Home / Browse projects / Palghar, Maharashtra / MARIAM PARK COMPLEX
MARIAM PARK COMPLEX
By SHAMSHAD & SONS PROPERTY PVT LTD
RG-MH-84916 · RERA P99000014057 · Last updated on MahaRERA portal: 27 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 102 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MARIAM PARK COMPLEX is a Residential / Group Housing project by SHAMSHAD & SONS PROPERTY PVT LTD in Palghar, Maharashtra, registered with MahaRERA as P99000014057 on 7 Nov 2017. Possession is promised by 31 Dec 2029. The completion date has moved by 102 months from the original filing. 56 of the 126 units on this registration are recorded sold or booked, and 13 of 38 construction stages are filed complete.
At a glance
Project
- NameMARIAM PARK COMPLEX
- TypeResidential / Group Housing
- Location
- station road
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401207
- Pincode401207
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000014057
- ReraGenie IDRG-MH-84916
Builder
- NameSHAMSHAD & SONS PROPERTY PVT LTD
- Entity typeCompany
- DirectorsNAJEEBALI LIYAKATALI KALANIA, SHAMEEK LIYAKATALI KALANIA
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on7 Nov 2017
- Promised completion31 Dec 2029
- Revised completionRevised to 31 Dec 2029 (originally 30 Jun 2021)
- Buildings4 building records
- Documents filed81 files
Current status
Figures as on 27 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 7 | NA | 7 | 5 | 60 | 0 | 60 |
| Building No 8 | NA | 8 | 7 | 49 | 0 | 49 |
| Building No 9 | NA | 8 | 7 | 7 | 0 | 7 |
| CFC Building | NA | 4 | 4 | 0 | 10 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 27 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
13 of 38 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 45%.
BUILDING NO 782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 857%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 45% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 90%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CFC Building0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed169
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| BUILDING NO 7 | 2 | 46 | 48 |
| Building No 8 | 0 | 36 | 36 |
| Building No 9 | 0 | 36 | 36 |
| CFC Building | 0 | 49 | 49 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING NO 7 | NA | Rs 5.05 cr | Rs 3.54 cr |
| Building No 9 | NA | Rs 1.50 cr | - |
| - | NA | Rs 37.41 lakh | - |
| Building No 8 | NA | Rs 12.63 lakh | - |
| CFC Building | NA | Rs 1.71 lakh | - |
Certifying professionals and partners11
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AJAY WADE AND ASSOCIATES |
| Architect | MEGHA URBANSCAPES |
| Architect | ABHAY D RAUT |
| Engineer | Sameer Mohile & Associates |
| Engineer | S S & ASSOCIATES |
| Engineer | Structbond Engineering Consultants |
| Engineer | ZIAUR REHMAN KHAN |
| Engineer | PRO TECT CONSULTANTS |
| Engineer | ZZ CONSULTANTS |
| Chartered Accountant | SPP Associates |
| Chartered Accountant | RAMESH DHONDIRAM LUKAD |
| Partner | Role in project |
|---|---|
| SHAMSHAD & SONS PROPERTY PVT LTD | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterit is respectfully submitted that the suo motu extension of the validity granted by Maharera is coming to an end. it is further submitted that the extension has served the limited purpose only as owing to continuation of COVID-19 pandemic we are suffering acute shortage of labor supply Occasionally we get the labor supply, but that is up to the extent of 50% than what is required. In circumstances like this we are not able to complete the construction on the extended date 30-06-2021. Therefore, we hereby request you to grant us extension as per online application field. Obiged
Reason as filed by the promoterCC Revised to 5th floor and for this reason there is delay in completion of project which we mutually taken consent from all our allottees for extension and same declaration is attach for extension.
