MAHAVIR RESIDENCY
RG-MH-92257 · RERA P51700012556 · Last updated on MahaRERA portal: 6 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 54 months
- 5 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MAHAVIR RESIDENCY is a Residential / Group Housing project by SHREE SALASAR REALTY in Thane, Maharashtra, registered with MahaRERA as P51700012556 on 4 Sep 2017. Possession was promised by 4 Jun 2026 and is now 4 months past that date. The completion date has moved by 54 months from the original filing. 21 of the 44 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameMAHAVIR RESIDENCY
- TypeResidential / Group Housing
- Location
- ADARSH PARK ROAD
- ADARSH PARK
- Bhiwandi (M Corp.)
- Bhiwandi
- Thane
- 421302
- Pincode421302
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700012556
- ReraGenie IDRG-MH-92257
Builder
- NameSHREE SALASAR REALTY
- Entity typePartnership
- PartnerPRAVIN MUKESH MISTRY
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Sep 2017
- Promised completion4 Jun 2026
- Revised completionRevised to 4 Jun 2026 (originally 30 Dec 2021)
- Buildings1 building record
- Documents filed98 files
Current status
Figures as on 6 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MAHAVIR RESIDENCY | NA | 13 | 11 | 44 | 0 | 44 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
MAHAVIR RESIDENCY: 73% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 6 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed20
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| MAHAVIR RESIDENCY | NA | Rs 12.00 cr | Rs 11.40 cr |
| - | NA | Rs 40.00 lakh | Rs 38.00 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Abdul Maajid |
| Engineer | Aditya Deshmukh |
| Chartered Accountant | CP Lohia & Co. |
| Chartered Accountant | Rajnikant Vadigoppula |
| Partner | Role in project |
|---|---|
| SHREE SALASAR REALTY | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterProject delayed due to covid situation.
Reason as filed by the promoter1. Project delayed due to covid situation
Reason as filed by the promoterThe building has completed in respect to all the construction activity and finishing work. Since the project has got the CRZ NOC in 2013, but due to change in alignment of CRZ line - 2019 changed as per the CRZ notification dated 25/08/2023, the clearance is yet to receive from the MCZMA Department, due to which our Occupation Certificate process is not able to proceed further.
Reason as filed by the promoterThe building has completed in respect to all the construction activity and finishing work. We have already submitted Architect Certificate for 100% completion of project. The reason behind delay of Occupancy Certificate is that the project has got the CRZ NOC in 2013, but due to change in alignment of CRZ line - 2019 changed as per the CRZ notification dated 25/08/2023, the clearance is yet to receive from the MCZMA Department, due to which our Occupancy Certificate process is not able to proceed further. Bhiwandi Nizampur City Municipal Corporation also wrote a letter to MCZMA that in respect
Reason as filed by the promoterWe, Shree Salasar Realty, the promoter of project “Mahavir Residency” having MahaRERA Registration No. P51700012556, hereby declare and confirm that there is no correction or change required in any of the project details submitted and available on the MahaRERA portal in respect of this project. We further request the Hon'ble Authority to kindly grant an extension of the MahaRERA Project Registration up to 4th June 2026, being the date of issuance of the Occupancy Certificate (OC) for the said project. Thanking You
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed98
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: Form 5 Shree Salasar Realty 2025-26 Signed.pdf | 6 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Q1.pdf | 3 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Q2.pdf | 3 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Q3.pdf | 3 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Q1.pdf | 3 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Q2.pdf | 3 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Q3.pdf | 3 Feb 2026 |
| Withdrawal Update Form 3File: SHREE SALASAR_Q1 2025-26 Signed.pdf | 3 Feb 2026 |
| Withdrawal Update Form 3File: SHREE SALASAR_Q2 2025-26 Signed.pdf | 3 Feb 2026 |
| Withdrawal Update Form 3File: SHREE SALASAR_Q3 2025-26 Signed.pdf | 3 Feb 2026 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 6 Oct 2025 |
| Withdrawal Update Form 2File: Engineer Certificate.pdf | 6 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Q4.pdf | 6 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5.pdf | 6 Oct 2025 |
| Form 5 (FY 2019-2020)File: Form 5 2019-20.pdf | 23 Jun 2025 |
| Form 5 (FY 2018-2019)File: Form 5 2018-19.pdf | 23 Jun 2025 |
| Form 5 (FY 2017-2018)File: Form 5 2017-18.pdf | 23 Jun 2025 |
| Form 5 (FY 2023-2024)File: FORM 5 SIGNED.pdf | 21 Jun 2025 |
| Form 5 (FY 2022-2023)File: Form 5 202223.pdf | 21 Jun 2025 |
| Form 5 (FY 2021-2022)File: Form 5 202223.pdf | 21 Jun 2025 |
| Form 5 (FY 2020-2021)File: Form 5 2020-21.pdf | 21 Jun 2025 |
| Declaration in FORM BFile: Form B.pdf | 9 Apr 2025 |
