • ReraGenie IDRG-MH-03029

Builder

  • NameSamir Mahamad Ghare
  • Entity typeIndividual
  • GSTIN27ABDPG6455H1ZN
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations3 more →
  • Completed2 of 4

Key dates

this monthRegisteredSep 2019First promiseDec 2021Revised toDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Sep 2019
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2021)
  • Buildings1 building record
  • Documents filed35 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DIPASHRI MARIGOLDNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

DIPASHRI MARIGOLD: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 5 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership20

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,290 sq m
Land owned byThe promoter, with other names on the file
Named landowners20
LandownerVillageDistrict
Shashikant Mahadeo JadhavMumbai CityMumbai City
Sudarshan Shashikant JadhavMumbai CityMumbai City
Suraiyya Hanif NaikLanja (CT)Ratnagiri
Mahamood Mohamad FodkarThane (M Corp.)Thane
Santosh Harishchandra KavacheArgaonRatnagiri
Digvijay Shankar DereLanja (CT)Ratnagiri
Ashok Shankar SurveKheravaseRatnagiri
Ibrahim Abdurlrehaman LanjekarOniRatnagiri
Ramchandra Sitaram TulsankarLanja (CT)Ratnagiri
Darshan Ramchandra KharatDhundareRatnagiri
Swetambhari Tukaram ShindeDhundareRatnagiri
Mahamud Abdulla NaikKurlaMumbai Suburban
Khetaramji Ambaramji DevasiLanja (CT)Ratnagiri
Bhavarlal Bharaji ChaudhariLanja (CT)Ratnagiri
Hajimiya Abbas NeverekarLanja (CT)Ratnagiri
Satish jayaram ChanodarkarLanja (CT)Ratnagiri
Hasan Hajimajid MemonLanja (CT)Ratnagiri
Dawood Akbar NevrekarLanja (CT)Ratnagiri
Usman Mahammad MukariPunasRatnagiri
Saurabh Sadashiv padhyeLanja (CT)Ratnagiri

Approvals and building plan

Permissible FSI1271.55
Proposed, not sanctioned1,272 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPandurang Plaza Keshav Wing Opp Sanskritik Bhavan Lanja Ratnagiri

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMILIND SURVE
EngineerManoj S Joshi
Chartered AccountantShailesh Kale & Company
PartnerRole in project
Samir Mahamad Ghare-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52800017049Dec 2021 → Dec 2026

Reason as filed by the promoterProject is completed but due to our two customers Full Occupancy Certificate is not yet received. Also Part Occupacny dated 10-6-2022 and 12-8-2022 is uploaded .Society also made on 19-5-2023 which is uploaded.. Form 4 is also uploaded . Even though the email came from your side to get Extention and hence we are applying for the same .. For That we have taken SRO member ship from NAREDCO the number is RPM/MAH/NR528000170

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000193366Prabhakar Mahadev Dorle and Prasad Prabhakar DorleSameer Mahamad Ghare01/07/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Mar 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Dec 2022

Documents filed35

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B.pdf5 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023.pdf5 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf5 Jan 2024
Certificates of CA (Form 3)File: Form 3.pdf5 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf5 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf5 Jan 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Mari gold society.pdf31 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Mari gold.pdf6 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Mari gold oc.pdf23 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC Mari gold.pdf2 Jul 2022
Declaration about Commencement CertificateFile: Format D Mari gold.pdf22 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A 31032020.pdf22 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 31032021.pdf22 Nov 2021
Disclosure of sold/ booked inventoryFile: sold unsold inventory Mari gold.pdf22 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 mari gold.pdf16 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Elite Developers-Marie Gold-RERA Form 5.pdf10 Jun 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf23 Oct 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Marie Gold- form 2 for RERA.pdf23 Oct 2020
Certificates of CA (Form 3)File: From 3 Mari Gold.pdf23 Oct 2020
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf23 Oct 2020
Declaration in FORM BFile: new Form b.pdf19 Aug 2019
Layout approvalFile: layout 1.pdf29 Mar 2019
Layout approvalFile: layout 2.pdf29 Mar 2019
Layout approvalFile: layout 3.pdf29 Mar 2019
Building plan approvalFile: Permission.pdf29 Mar 2019
PAN CardFile: pan card.pdf29 Mar 2019
Copy of the legal title reportFile: Search Report.pdf29 Mar 2019
Details of encumbrancesFile: encumbrance.pdf29 Mar 2019
Copy of Layout Approval (in case of layout)File: layout 1.pdf29 Mar 2019
Copy of Layout Approval (in case of layout)File: layout 2.pdf29 Mar 2019
Copy of Layout Approval (in case of layout)File: layout 3.pdf29 Mar 2019
Building Plan Approval (IOD)File: Permission.pdf29 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: Permission.pdf29 Mar 2019
Certificates of CA (Form 3)File: Form 3.pdf29 Mar 2019
Proforma of Allotment letterFile: Agreement to sale.pdf29 Mar 2019

How this compares with Ratnagiri

15%of Ratnagiri projects moved their completion datethis one moved by 60 months
30%of Ratnagiri registrations have lapsed or been cancelledthis one is completed

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep MARIGOLD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Lanja1,100+ in Ratnagiri

Builder: Samir Mahamad Ghare

Samir Mahamad Ghare has 4 registrations on MahaRERA, including Royal Park and MARIGOLD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if MARIGOLD is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MARIGOLD?

The registered promoter entity is Samir Mahamad Ghare, an individual as per the filing. Its GSTIN 27ABDPG6455H1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MARIGOLD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MARIGOLD?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MARIGOLD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MARIGOLD?

The professionals named in the filing: Architect: MILIND SURVE; Engineer: Manoj S Joshi; Chartered Accountant: Shailesh Kale & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MARIGOLD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARIGOLD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARIGOLD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.