Home / Browse projects / Thane, Maharashtra / MALI PINNACLE

Registered No litigation declared Residential / Group Housing project

MALI PINNACLE

By MALI INFRA

RG-MH-28442 · RERA P51700026067 · Last updated on MahaRERA portal: 18 Aug 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jan 2027Possession promisedmoved 24 months from the original
5 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 80%
34 of 113Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 112 documents Report an error

MALI PINNACLE is a Residential / Group Housing project by MALI INFRA in Thane, Maharashtra, registered with MahaRERA as P51700026067 on 15 Aug 2020. Possession is promised by 31 Jan 2027. The completion date has moved by 24 months from the original filing. 79 of the 113 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMALI PINNACLE
  • TypeResidential / Group Housing
  • Location
    • KALYAN HAJIMALANG ROAD
    • HAJIMALANG ROAD
    • Bhal
    • Ambarnath
    • Thane
    • 421306
  • Pincode421306
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700026067
  • ReraGenie IDRG-MH-28442

Builder

  • NameMALI INFRA
  • Entity typePartnership
  • PartnersGANESH JETHALAL MALI, JETHALAL GENAJI MALI, NANDALA GANESH MALI
  • Other registrations1 more →

Key dates

this monthRegisteredAug 2020First promiseJan 2025Revised toJan 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Aug 2020
  • Promised completion31 Jan 2027
  • Revised completionRevised to 31 Jan 2027 (originally 31 Jan 2025)
  • Buildings1 building record
  • Documents filed112 files

Current status

70%79 of 113 units booked
80.8%Work done, per cost certificate

Figures as on 18 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MALI PINNACLENA30171130113

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 80%.

MALI PINNACLE: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 18 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed53

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots53
Closed/Covered13
Open Space40

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,150 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Oct 2025
LandownerVillageDistrict
GANESH MALIDOMBIVLIThane

Approvals and building plan

Sanctioning authorityKalyan Dombivali Municipal Corporation, Kalyan
Permissible FSI2324.22
Proposed, not sanctioned2,324 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch10 11 12 15 16 KASTURI ASHISH DAVDI NAKA KALYAN SHIL ROAD THANE MAHARASHTRA
Estimated costRs 17.24 cr
Cost incurredRs 13.93 cr
Work done80.76%
BuildingWingEstimatedIncurred
MALI PINNACLENARs 16.58 crRs 13.93 cr
-NARs 66.33 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR MADAN GADGIL
EngineerER ATUL KURTADKAR
Chartered AccountantKriti B Gada
Chartered AccountantPratik N Pandya and Co
Chartered AccountantRajesh Murugan And Associates
PartnerRole in project
MALI INFRA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700026011Jan 2025 → Jan 2027

Reason as filed by the promoterDue to some of shortage we are not able to complete project. Request you to kindly grant us extension till 31/01/2027.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600081Vijay Badriprasad RajbharMALI INFRA05/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jan 2027

