ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Maplle Plazza

Registration lapsed No litigation declared Others project

Maplle Plazza

By Maplle Infraprojects Limited

RG-MH-27145 · RERA P51800002879 · Last updated on MahaRERA portal: 5 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 45 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
10 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 65%
2Complaints at MahaRERAon this registration
Jump to the 151 documents Report an error

Maplle Plazza is a Others project by Maplle Infraprojects Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002879 on 4 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 45 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameMaplle Plazza
  • TypeOthers
  • Location
    • SUBHASH NAGAR
    • JOGESHWARI EAST
    • Andheri
    • Mumbai Suburban
    • 400060
  • Pincode400060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800002879
  • ReraGenie IDRG-MH-27145

Builder

  • NameMaplle Infraprojects Limited
  • Entity typeCompany
  • Managing DirectorAtul Parekh

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseMar 2022Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Mar 2022)
  • Buildings2 building records
  • Documents filed151 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Maplle PlazzaNA130000
NANA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 5 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 65%.

Maplle Plazza97%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
NA0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 5 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes95%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes35%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Fitness center and society officeYes75%

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Closed/Covered26

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,769 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5586.39
Proposed, not sanctioned2,784 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAHEK PLAZA OFF CHANDRAWARKAR ROAD BORIVALI WEST MUMBAI 400092

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVerticohorizon
EngineerMr Dwijen Bhatt
EngineerSK Consultants & Engineers
Chartered AccountantRutuja Narsingh & Associates
Chartered AccountantGaurav S Rajpal & Co
PartnerRole in project
Maplle Infraprojects Limited-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012559Mar 2022 → Mar 2023

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

EXT51800011440Mar 2022 → Sep 2022

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of the project u/s 6 in Format B.

EXT51800015167Mar 2022 → Dec 2023

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 63.27% allottees for purpose of extension of RERA registration period of the said project.

EXT51800024486Mar 2022 → Dec 2025

Reason as filed by the promoterI, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P52100025883. As per HEARING DATED 10th December 2024, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31/12/2025. The order is Other Tab for your reference

Litigation declared2

CaseCourtStatus
1462/2016Bombay City Civil Court at DindoshiService of Notice of Motion and Suit to defendant pending
1872/2018Bombay City Civil Court at DindoshiReply on chamber summons

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000198407Jitendra ShahM/s. Maplle Infraprojects Limited (Formerly known as Maple Industries (Laminates)limited.21/09/2021
CC006000000198409Chandravali Jitendra ShahM/s. Maplle Infraprojects Limited (Formerly known as Maple Industries (Laminates) Limited.21/09/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed151

