MAHAVIR SAPPHIRE B

By Mahavir Estate and Properties

RG-MH-05267 · RERA P99000050557 · Last updated on MahaRERA portal: 18 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
206 of 275Construction stages doneacross 25 buildings; furthest along: Slabs of Super Structure, 80%
3 of 25Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 90 documents Report an error

MAHAVIR SAPPHIRE B is a Residential / Group Housing project by Mahavir Estate and Properties in Palghar, Maharashtra, registered with MahaRERA as P99000050557 on 21 Apr 2023. Possession is promised by 31 Dec 2028. 22 of the 25 units on this registration are recorded sold or booked, and 206 of 275 construction stages are filed complete.

At a glance

Project

  • NameMAHAVIR SAPPHIRE B
  • TypeResidential / Group Housing
  • Location
    • Boisar Chilhar Road
    • Boisar
    • Betegaon
    • Palghar
    • 401501
  • Pincode401501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000050557
  • ReraGenie IDRG-MH-05267

Builder

  • NameMahavir Estate and Properties
  • Entity typePartnership
  • GSTIN27AAPFM3746C1Z6
  • PartnersRajesh Mahendra Mehta, Minal Mahendra Mehta, Sonal Manoj Mehta
  • Other registrations3 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredApr 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Apr 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings25 building records
  • Documents filed90 files

Current status

88%22 of 25 units booked
85.7%Work done, per cost certificate

Figures as on 18 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MAHAVIR SAPPHIRE 8NA30303
MAHAVIR SAPPHIRE 9NA30303
MAHAVIR SAPPHIRE 10NA30303
MAHAVIR SAPPHIRE 11NA30303
MAHAVIR SAPPHIRE 12NA30303
MAHAVIR SAPPHIRE 13NA30303
MAHAVIR SAPPHIRE 14NA30303
MAHAVIR SAPPHIRE 15NA30404
MAHAVIR SAPPHIRE 16NA30000
MAHAVIR SAPPHIRE 17NA30000
MAHAVIR SAPPHIRE 18NA30000
MAHAVIR SAPPHIRE 19NA30000
MAHAVIR SAPPHIRE 20NA30000
MAHAVIR SAPPHIRE 21NA30000
MAHAVIR SAPPHIRE 22NA30000
MAHAVIR SAPPHIRE 29NA30000
MAHAVIR SAPPHIRE 30NA30000
MAHAVIR SAPPHIRE 31NA30000
MAHAVIR SAPPHIRE 32NA30000
MAHAVIR SAPPHIRE 23NA30000
MAHAVIR SAPPHIRE 24NA30000
MAHAVIR SAPPHIRE 25NA30000
MAHAVIR SAPPHIRE 26NA30000
MAHAVIR SAPPHIRE 27NA30000
MAHAVIR SAPPHIRE 28NA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 18 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 25 buildings; the table lists the first 20.

206 of 275 construction stages are filed complete across 25 buildings. The stage furthest along is Slabs of Super Structure, at 80%.

MAHAVIR SAPPHIRE 891%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 9100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 1091%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 1191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 1291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 1391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 1491%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 1591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 1691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 1791%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 1891%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 1991%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 2091%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 2191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 2291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MAHAVIR SAPPHIRE 2960%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
MAHAVIR SAPPHIRE 3060%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
MAHAVIR SAPPHIRE 3143%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
MAHAVIR SAPPHIRE 3254%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
MAHAVIR SAPPHIRE 2362%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 18 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Closed/Covered25
Open Space1
BuildingClosed/CoveredOpen SpaceTotal
MAHAVIR SAPPHIRE 8101
MAHAVIR SAPPHIRE 9101
MAHAVIR SAPPHIRE 10101
MAHAVIR SAPPHIRE 11101
MAHAVIR SAPPHIRE 12101
MAHAVIR SAPPHIRE 13101
MAHAVIR SAPPHIRE 14101
MAHAVIR SAPPHIRE 15101
MAHAVIR SAPPHIRE 16101
MAHAVIR SAPPHIRE 17101
MAHAVIR SAPPHIRE 18101
MAHAVIR SAPPHIRE 19101
MAHAVIR SAPPHIRE 20101
MAHAVIR SAPPHIRE 21101
MAHAVIR SAPPHIRE 22101
MAHAVIR SAPPHIRE 29101
MAHAVIR SAPPHIRE 30101
MAHAVIR SAPPHIRE 31101
MAHAVIR SAPPHIRE 32101
MAHAVIR SAPPHIRE 23101
MAHAVIR SAPPHIRE 24101
MAHAVIR SAPPHIRE 25101
MAHAVIR SAPPHIRE 26101
MAHAVIR SAPPHIRE 27112
MAHAVIR SAPPHIRE 28101

