ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / MAN OPUS

Completed No litigation declared Residential / Group Housing project

MAN OPUS

By MAN GLOBAL LTD.

RG-MH-26147 · RERA P51700008395 · Last updated on MahaRERA portal: 24 Mar 2021

Source: official MahaRERA filing

Red flags

  • 104 complaints at MahaRERA
  • Completion date moved by 8 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Aug 2019Possession promisedregistration recorded completed
37 of 88Construction stages doneacross 8 buildings; furthest along: Internal walls, 85%
104Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

MAN OPUS is a Residential / Group Housing project by MAN GLOBAL LTD. in Thane, Maharashtra, registered with MahaRERA as P51700008395 on 18 Aug 2017. The registration is recorded completed; possession was promised by 30 Aug 2019. The completion date has moved by 8 months from the original filing. 104 complaints are on record with the regulator.

At a glance

Project

  • NameMAN OPUS
  • TypeResidential / Group Housing
  • Location
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700008395
  • ReraGenie IDRG-MH-26147

Builder

  • NameMAN GLOBAL LTD.
  • Entity typeCompany
  • ChairpersonRAMESHCHANDRA JHAMAKLAL MANSUKHANI
  • Managing DirectorHEENA VINAY KALANTRI
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toAug 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 Aug 2017
  • Promised completion30 Aug 2019
  • Revised completionRevised to 30 Aug 2019 (originally 31 Dec 2018)
  • Buildings8 building records
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C1 - BLDG 2, 3NA260000
C2 - BLDG 4,5NA260000
A - BLDG 8,9NA250000
RENTAL-BLDG R1NA250000
RENTAL-BLDG R2NA60000
E - BLDG 1 - PHASE 2NA250000
D1 - BLDG 7 - PHASE 2NA220000
D2- BLDG 6 - PHASE 2NA250000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 24 Mar 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

37 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Internal walls, at 85%.

C1 - BLDG 2, 382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%
C2 - BLDG 4,583%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
A - BLDG 8,955%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RENTAL-BLDG R154%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RENTAL-BLDG R220%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E - BLDG 1 - PHASE 247%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure18%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D1 - BLDG 7 - PHASE 247%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor85%
Slabs of Super Structure32%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D2- BLDG 6 - PHASE 249%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor85%
Slabs of Super Structure55%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Mar 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes15%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes5%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed274

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots274
Closed/Covered274
BuildingClosed/CoveredTotal
C1 - BLDG 2, 36161
C2 - BLDG 4,56161
A - BLDG 8,99191
RENTAL-BLDG R11010
RENTAL-BLDG R255
E - BLDG 1 - PHASE 21212
D1 - BLDG 7 - PHASE 21515
D2- BLDG 6 - PHASE 21919

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,174 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI30224.93
Proposed, not sanctioned29,452 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch11, SHIVASHAKTI, GROUND FLR, 10TH RD, VITHAL NAGAR CHS, JVPD SCHEME, VILEPARLE WEST, MUMBAI-400049

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAVINASH MHATRE AND ASSOCIATESE
ArchitectSOM DESIGNS
EngineerRAJE STRUCTURAL CONSULTANTS
PartnerRole in project
MAN GLOBAL LTD.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700001313Dec 2018 → Aug 2019

Reason as filed by the promoterDue to delay and latches on the part of environmental department who took almost three and half year to issue clearance certificate , twelve months due to conversion is auto DCR , eight months due to erroneous stay order, six months to due cancellation of existing contractors & appointment of new contractors , etc. and then only project could restart. This all delays costed not only delay of sixty eight months from land acquisition but also capital of company was locked apart from payment of interest / repayment of loans availed for construction / development purpose. The work on the project s