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 151 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 - Maplle Plazza as on Sep 2025.pdf5 Jan 2026
Form 2File: Form 2 - Maplle Plazza as on Sep 2025.pdf5 Jan 2026
Form 3File: Form 3 - Maplle Plazza as on Sep 2025.pdf5 Jan 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Maplle Plazza as on Sep 2025.pdf5 Jan 2026
Form 1File: Form 1 - Maplle Plazza as on Dec 2024.pdf23 Dec 2025
Form 2File: Form 2 - Maplle Plazza as on Dec 2024.pdf23 Dec 2025
Form 3File: Form 3 - Maplle Plazza as on Dec 2024.pdf23 Dec 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Maplle Plazza as on Dec 2024.pdf23 Dec 2025
Form 1File: Form 1 - Maplle Plazza as on March 2025.pdf23 Dec 2025
Form 2File: Form 2 - Maplle Plazza as on March 2025.pdf23 Dec 2025
Form 3File: Form 3 - Maplle Plazza as on March 2025.pdf23 Dec 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Maplle Plazza as on March 2025.pdf23 Dec 2025
Form 1File: Form 1 - Maplle Plazza as on June 2025.pdf23 Dec 2025
Form 2File: Form 2 - Maplle Plazza as on June 2025.pdf23 Dec 2025
Form 3File: Form 3 - Maplle Plazza as on June 2025.pdf23 Dec 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Maplle Plazza as on June 2025.pdf23 Dec 2025
Declaration in FORM BFile: Form B.pdf19 Feb 2025
Declaration in FORM BFile: FORM - B (Promoter).pdf27 Dec 2024
Disclosure of sold/ booked inventoryFile: CIRCULAR 29 - 30 Sept 2024 Signed copy.pdf15 Nov 2024
Certificates of CA (Form 3)File: FORM 3 JUL 2024 SEP 2024_compressed.pdf11 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Sep -2024.pdf11 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: fg.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5- Annual Report- FY 2017-18 With MIL STAMP.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5- Annual Report - FY 2018 - 2019 WITH MIL STAMP.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5- Annual Report - FY 2019-20 WITH MIL STAMP.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5- Annual Report - FY 2020-21 WITH MIL STAMP.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- Maplle Plazza as on 2021-22 WITH MIL STAMP.pdf30 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Mar -2024.pdf6 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- June-2024.pdf6 Aug 2024
Disclosure of sold/ booked inventoryFile: CIRCULAR 29_Maplle Plazza (2) Signed Copy.pdf6 Aug 2024
Certificates of CA (Form 3)File: Form -3 June 2024 revised_compressed.pdf6 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 APR 22 to MAR 23.pdf6 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 APR 2023 MAR 2024.pdf6 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect Certificate-Apr 24 to Jun 24 SIGN.pdf5 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-2024 Singed copy.pdf5 Aug 2024
Declaration in FORM BFile: Form B.pdf3 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate-Jan 23 to Mar 23.pdf3 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate - Apr 23 to Jun 23.pdf3 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate-Jul 23 to Sep 23.pdf3 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate-Oct 23 to Dec 23.pdf3 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate-Jan 24 to Mar 24.pdf3 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate-Apr 24 to Jun 24.pdf3 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf3 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 23-24.pdf3 Aug 2024
CERSAI detailsFile: DECLARATION of Cersai.pdf3 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Format N.pdf3 Aug 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A - Seperate Bank Account Details.pdf3 Aug 2024
Certificates of CA (Form 3)File: 24 Certificates of CA (Form 3).pdf3 Apr 2024
Certificates of CA (Form 3)File: Form 3- Maplle Plazza as on 31-03-2023.pdf28 Aug 2023
Certificates of CA (Form 3)File: Form 3- Maplle Plazza as on 31-12-2022.pdf28 Aug 2023
Certificates of CA (Form 3)File: Form 3- Maplle Plazza as on 31-03-2023.pdf28 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-20_compressed.pdf15 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21.pdf15 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-22.pdf15 Apr 2023
Disclosure of sold/ booked inventoryFile: CIRCULER 29.pdf15 Apr 2023
Disclosure of sold/ booked inventoryFile: Circular 29 - 31-12-2022.pdf14 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on December 2017.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on March 2018.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on June 2018.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on September 2018.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on December 2018.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on March 2019.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on June 2019.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on September 2019.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on December 2019.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on September 2020.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on December 2020.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on March 2021.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on September 2021.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on December 2021.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on March 2022.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on June 2022.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Maplle Plazza as on September 2022.pdf4 Mar 2023
Certificates of CA (Form 3)File: Form 3- Maplle Plaza as on December 2017.pdf4 Mar 2023
Certificates of CA (Form 3)File: Form 3- Maplle Plaza as on March 2018.pdf4 Mar 2023
Certificates of CA (Form 3)File: Form 3- Maplle Plaza as on June 2018.pdf4 Mar 2023
Certificates of CA (Form 3)File: Form 3- Maplle Plaza as on September 2018.pdf4 Mar 2023
Certificates of CA (Form 3)File: Form 3- Maplle Plaza as on December 2018.pdf4 Mar 2023
Certificates of CA (Form 3)File: Form 3- Maplle Plaza as on March 2019.pdf4 Mar 2023
Certificates of CA (Form 3)File: Form 3- Maplle Plaza as on June 2019.pdf4 Mar 2023

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 45 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Maplle Plazza on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near JOGESHWARI EAST6,700+ in Mumbai Suburban

2 kmMaplle PlazzaCompleted 164Lapsed / revoked 69Other 148Dot size: filed unitsN

Filed coordinates, straight-line distance. 381 registered projects within 2 km.

Builder: Maplle Infraprojects Limited

Maplle Infraprojects Limited has 1 registration on MahaRERA, including Maplle Plazza. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Maplle Plazza shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Maplle Plazza is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Maplle Plazza?

The registered promoter entity is Maplle Infraprojects Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Maplle Plazza?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Maplle Plazza?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Maplle Plazza?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Maplle Plazza?

The professionals named in the filing: Architect: Verticohorizon; Engineer: Mr Dwijen Bhatt; Engineer: SK Consultants & Engineers; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: Gaurav S Rajpal & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Maplle Plazza?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Maplle Plazza. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Maplle Plazza to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.