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,289 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Oct 2024

Approvals and building plan

Sanctioning authorityZilla Adhikari Palghar
Permissible FSI5263.76
Proposed, not sanctioned5,264 sq m
Buildings approved25
Buildings sanctioned25

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPalghar
Estimated costRs 15.92 cr
Cost incurredRs 13.64 cr
Work done85.69%
BuildingWingEstimatedIncurred
MAHAVIR SAPPHIRE 22NARs 73.31 lakhRs 73.31 lakh
MAHAVIR SAPPHIRE 29NARs 73.31 lakhRs 46.72 lakh
MAHAVIR SAPPHIRE 30NARs 73.31 lakhRs 46.72 lakh
MAHAVIR SAPPHIRE 31NARs 73.31 lakhRs 35.89 lakh
MAHAVIR SAPPHIRE 32NARs 73.31 lakhRs 35.89 lakh
MAHAVIR SAPPHIRE 23NARs 73.31 lakhRs 42.32 lakh
MAHAVIR SAPPHIRE 24NARs 73.31 lakhRs 73.31 lakh
MAHAVIR SAPPHIRE 25NARs 73.31 lakhRs 73.31 lakh
MAHAVIR SAPPHIRE 26NARs 73.31 lakhRs 50.42 lakh
MAHAVIR SAPPHIRE 27NARs 73.31 lakhRs 50.42 lakh
MAHAVIR SAPPHIRE 28NARs 73.31 lakhRs 50.42 lakh
MAHAVIR SAPPHIRE 8NARs 62.15 lakhRs 62.15 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVastushilp Associates
EngineerDARSH CONSULT
EngineerPARAG SHAH
Chartered AccountantL N Vasa & Co
Chartered AccountantRajesh Balsara
Chartered AccountantC D Chauhan and Company
PartnerRole in project
Mahavir Estate and Properties-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed90