Litigation declared11

CaseCourtStatus
CC/17/593/2017 /2017CONSUMER COURTPENDING
CC/17/594/2017 /2017CONSUMER COURTPENDING
CC/17/596/2017 /2017CONSUMER COURTPENDING
CC/17/597/2017 /2017CONSUMER COURTPENDING
CC/17/595/2017 /2017CONSUMER COURTPENDING
CC/17/599/2017 /2017CONSUMER COURTPENDING
CC/17/600/2017 /2017CONSUMER COURTPENDING
CC/17/601/2017 /2017CONSUMER COURTPENDING
CC/17/602/2017 /2017CONSUMER COURTPENDING
CC/419/2014/2014CONSUMER COURTPENDING
CC/101/2015/2015CONSUMER COURTPENDING

Complaints filed with MahaRERA104

Case no.ComplainantRespondentFiled
CC006000000001065Sadiqali MankarRameshchandra Jhamaklal Mansukhani13/10/2017
CC006000000000917Tilkesh SoniMan Global Ltd.09/11/2017
CC006000000001881Samrat Samir PaulMan Global Ltd15/11/2017
CC006000000001600Rajiv Kumar PandeyMan Gobal Ltd15/11/2017
CC006000000001078Mr. Swarup Saha & Kusumita SahaMan Global Ltd.09/11/2017
CC006000000001825Rakesh Kumar Shyamal JhaMan Global Ltd.15/11/2017
CC006000000001955Shivnath Shivshankar GundaMan Global Ltd21/11/2017
CC006000000012186Mrs Chandra Babulal PariharMan Global Ltd.28/11/2017
CC006000000001136Mr. Srinivas YennemMan Global Ltd .31/01/2018
CC006000000001268Juliet Anthony DsouzaMan Global Ltd.15/11/2017
CC006000000044110MR. WILBRIT D RAJMAN GLOBAL LTD13/04/2018
CC006000000012220JINENDRA JAINMAN GLOBAL LIMITED01/12/2017
CC006000000012290JITENDRA JAINMAN GLOBAL LIMITED05/12/2017
CC006000000012197Mrs. Monali Chandrakant SutraveMan Global Ltd01/12/2017
CC006000000012254Rajiv Kumar KhareMAN GLOBAL LTD02/12/2017
CC006000000023070Ms. Neha ChaubeMan Global Ltd.23/01/2018
CC006000000012648Mrs. Manisha R. GuptaMan Global Ltd01/01/2018
CC006000000012666Dhiraj Kumar BirlaMan Global Ltd30/12/2017
CC006000000012700Mr. Murli Tolaram ManglaniMan Global Ltd08/01/2018
CC006000000022903Arvind Padmanabha RaoMAN Global Ltd14/01/2018
CC006000000022961Mrs. Susmita RaiMan Global Ltd23/01/2018
CC006000000023247Dhiraj Harishankar YadavMan Global Ltd06/02/2018
CC006000000023272Mr. Ashish RunwalMan Global Ltd20/02/2018
CC006000000023291Mr Ashok Kumar D PandeyMan Global Ltd16/02/2018
CC006000000023294Mrs. Vidyaa C. SoniMan Global Ltd16/02/2018
CC006000000023316Suresh SelvarajMan Global Ltd11/02/2018