Reason as filed by the promoterWe respectfully submit that the construction of the project is being carried out strictly in accordance with the sanctioned plans and approved construction schedule. The execution of the project involves multiple sequential and inter-dependent activities including structural works, internal finishing, services installations, and external site development, all of which are required to be completed in a phased and regulated manner. While major structural and finishing works have been completed / are nearing completion, certain essential services and external development works such as lifts, fire
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Oct 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Sep 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Aug 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2029
Documents filed81
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 APRIL TO JUNE.pdf | 27 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 APRIL TO JUNE.pdf | 27 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 APRIL TO JUNE.pdf | 27 Jul 2026 |
| Withdrawal Update Form 1File: form 1 mariam park.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Mariam Park engg.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: form 3 C A.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 10 Feb 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 10 Feb 2026 |
| Withdrawal Update Form 3File: Form_3.pdf | 10 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 - 2 Quarter (1).pdf | 22 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate - 2 Quarter (1) (1).pdf | 22 Dec 2025 |
| Withdrawal Update Form 3File: Form_3.pdf | 22 Dec 2025 |
| Form 5 (FY 2022-2023)File: Form5 -22-23.pdf | 18 Dec 2025 |
| Form 5 (FY 2023-2024)File: fORM 5 -23-24.pdf | 18 Dec 2025 |
| Form 5 (FY 2024-2025)File: FORM5 -24-25.pdf | 18 Dec 2025 |
| Form 2A (FY 2019-2020)File: 490c2083-bee8-4a34-8b0d-6a5acd37549e.pdf | 3 Dec 2025 |
| Form 2A (FY 2020-2021)File: 6bab7f9d-a44c-41e2-b191-44d4d2b90976.pdf | 3 Dec 2025 |
| Form 2A (FY 2021-2022)File: 8f1d0440-31f4-4d5e-a9c5-6bc3ff05d272.pdf | 3 Dec 2025 |
| Form 2A (FY 2022-2023)File: 8f1d0440-31f4-4d5e-a9c5-6bc3ff05d272 (1).pdf | 3 Dec 2025 |
| Form 2A (FY 2023-2024)File: 8f1d0440-31f4-4d5e-a9c5-6bc3ff05d272 (2).pdf | 3 Dec 2025 |
| Form 2A (FY 2024-2025)File: 8f1d0440-31f4-4d5e-a9c5-6bc3ff05d272 (3).pdf | 3 Dec 2025 |
| Form 5 (FY 2017-2018)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18).pdf | 3 Dec 2025 |
| Form 5 (FY 2018-2019)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19).pdf | 3 Dec 2025 |
| Form 5 (FY 2019-2020)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20).pdf | 3 Dec 2025 |
| Form 5 (FY 2020-2021)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf | 3 Dec 2025 |
| Form 5 (FY 2021-2022)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf | 3 Dec 2025 |
| Layout approvalFile: layout.pdf | 10 Sep 2025 |
| Building plan approvalFile: Building7.pdf | 14 Aug 2025 |
| Building plan approvalFile: Bldg 8.pdf | 4 Aug 2025 |
| Building plan approvalFile: Bldg 9.pdf | 4 Aug 2025 |
| Building plan approvalFile: CFC_compressed.pdf | 4 Aug 2025 |
| Withdrawal Update Form 1File: Form 1 - 2 Quarter.pdf | 4 Aug 2025 |
| Withdrawal Update Form 2File: Engineer Certificate.pdf | 4 Aug 2025 |
| Withdrawal Update Form 3File: Form_3.pdf | 4 Aug 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 Architect Certificate_compressed (1).pdf | 21 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 (2022-23) (1)_compressed.pdf | 21 Feb 2025 |
| Certificates of CA (Form 3)File: Form - 3 (2023-24) (1)_compressed.pdf | 21 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 Engineer Certificate_compressed.pdf | 21 Feb 2025 |
| Details of encumbrancesFile: Letter Of Encumbrances-Finance.pdf | 9 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: Letter Of Encumbrances-Legal.pdf | 9 Mar 2023 |
| Details of encumbrances concerned to LegalFile: Letter Of Encumbrances-Legal.pdf | 9 Mar 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Of Interest.pdf | 9 Mar 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Of Seperate Bank Ac.pdf | 9 Mar 2023 |
| Deviation Report with respect to Allotment letterFile: Letter Of Encumbrances-Allotment.pdf | 9 Mar 2023 |