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARCHITECT SAPPHIRE B0.pdf18 Apr 2026
Withdrawal Update Form 2File: ENGINEER SAPPHIRE B.pdf18 Apr 2026
Withdrawal Update Form 3File: CA SAPPHIRE B.pdf18 Apr 2026
Withdrawal Update Form 1File: Architect Sapphire B_compressed.pdf19 Jan 2026
Withdrawal Update Form 1File: Architect Sapphire B_compressed.pdf19 Jan 2026
Withdrawal Update Form 2File: Engineer Sapphire B_compressed.pdf19 Jan 2026
Withdrawal Update Form 2File: Engineer Sapphire B_compressed.pdf19 Jan 2026
Withdrawal Update Form 3File: CA Sapphire B_compressed.pdf19 Jan 2026
Withdrawal Update Form 3File: CA Sapphire B_compressed.pdf19 Jan 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CA Sapphire B.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Sapphire B.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Sapphire B.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sapphire B Architect Oct Dec 2024 1.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sapphire B CA Oct Dec 2024.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sapphire B Engineer Oct Dec 2024.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sapphire B Architect 1.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sapphire B CA.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sapphire B Engineer 1.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_20241010_0002-4.pdf12 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: P99000050557 (1).pdf12 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect_20240716_0001-5-18.pdf17 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Signed.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Signed.pdf17 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Signed_compressed.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Signed.pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Signed.pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Signed_compressed (1).pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_0001.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Signed.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Signed_compressed.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Signed.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Signed_compressed.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer organized (1)_compressed.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA organized_pages-to-jpg-0001.pdf19 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect organized_compressed.pdf15 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA organized.pdf15 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Sapphire B_0001.pdf11 Jul 2023
Declaration about Commencement CertificateFile: Declaration CC0001.pdf23 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect 22-6.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer _0001.pdf23 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA 20-6.pdf23 Jun 2023
Layout approvalFile: marked layout final final.pdf22 Jun 2023
Details of encumbrances concerned to FinanceFile: No Encumbrance.pdf22 Jun 2023
Details of encumbrances concerned to LegalFile: No Encumbrance.pdf22 Jun 2023
Copy of Layout Approval (in case of layout)File: marked layout final final.pdf22 Jun 2023
CERSAI detailsFile: 20062023CERSAI_Search_Report_200271998710_For_Asset_Based_Search_20_06_2023_16_17_58_575.p22 Jun 2023
CERSAI detailsFile: 20062023CERSAI_Search_Report_200271998710_For_Asset_Based_Search_20_06_2023_16_17_58_575.p22 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf17 Apr 2023
Details of encumbrances concerned to FinanceFile: Finance encumbrance.pdf14 Apr 2023
Details of encumbrances concerned to LegalFile: Finance encumbrance.pdf14 Apr 2023
Details of encumbrances concerned to FinanceFile: Declaration.pdf12 Apr 2023
Details of encumbrances concerned to LegalFile: Declaration.pdf12 Apr 2023
Other - FinanceFile: Declaration.pdf12 Apr 2023
Proforma of Agreement for saleFile: AGREEMENT FOR SALE Mahavir Sapphire 6-4-23.pdf6 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Revised.pdf5 Apr 2023
Details of encumbrances concerned to FinanceFile: No Encumbrace_organized.pdf31 Mar 2023
Details of encumbrances concerned to FinanceFile: No Encumbrace_organized.pdf31 Mar 2023
Details of encumbrances concerned to LegalFile: No Encumbrace_organized.pdf31 Mar 2023
Details of encumbrances concerned to LegalFile: No Encumbrace_organized.pdf31 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_compressed.pdf27 Mar 2023
CERSAI detailsFile: CERSAI Declaration.pdf27 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 1.pdf24 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure RM.pdf24 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure SM.pdf24 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure MM.pdf24 Mar 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf24 Mar 2023
Declaration about Commencement CertificateFile: Format CC.pdf23 Mar 2023
CERSAI detailsFile: MEPCERSAI_Search_Report_200263982919_For_Asset_Based_Search_23_03_2023_12_55_29_722.pdf23 Mar 2023
Layout approvalFile: RERA MARKED PHASE 2.pdf22 Mar 2023
Building plan approvalFile: TYPE E (1).pdf22 Mar 2023
Building plan approvalFile: TYPE E1.pdf22 Mar 2023
Building plan approvalFile: TYPE F.pdf22 Mar 2023
Building plan approvalFile: TYPE F1.pdf22 Mar 2023
Building plan approvalFile: TYPE G.pdf22 Mar 2023
Building plan approvalFile: TYPE G1.pdf22 Mar 2023
Copy of the legal title reportFile: Legal Title Report.pdf22 Mar 2023
Details of encumbrances concerned to FinanceFile: No Encumbrace.pdf22 Mar 2023
Details of encumbrances concerned to LegalFile: No Encumbrace.pdf22 Mar 2023
Copy of Layout Approval (in case of layout)File: RERA MARKED PHASE 2.pdf22 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: TYPE E (1).pdf22 Mar 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
MAHAVIR SAPPHIREP99000048428Boisar, Palghar7Jan 2023OngoingDec 2027Not due yet

How this compares with Palghar

88%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAHAVIR SAPPHIRE B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Boisar3,200+ in Palghar

2 kmMAHAVIR SAPPHIRE BCompleted 4Lapsed / revoked 18Other 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 52 registered projects within 2 km.

Builder: Mahavir Estate and Properties

MAHAVIR ESTATE AND PROPERTIES has 4 registrations on MahaRERA, including MAHAVIR SAPPHIRE and MAHAVIR SAPPHIRE B. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if MAHAVIR SAPPHIRE B is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAHAVIR SAPPHIRE B?

The registered promoter entity is Mahavir Estate and Properties, a partnership as per the filing. Its GSTIN 27AAPFM3746C1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAHAVIR SAPPHIRE B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MAHAVIR SAPPHIRE B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAHAVIR SAPPHIRE B?

The professionals named in the filing: Architect: Vastushilp Associates; Engineer: DARSH CONSULT; Engineer: PARAG SHAH; Chartered Accountant: L N Vasa & Co; Chartered Accountant: Rajesh Balsara; Chartered Accountant: C D Chauhan and Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHAVIR SAPPHIRE B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHAVIR SAPPHIRE B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHAVIR SAPPHIRE B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.