CC006000000023317Raj Kumar SawMan global Ltd11/02/2018
CC006000000023320Ram Krishna KumarMan Global Ltd11/02/2018
CC006000000023343Pascoal DsilvaMan Global Ltd.15/02/2018
CC006000000023350Mr. Vikas KhannaMan Global Ltd16/02/2018
CC006000000023362Mrs. Shyampyari Harichandra YadavMan Global Ltd26/02/2018
CC006000000023415Mr. Suresh S. ChauhanMr Man Global Ltd05/03/2018
CC006000000023417Mr. Suresh Chandra VishwakarmaMan Global Ltd01/03/2018
CC006000000023436Mr. Rakesh Hiralal ParmarMan Global Ltd05/03/2018
CC006000000023664Amreen BhimaniMan Global Ltd09/03/2018
CC006000000023464Mr. Subhasis GoswamiMan Global Ltd01/03/2018
CC006000000023722VINOD JAINMAN GLOBAL LTD27/11/2018
CC006000000023548Ajit K ThakurMan Global Ltd01/03/2018
CC006000000023551Jamal Ahmad Buniyad Ali MansuriMan Global Ltd01/03/2018
CC006000000023592Manoj Kumar NatholiaMan Global Ltd03/03/2018
CC006000000023611Sameer Bhaskarrai BhattMan Global Ltd05/03/2018
CC006000000023596Hemant PareekMan Global Ltd04/03/2018
CC006000000023721MRS. SIMIN MOHAMMAD ASIFMAN GLOBAL LTD19/03/2018
CC006000000044107MR. NIKHIL KUMAR KATHANEMAN GLOBAL LTD.13/04/2018
CC006000000044117MR. DINESH VASANT RAIMAN GLOBAL LTD20/04/2018
CC006000000044019Deoki Nandan MishraMan Global Limited07/04/2018
CC006000000044053Sonal Sudhir ChaugaleMan Global Ltd08/04/2018
CC006000000044051Umesh R VedMan Global Ltd08/04/2018
CC006000000044088Rajeev KhannaNikhil Mansukhani11/04/2018
CC006000000044104MR. BRIJESH KUMAR MATHURMAN GLOBAL LTD13/04/2018
CC006000000044171DINESHKUMAR INDRAJEET SHUKLAMAN GLOBAL LTD20/04/2018
CC006000000044225MRS ANITA JAGDISHKUMAR SHUKLAMAN GLOBAL LTD23/04/2018
CC006000000044253MR. GAURAV KUMARMAN GLOBAL LTD25/04/2018
CC006000000044270MR. ATISH KUMAR VERMAMAL GLOBAL LTD25/04/2018
CC006000000044452Mr. Swapnil KadamMan Global Ltd11/05/2018
CC006000000044461Alok ChaturvediMan Global Ltd10/05/2018
CC006000000054696Aniruddh DaveMan Global Limited31/05/2018
CC006000000054908MRS. MEENAL PARABMAN GLOBAL LTD15/06/2018
CC006000000057808Mr. Gaurav Arora and Mrs. Dilnavaz MunshiMan Global Ltd24/01/2019
CC006000000055743Bharti R. Rawal and Satyam R. RawalMAN GLOBAL LIMITED10/08/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Mar 2021

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Man Opus.pdf24 Mar 2021
OtherFile: IMG-20200316-WA0034 FORCE MAJEUR.pdf20 Mar 2020
Certificates of CA (Form 3)File: Man Opus-Dec18(Form3).pdf23 Jan 2020
Certificates of CA (Form 3)File: Man Opus-Mar19(Form3).pdf23 Jan 2020
Certificates of CA (Form 3)File: Man Opus-Jun19(Form3).pdf23 Jan 2020
Certificates of CA (Form 3)File: Man Opus-Sept19(Form3).pdf23 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Man Opus-Mar19(Form5).pdf23 Jan 2020
Certificates of Architect (Form 4)File: Form -4 MAN Opus A D1 D2.pdf1 Oct 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Opus_OC 13092019.pdf19 Sep 2019
OtherFile: reasons for delay - extension.pdf27 Aug 2019
OtherFile: reasons for delay - extension.pdf27 Aug 2019
OtherFile: annexure 1.pdf27 Aug 2019
OtherFile: ANNEXURE A.pdf27 Aug 2019
OtherFile: ANNEXURE B.pdf27 Aug 2019
OtherFile: RERA UPDATE 1 _opt.pdf21 Aug 2019
OtherFile: Opus Agreement for sale Final.pdf5 Jun 2019
OtherFile: OPUS RERA AGREEMENT AMENITIES FINAL.pdf3 Jun 2019
Certificates of Architect (Form 4)File: Form 4-Opus.pdf11 May 2019
OtherFile: Opus OC.pdf8 May 2019
OtherFile: 181116161757_0001_opt.pdf12 Jan 2019
OtherFile: 181116161918_0001.pdf12 Jan 2019
OtherFile: 181116162156_0001.pdf12 Jan 2019
OtherFile: 181116162123_0001_opt.pdf12 Jan 2019
OtherFile: Man Opus Pre-Inspection-Suggestion Letter C1 C2.pdf12 Jan 2019
OtherFile: Man Opus Pre-Inspection-Suggestion Letter C1 C2.pdf12 Jan 2019
OtherFile: Man Opus Pre-Inspection- Suggestion.pdf12 Jan 2019
OtherFile: Man Opus Pre-Inspection- Suggestion 2.pdf12 Jan 2019
OtherFile: DOc 1.pdf12 Jan 2019
OtherFile: Doc 2.pdf12 Jan 2019
OtherFile: Doc 3.pdf12 Jan 2019
Certificates of CA (Form 3)File: Man Opus-31-mar-20180001.pdf9 Jan 2019
Certificates of CA (Form 3)File: Man Opus-30-jun-20180001.pdf9 Jan 2019
Certificates of CA (Form 3)File: Man Opus-30-sep-20180001.pdf9 Jan 2019
Certificates of CA (Form 5)File: Man Opus-Mar18(Form5).pdf9 Jan 2019
OtherFile: annexure -1.pdf16 Nov 2018
OtherFile: Annexure -2.pdf16 Nov 2018
OtherFile: Annexure 3.pdf16 Nov 2018
OtherFile: annexure -4.pdf16 Nov 2018
OtherFile: Annexure 5.pdf16 Nov 2018
OtherFile: Annexure 6.pdf16 Nov 2018
OtherFile: Reasons for Extension of Date of Possession in RERA- Man Opus- FINAL.pdf16 Nov 2018
OtherFile: Annexure 7 colly _opt.pdf16 Nov 2018
OtherFile: Annexure 8_opt.pdf16 Nov 2018
Building plan approvalFile: IOD.pdf29 Jul 2017
Layout approvalFile: Layout Plan.pdf29 Jul 2017
PAN CardFile: PAN Man Global Ltd.pdf29 Jul 2017
Copy of the legal title reportFile: Title certificate.pdf29 Jul 2017
Copy of the legal title reportFile: Shiralkar 1.pdf29 Jul 2017
Copy of the legal title reportFile: Shiralkar 2.pdf29 Jul 2017
Copy of the legal title reportFile: Shiralkar 3.pdf29 Jul 2017
Details of encumbrancesFile: Encumbrances.pdf29 Jul 2017
Details of encumbrancesFile: ENCUBRENCES.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf29 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC-10-4-2015-BINDER_Upload.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: SHEET-1.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: SHEET-2.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: SHEET-3.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: SHEET-4.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: SHEET-5.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: SHEET-6.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: SHEET-7.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: SHEET-8.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: SHEET-9.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: SHEET-10.pdf29 Jul 2017
Declaration in FORM BFile: Affidavit cum declaration.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH-CERT-BINDER_1.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Opus Engg Cert.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Certificate OPUS.pdf29 Jul 2017
Proforma of Allotment letterFile: Man Opus Allotment Letter.pdf29 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 8 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAN OPUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mira-Bhayandar (M Corp.)7,600+ in Thane

2 kmMAN OPUSCompleted 42Lapsed / revoked 22Other 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 125 registered projects within 2 km.

Builder: MAN GLOBAL LTD.

MAN GLOBAL LTD. has 2 registrations on MahaRERA, including MAN OPUS and SHANTI SADAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if MAN OPUS is delayed beyond 30 Aug 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAN OPUS?

The registered promoter entity is MAN GLOBAL LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAN OPUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MAN OPUS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MAN OPUS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAN OPUS?

The professionals named in the filing: Architect: AVINASH MHATRE AND ASSOCIATESE; Architect: SOM DESIGNS; Engineer: RAJE STRUCTURAL CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAN OPUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAN OPUS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAN OPUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.