Documents filed112

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_Jun 2026.pdf18 Aug 2026
Withdrawal Update Form 2File: Form 2_Jun 2026.pdf18 Aug 2026
Withdrawal Update Form 3File: Form 3_Jun 2026.pdf18 Aug 2026
Withdrawal Update Form 1File: form 1 mali pinnacle Mar-26.pdf25 May 2026
Withdrawal Update Form 1File: form 1 mali pinnacle Mar-26.pdf25 May 2026
Withdrawal Update Form 1File: form 1 mali pinnacle Mar-26.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 Mali pinnacle Mar-26.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 Mali pinnacle Mar-26.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 Mali pinnacle Mar-26.pdf25 May 2026
Withdrawal Update Form 3File: Form 3 Mali Pinnacle Mar-26.pdf25 May 2026
Withdrawal Update Form 3File: Form 3 Mali Pinnacle Mar-26.pdf25 May 2026
Withdrawal Update Form 3File: Form 3 Mali Pinnacle Mar-26.pdf25 May 2026
Withdrawal Update Form 1File: Form -1 Dec 25_mali pinnacle.pdf29 Apr 2026
Withdrawal Update Form 2File: form 2_Dec 25_mali pinnacle.pdf29 Apr 2026
Withdrawal Update Form 3File: form 3_Dec 25_mali pinnacle.pdf29 Apr 2026
Form 5 (FY 2024-2025)File: Form 5 FY 2024-25.pdf30 Mar 2026
Withdrawal Update Form 1File: form 1 mali pinnacle Sep 25.pdf2 Feb 2026
Withdrawal Update Form 2File: form 2 mali pinnacle Sep 25.pdf2 Feb 2026
Withdrawal Update Form 3File: form 3 mali pinnacle Sep 25.pdf2 Feb 2026
Withdrawal Update Form 1File: Form 1 June 2025.pdf19 Nov 2025
Withdrawal Update Form 2File: form 2 June 2025.pdf19 Nov 2025
Withdrawal Update Form 3File: form 3 June 2025.pdf19 Nov 2025
Disclosure of sold/ booked inventoryFile: Pinnacle Inventory.pdf16 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Pinnacle form 1.pdf8 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pinnacle form 3 - converted.pdf8 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 pinnacle.pdf8 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure letter Sold booked inventory.pdf12 Mar 2025
Other - TechnicalFile: 6.pdf12 Mar 2025
Declaration in FORM BFile: Form B.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Dec 24.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclosure letter Sold booked inventory_Dec 24.pdf3 Mar 2025
Declaration in FORM BFile: Form B.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure letter Sold booked inventory.pdf14 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: format A.pdf14 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A ganesh sir.pdf14 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A jethalal.pdf14 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf14 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: Secaued.pdf14 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23.pdf15 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 23-24.pdf15 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 pinnacle december.pdf11 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 pinnacle december.pdf11 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 pinnacle december.pdf11 Jan 2025
Declaration in FORM BFile: Notary B.pdf26 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A 2020-2021.pdf25 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A 2021-2022.pdf25 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A 2022-2023.pdf25 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A 2023-2024.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: artichecht 05-10-2024.pdf23 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 08-10-2024.pdf23 Dec 2024
Declaration about Commencement CertificateFile: form D.pdf23 Dec 2024
CERSAI detailsFile: Cersai.pdf23 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9th slab Certificate.pdf17 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10th slab Certificate.pdf17 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11th slab.pdf17 Nov 2023
Other - TechnicalFile: Mali Pinnacle Payment Schedule.pdf27 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 dtd-13-02-2023.pdf6 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 - Dtd- 16-05-2023.pdf6 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Dtd-31-03-2022.pdf6 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Dtd-30-06-2022.pdf6 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- dtd- 03-11-2022.pdf6 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Dtd-14-02-2023.pdf6 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dtd-16-05-2023.pdf6 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1.pdf2 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1.pdf2 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf30 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf30 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf12 Jul 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf13 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Mali_Infra__1_ FORM NO 3.pdf31 Mar 2022
Building plan approvalFile: sheet 1.pdf21 Mar 2022
Building plan approvalFile: sheet 2.pdf21 Mar 2022
Building plan approvalFile: sheet 3.pdf21 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: sheet 1.pdf21 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: sheet 2.pdf21 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: sheet 3.pdf21 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Mali CC.pdf21 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mali infra architects certificate.pdf21 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MALI INFRA engineer's certificate.pdf21 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form_5_Mali_Infra.pdf30 Sep 2021

How this compares with Thane

70%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MALI PINNACLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HAJIMALANG ROAD7,600+ in Thane

2 kmMALI PINNACLECompleted 2Lapsed / revoked 7Other 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 39 registered projects within 2 km.

Builder: MALI INFRA

MALI INFRA has 2 registrations on MahaRERA, including MALI PINNACLE and Mali Avenue. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if MALI PINNACLE is delayed beyond 31 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MALI PINNACLE?

The registered promoter entity is MALI INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MALI PINNACLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MALI PINNACLE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MALI PINNACLE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MALI PINNACLE?

The professionals named in the filing: Architect: AR MADAN GADGIL; Engineer: ER ATUL KURTADKAR; Chartered Accountant: Kriti B Gada; Chartered Accountant: Pratik N Pandya and Co; Chartered Accountant: Rajesh Murugan And Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MALI PINNACLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MALI PINNACLE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MALI PINNACLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.