| Declaration in FORM BFile: Form B.pdf | 18 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Archeitech Certificate.pdf | 18 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 Q1.pdf | 18 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 Q2.pdf | 18 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 Q3.pdf | 18 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 18 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold or booked.pdf | 18 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SIGNED.pdf | 14 Feb 2025 |
| Declaration in FORM BFile: Form B SSR.pdf | 2 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 29 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 29 May 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Certificate Legal.pdf | 14 May 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Certificate Finance.pdf | 14 May 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance Certificate Legal.pdf | 14 May 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance Certificate Finance.pdf | 14 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 14 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 14 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - March 23.pdf | 14 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - March 24.pdf | 14 May 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf | 14 May 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_200306622226_For_Asset_Based_Search_14_05_2024_19_02_33_065.pdf | 14 May 2024 |
| Certificates of CA (Form 3)File: FORM 3 SSR 2023-24 Q2.pdf | 14 May 2024 |
| Certificates of CA (Form 3)File: FORM 3 SSR 2023-24 Q3.pdf | 14 May 2024 |
| Certificates of CA (Form 3)File: FORM 3 SSR 2023-24 Q4.pdf | 14 May 2024 |
| Certificates of CA (Form 3)File: FORM 3 SSR 2023-24 Q1.pdf | 31 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold.pdf | 14 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 30062022.pdf | 14 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 30092022.pdf | 14 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 31122022.pdf | 14 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 31032023.pdf | 14 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 202223.pdf | 14 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE SHREE SALASAR REALTY,.pdf | 19 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf | 10 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf | 10 Apr 2023 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf | 28 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form - 2A.pdf | 28 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf | 28 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22.pdf | 24 Mar 2023 |
| Details of encumbrancesFile: Encumbrances 31072017.pdf | 11 Feb 2023 |
| Certificates of CA (Form 5)File: Form 5 2021-22.pdf | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf | 9 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 Q1 2020-21.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 Q2 2020-21.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 Q3 2020-21.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 Q4 2020-21.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 Q1 2021-22.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 Q2 2021-22.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 Q3 2021-22.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 Q4 2021-22.pdf | 1 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-19.pdf | 26 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf | 26 Dec 2021 |
| Certificates of CA (Form 3)File: Q1 2017-18_compressed.pdf | 25 Dec 2021 |
| Certificates of CA (Form 3)File: Q2 2017-18_compressed.pdf | 25 Dec 2021 |
| Certificates of CA (Form 3)File: Q3 2017-18_compressed.pdf | 25 Dec 2021 |
| Certificates of CA (Form 3)File: Q4 2017-18_compressed.pdf | 25 Dec 2021 |
| Certificates of CA (Form 3)File: Q1 2018-19_compressed.pdf | 25 Dec 2021 |
| Certificates of CA (Form 3)File: Q2 2018-19_compressed.pdf | 25 Dec 2021 |
| Certificates of CA (Form 3)File: Q3 2018-19_compressed.pdf | 25 Dec 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 98 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MAHAVIR RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near ADARSH PARK7,600+ in Thane
Filed coordinates, straight-line distance. 36 registered projects within 2 km.
GODREJ UPAVAN
PRAKHHYAT DWELLINGS LLP
DGT - Sector 3A - Cluster 2 - Phase 1
ADRIKA DEVELOPERS PRIVATE LIMITED
DOSTI GREATER THANE - PHASE 1
ADRIKA DEVELOPERS PRIVATE LIMITED
Dosti Greater Thane - Sector 3A - Cluster 1B -
ADRIKA DEVELOPERS PRIVATE LIMITED
USHA RESIDENCY
SHREE BUDHDEV INFRA
NARAYANI DHAM BUILDING NO 2A AND 2B
MAYA DEVELOPER
See every Thane project, with the district possession charts
Builder: SHREE SALASAR REALTY
SHREE SALASAR REALTY has 1 registration on MahaRERA, including MAHAVIR RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that MAHAVIR RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if MAHAVIR RESIDENCY is delayed beyond 4 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MAHAVIR RESIDENCY?
The registered promoter entity is SHREE SALASAR REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MAHAVIR RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MAHAVIR RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MAHAVIR RESIDENCY?
The professionals named in the filing: Architect: Abdul Maajid; Engineer: Aditya Deshmukh; Chartered Accountant: CP Lohia & Co.; Chartered Accountant: Rajnikant Vadigoppula. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MAHAVIR RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback