MANGESHI SANSKAR
RG-MH-58698 · RERA P51700008382 · Last updated on MahaRERA portal: 11 Apr 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 13 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 18 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MANGESHI SANSKAR is a Residential / Group Housing project by Mangesh Dashrath Gaikar in Thane, Maharashtra, registered with MahaRERA as P51700008382 on 18 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2018.
At a glance
Project
- NameMANGESHI SANSKAR
- TypeResidential / Group Housing
- Location
- KHADEGOLAVALI
- Kalyan
- Thane
- 421306
- Pincode421306
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700008382
- ReraGenie IDRG-MH-58698
Builder
- NameMangesh Dashrath Gaikar
- Entity typeIndividual
- GSTIN27AFAPG5995H1Z7
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Other registrations18 more →
- Completed8 of 19
- No longer live2 lapsed, de-registered or revoked
- Past their filed date1
- Declared earlier projects13 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on18 Aug 2017
- Promised completion30 Jun 2018
- Revised completionNone
- Buildings2 building records
- Documents filed23 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Sanskar I - Building D | NA | 9 | 0 | 0 | 0 | 0 |
| Plot 2 Building 1 | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 11 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
Sanskar I - Building D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Plot 2 Building 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 11 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed11
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DECON CONSULTANT |
| Engineer | KHASNIS AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| Mangesh Dashrath Gaikar | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 29 Jan 2020
Documents filed23
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of Formation of Legal Entity (Society/Co Op etc.)File: D wing cert.pdf | 11 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Sanction Letter.pdf | 21 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: ushh kiran 20-21.pdf | 21 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: sanskar 18-19.pdf | 20 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: sanskar 19-20.pdf | 20 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: sanskar.pdf | 12 Jun 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf | 4 Feb 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: sanskar comp.pdf | 29 Jan 2020 |
| OtherFile: Mangeshi Sanskar Commercial bldg.pdf | 4 Jul 2019 |
| OtherFile: Completion Certificate Sanskar.pdf | 25 May 2019 |
| Certificates of CA (Form 5)File: Mangeshi Sanskar_Form 5_17-18.pdf | 15 Oct 2018 |
| Layout approvalFile: Flor Plan-min.pdf | 31 Jul 2017 |
| Building plan approvalFile: IOD-min.pdf | 31 Jul 2017 |
| PAN CardFile: MDG_PAN-min.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Declaration of no encumbrances sanskar.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Flor Plan-min.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: IOD-min.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Sanskar Form B.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: New Architect Certificate.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Pg1-min.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: Mangeshi Constrction_Mangeshi Sanskar-I_Form-3-min.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Declaration of no encumbrances sanskar.pdf | 31 Jul 2017 |
Promoter's earlier projects13
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| MANGESHI CRYSTALP51700009923 | Kalyan, Thane | 39 | Aug 2017 | Completed | Jun 2018 | Sep 2017 |
| Mangeshi Floora | Rambaug Lane No.4 end Chikanghar Kalyan West | 110 | - | Completed | Sep 2015 | Jun 2015 |
| Mangeshi Elite | Rambag Lane No.4 end Chikanghar Kalyan West | 175 | - | Completed | Dec 2014 | Oct 2014 |
| Chandrabhaga-II | Shree Complex Chowk Kolivali Kalyan West | 63 | - | Completed | Jun 2014 | Jan 2014 |
| Vishnukunj | Adharwadi Chowk Kalyan West | 15 | - | Completed | Sep 2013 | May 2013 |
| Mangeshi Vihar | Shree Complex Chowk Wadeghar Kalyan West | 66 | - | Completed | Jun 2013 | Mar 2013 |
| Mangeshi City-II | Shree Complex Chowk Kolivali Kalyan West | 130 | - | Completed | Jun 2013 | Feb 2013 |
| Mangeshi City-I | Shree Complex Chowk Kolivali Kalyan West | 395 | - | Completed | Mar 2013 | Oct 2012 |
| Appaji Dham | Shree Complex Chowk Wadeghar Kalyan West | 94 | - | Completed | Sep 2012 | Mar 2012 |
| Mangeshi Srushti-II | Khadakpada Nr. Vasantvally Kalyan West | 179 | - | Completed | Mar 2012 | Mar 2012 |
| Mangeshi Srushti-I | Khadakpada Nr. Vasantvali Gandhare Kalyan West | 154 | - | Completed | Dec 2010 | Nov 2010 |
| Mangeshi Sahara | Chikanghar Kalyan West | 193 | - | Completed | Dec 2010 | Nov 2010 |
| Chandrabhaga Tower | Shree Complex Chowk Kolivali Kalyan West | 53 | - | Completed | Aug 2010 | Mar 2010 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 18 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 23 filed documents as one ZIP, foldered, with a manifest
Keep MANGESHI SANSKAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KHADEGOLAVALI7,600+ in Thane
Filed coordinates, straight-line distance. 155 registered projects within 2 km.
Kohinoor Eden
KGI REALTY PRIVATE LIMITED
Olympia City Phase 1
Balaji Rattan Lifespaces
Krishna Trident
Sonawane Infrastructure Private Limited
Rai s Heaven
RAI RESIDENCY Private Limited
Metro Grande Tower C and D
West Pioneer Properties India Pvt Ltd
SEASON SAHARA BUILDING NO 4 AND 5
SAMARTH SAI BUILDERS & DEVELOPERS
See every Thane project, with the district possession charts
Builder: Mangesh Dashrath Gaikar
Mangesh Dashrath Gaikar has 19 registrations on MahaRERA, including USSH KIRAN and MANGESHI CRYSTAL. Its filings disclose 13 earlier MahaRERA projects: declares 13 of 13 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if MANGESHI SANSKAR is delayed beyond 30 Jun 2018?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MANGESHI SANSKAR?
The registered promoter entity is Mangesh Dashrath Gaikar, an individual as per the filing. Its GSTIN 27AFAPG5995H1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MANGESHI SANSKAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MANGESHI SANSKAR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MANGESHI SANSKAR?
The professionals named in the filing: Architect: DECON CONSULTANT; Engineer: KHASNIS AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MANGESHI SANSKAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback