Home / Browse projects / Pune, Maharashtra / Manor Crystal

Registered No litigation declared Residential / Group Housing project

Manor Crystal

By OXFORD INFRA GROUP

RG-MH-04628 · RERA P52100020056 · Last updated on MahaRERA portal: 4 Jun 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • 7 complaints at MahaRERA
  • Completion date moved by 45 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
8 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 75%
20 of 32Units unsoldnot recorded sold or booked
7Complaints at MahaRERAon this registration
Jump to the 272 documents Report an error

Manor Crystal is a Residential / Group Housing project by OXFORD INFRA GROUP in Pune, Maharashtra, registered with MahaRERA as P52100020056 on 25 Mar 2019. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 45 months from the original filing. 12 of the 32 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete. 7 complaints are on record with the regulator.

At a glance

Project

  • NameManor Crystal
  • TypeResidential / Group Housing
  • Location
    • Bhumkar Chowk-Karpe Nagar
    • Wakad
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100020056
  • ReraGenie IDRG-MH-04628

Builder

  • NameOXFORD INFRA GROUP
  • Entity typePartnership
  • PartnersAMAR CHANDRAKANT BHUMKAR, Chandrakant Baburao Bhumkar, Dnyaneshwar baburao Bhumkar, Arun Baburao Bhumkar
  • Other registrations1 more →
  • Completed1 of 2
  • Past their filed date1

Key dates

1 months past promisethis monthRegisteredMar 2019First promiseDec 2022Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Mar 2019
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed272 files

Current status

38%12 of 32 units booked
51.0%Work done, per cost certificate

Figures as on 4 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA6416016
BNA5416016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 75%.

A56%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B56%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,325 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Jul 2025
LandownerVillageDistrict
KASUBAI ASHOK SHINDEWakadPune
BALASAHEB JAYWANT MANEWakadPune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI1486.65
Proposed, not sanctioned1,125 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWAKAD PUNE
Estimated costRs 5.19 cr
Cost incurredRs 2.65 cr
Work done50.98%
BuildingWingEstimatedIncurred
ANARs 2.60 crRs 1.32 cr
BNARs 2.60 crRs 1.32 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectunusual spaces
EngineerNihal Abdul Shaikh
Chartered AccountantR H Pothiwal & Associates
PartnerRole in project
OXFORD INFRA GROUP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017660Dec 2022 → Dec 2024

Reason as filed by the promoter1. Changes in bye-laws and policies of the state government (UDCPR) and PCMC authority, necessitating the revision of the Sanction Plan, 2. Disputes arising from TDR procurement issues with the landowner. 3.Unavailability of Slum TDR and Regular TDR in the market resulted in a suspension of construction activities. The construction work for both wings could only resume after I personally purchased the TDR following the unfortunate death of the landowner on 07/08/2021, despite it not being initially within my scope of responsibilities as specified in the Development Agreement, significantly aff

EA31072502273Dec 2022 → Sep 2026

Reason as filed by the promoter1. Changes in bye-laws and policies of the state government (UDCPR) and PCMC authority, necessitating the revision of the Sanction Plan, 2. Disputes arising from TDR procurement issues with the landowner. 3.Unavailability of Slum TDR and Regular TDR in the market resulted in a suspension of construction activities. The construction work for both wings could only resume after I personally purchased the TDR following the unfortunate death of the landowner on 07/08/2021, despite it not being initially within my scope of responsibilities as specified in the Development Agreement, significantly aff

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC005000000127137Pravin Devidas KharatAmar Bhumkar23/05/2022
CC005000000137162Sumit Dattatraya NaikAmar Chandrakant Bhumkar31/05/2022
CC005000000147202SADHANA GAJANAN SHASTRIShri Amar Bhumkar17/06/2022
CC005000000259233Vibhor Vikas GujjewarAmar Chandrakant Bhumkar30/07/2023
CC005000000228487KETAN Avinash BHUTEAMAR CHANDRAKANT BHUMKAR11/03/2023
CC005000000238496Tanvi Balvantrao ThoratOXFORD INFRA GROUP06/04/2023
CC005000000238597Dilip Bhaskarrao KhanzodeAmar Chandrakant Bhumkar30/03/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Feb 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed272

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 272 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: F1 Sept (Manor Crystal).pdf4 Jun 2026
Withdrawal Update Form 1File: F1 Dec 25 (Manor Crystal).pdf4 Jun 2026
Withdrawal Update Form 1File: F1 Mar 26 (Manor Crystal)..pdf4 Jun 2026
Withdrawal Update Form 2File: Engineer certificate Sep 25.pdf4 Jun 2026
Withdrawal Update Form 2File: Engineer certificate dec 25.pdf4 Jun 2026
Withdrawal Update Form 2File: Engineer certificate March 26.pdf4 Jun 2026
Withdrawal Update Form 3File: F3 Sept.pdf4 Jun 2026
Withdrawal Update Form 3File: F3-Crystal Manor (Dec 25).pdf4 Jun 2026
Withdrawal Update Form 3File: F3-MARCH-26.pdf4 Jun 2026
Withdrawal Update Form 1File: F1 Sept (Manor Crystal).pdf18 May 2026
Withdrawal Update Form 2File: Engineer certificate Sep.pdf18 May 2026
Withdrawal Update Form 3File: F3 Sept.pdf18 May 2026
Form 2A (FY 2023-2024)File: Form 2A.pdf16 Sep 2025
Form 2A (FY 2023-2024)File: Form 2A.pdf16 Sep 2025
Form 2A (FY 2024-2025)File: Form 2A.pdf16 Sep 2025
Form 2A (FY 2024-2025)File: Form 2A.pdf16 Sep 2025
Form 5 (FY 2018-2019)File: 2018-19.pdf16 Sep 2025
Form 5 (FY 2019-2020)File: 2019-20.pdf16 Sep 2025
Form 5 (FY 2020-2021)File: 2020-21.pdf16 Sep 2025
Form 5 (FY 2021-2022)File: 2021-22.pdf16 Sep 2025
Form 5 (FY 2022-2023)File: 2022-23.pdf16 Sep 2025
Form 5 (FY 2023-2024)File: 2023-24.pdf16 Sep 2025
Form 1File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 20.pdf15 Sep 2025
Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf15 Sep 2025
Form 3File: 4 Certificates of CA (Form 3) Mar 19.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory March 20.pdf15 Sep 2025
Form 1File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 20.pdf15 Sep 2025
Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf15 Sep 2025
Form 3File: 5 Certificates of CA (Form 3) June 19.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory March 20.pdf15 Sep 2025
Form 1File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 20.pdf15 Sep 2025
Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf15 Sep 2025
Form 3File: 6 Certificates of CA (Form 3) Sept 19.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory March 20.pdf15 Sep 2025
Form 1File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 20.pdf15 Sep 2025
Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf15 Sep 2025
Form 3File: 7 Certificates of CA (Form 3) Dec 19.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory March 20.pdf15 Sep 2025
Form 1File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 20.pdf15 Sep 2025
Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf15 Sep 2025
Form 3File: 8 Certificates of CA (Form 3) March 20.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory March 20.pdf15 Sep 2025
Form 1File: 7 Architect’s Certificate of Percentage of Completion of Work (Form 1) June 20.pdf15 Sep 2025
Form 2File: 7 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 21.pdf15 Sep 2025
Form 3File: 8 Certificates of CA (Form 3) March 20.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory March 20.pdf15 Sep 2025
Form 1File: 8 Architect’s Certificate of Percentage of Completion of Work (Form 1) Sept 20.pdf15 Sep 2025
Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf15 Sep 2025
Form 3File: 8 Certificates of CA (Form 3) March 20.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory March 20.pdf15 Sep 2025
Form 1File: 9 Architect’s Certificate of Percentage of Completion of Work (Form 1) Dec 20.pdf15 Sep 2025
Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf15 Sep 2025
Form 3File: 8 Certificates of CA (Form 3) March 20.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory March 20.pdf15 Sep 2025
Form 1File: 10 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 21.pdf15 Sep 2025
Form 2File: 7 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 21.pdf15 Sep 2025
Form 3File: 9 Certificates of CA (Form 3) March 21.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 Disclosure of sold_ booked inventory March 21.pdf15 Sep 2025
Form 1File: 11 Architect’s Certificate of Percentage of Completion of Work (Form 1) June 21.pdf15 Sep 2025
Form 2File: 7 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 21.pdf15 Sep 2025
Form 3File: 9 Certificates of CA (Form 3) March 21.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 Disclosure of sold_ booked inventory March 21.pdf15 Sep 2025
Form 1File: 12 Architect’s Certificate of Percentage of Completion of Work (Form 1) Sept 21.pdf15 Sep 2025
Form 2File: 7 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 21.pdf15 Sep 2025
Form 3File: 9 Certificates of CA (Form 3) March 21.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 Disclosure of sold_ booked inventory March 21.pdf15 Sep 2025
Form 1File: 13 Architect’s Certificate of Percentage of Completion of Work (Form 1) Dec 21.pdf15 Sep 2025
Form 2File: 7 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 21.pdf15 Sep 2025
Form 3File: 9 Certificates of CA (Form 3) March 21.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 4 Disclosure of sold_ booked inventory March 21.pdf15 Sep 2025
Form 1File: 14 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 22.pdf15 Sep 2025
Form 2File: 8 Engineer’s Certificate on Cost Incurred on Project (Form 2) march 22.pdf15 Sep 2025
Form 3File: 10 Certificates of CA (Form 3) March 22.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 5 Disclosure of sold_ booked inventory March 22.pdf15 Sep 2025
Form 1File: 15 Architect’s Certificate of Percentage of Completion of Work (Form 1) june 22.pdf15 Sep 2025
Form 2File: 8 Engineer’s Certificate on Cost Incurred on Project (Form 2) march 22.pdf15 Sep 2025
Form 3File: 10 Certificates of CA (Form 3) March 22.pdf15 Sep 2025
Disclosure of Sold and Booked InventoryFile: 5 Disclosure of sold_ booked inventory March 22.pdf15 Sep 2025
Form 1File: 16 Architect’s Certificate of Percentage of Completion of Work (Form 1) Sept 22.pdf15 Sep 2025
Form 2File: 8 Engineer’s Certificate on Cost Incurred on Project (Form 2) march 22.pdf15 Sep 2025

How this compares with Pune

38%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 45 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Manor Crystal on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wakad13,700+ in Pune

2 kmManor CrystalCompleted 72Lapsed / revoked 32Other 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 149 registered projects within 2 km.

Builder: OXFORD INFRA GROUP

OXFORD INFRA GROUP has 2 registrations on MahaRERA, including OLYMPIA PHASE 1 and Manor Crystal. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Manor Crystal is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Manor Crystal?

The registered promoter entity is OXFORD INFRA GROUP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Manor Crystal?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Manor Crystal?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Manor Crystal?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Manor Crystal?

The professionals named in the filing: Architect: unusual spaces; Engineer: Nihal Abdul Shaikh; Chartered Accountant: R H Pothiwal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Manor Crystal?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Manor Crystal. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Manor Crystal to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.