| Deviation Report with respect to model copy of AgreementFile: Letter Of Encumbrances-Agreement.pdf | 9 Mar 2023 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 8 Mar 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200262405230_For_Asset_Based_Search_08_03_2023_18_54_23_505.pdf | 8 Mar 2023 |
| Proforma of Agreement for saleFile: Draft Agreement.pdf | 1 Mar 2023 |
| Proforma of Allotment letterFile: Allotment Letter Format.pdf | 1 Mar 2023 |
| Building plan approvalFile: F WING PLAN 2022_.pdf | 22 Jan 2023 |
| Building Plan Approval (IOD)File: F WING PLAN 2022_.pdf | 22 Jan 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC - 2022_.pdf | 22 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 Architect Certificate.pdf | 22 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 22 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 03-07-2020.pdf | 22 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 22 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A - 21-22.pdf | 12 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2021-22.pdf | 31 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2021-22.pdf | 31 Dec 2022 |
| Declaration about Commencement CertificateFile: DECLARATION OF CC.pdf | 6 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2020-2021.pdf | 6 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: SoldBooked Inventory.pdf | 6 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 2017-18.pdf | 6 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19.pdf | 6 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20.pdf | 6 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020-21.pdf | 6 Jul 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: C Certificate.pdf | 28 Jun 2018 |
| Layout approvalFile: lay out-ilovepdf-compressed.pdf | 9 Oct 2017 |
| Building plan approvalFile: building plan F-ilovepdf-compressed.pdf | 9 Oct 2017 |
| Building plan approvalFile: building plan G-ilovepdf-compressed.pdf | 9 Oct 2017 |
| PAN CardFile: COMPANY PAN CARD.pdf | 9 Oct 2017 |
| Copy of the legal title reportFile: TITLE CLEARENCE CERTIFICATE.pdf | 9 Oct 2017 |
| Details of encumbrancesFile: NO ENCUMBERENCE CERTIFICATE.pdf | 9 Oct 2017 |
| Copy of Layout Approval (in case of layout)File: lay out-ilovepdf-compressed.pdf | 9 Oct 2017 |
| Building Plan Approval (IOD)File: building plan F-ilovepdf-compressed.pdf | 9 Oct 2017 |
| Building Plan Approval (IOD)File: building plan G-ilovepdf-compressed.pdf | 9 Oct 2017 |
| Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION FINAL FORM B.pdf | 9 Oct 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERT.pdf | 9 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER REPORT FINAL RESIZE.pdf | 9 Oct 2017 |
| Certificates of CA (Form 3)File: CA CERT RERA 11.pdf | 9 Oct 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 81 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MARIAM PARK COMPLEX on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar
Filed coordinates, straight-line distance. 161 registered projects within 2 km.
SHRIPAL SATTVA - BLDG. 1
SHRIPAL SATTVA LLP
SUNSHINE MEADOWS
SHANTEE GLOBAL REALTY LLP
Mangeshi Gemini
Mangesh Dashrath Gaikar
SKY VISTA
M/s. Divine Construction
Miracle Tower
Modernscape Infra LLP
PREMIER ELEGANCE
PREMEAR LANDMARK DEVELOPERS LLP
See every Palghar project, with the district possession charts
Builder: SHAMSHAD & SONS PROPERTY PVT LTD
SHAMSHAD & SONS PROPERTY PVT LTD has 1 registration on MahaRERA, including MARIAM PARK COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if MARIAM PARK COMPLEX is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MARIAM PARK COMPLEX?
The registered promoter entity is SHAMSHAD & SONS PROPERTY PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MARIAM PARK COMPLEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MARIAM PARK COMPLEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MARIAM PARK COMPLEX?
The professionals named in the filing: Architect: AJAY WADE AND ASSOCIATES; Architect: MEGHA URBANSCAPES; Architect: ABHAY D RAUT; Engineer: Sameer Mohile & Associates; Engineer: S S & ASSOCIATES; Engineer: Structbond Engineering Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MARIAM PARK COMPLEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback