Home / Browse projects / Nagpur, Maharashtra / Mahalaxmi City Phase II

Completed No litigation declared Residential / Group Housing project

Mahalaxmi City Phase II

By GRUHLAXMI LIFE SPACE PRIVATE LIMITED

RG-MH-01091 · RERA P50500002647 · Last updated on MahaRERA portal: 28 Jun 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
May 2022Possession promisedregistration recorded completed
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 95%
0Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

Mahalaxmi City Phase II is a Residential / Group Housing project by GRUHLAXMI LIFE SPACE PRIVATE LIMITED in Nagpur, Maharashtra, registered with MahaRERA as P50500002647 on 2 Aug 2017. The registration is recorded completed; possession was promised by 24 May 2022. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameMahalaxmi City Phase II
  • TypeResidential / Group Housing
  • Location
    • Koradi Road
    • Bokhara
    • Nagpur (Rural)
    • Nagpur
    • 441111
  • Pincode441111
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500002647
  • ReraGenie IDRG-MH-01091

Builder

  • NameGRUHLAXMI LIFE SPACE PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorDhirendra Kumar Gupta
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseNov 2020Revised toMay 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on2 Aug 2017
  • Promised completion24 May 2022
  • Revised completionRevised to 24 May 2022 (originally 24 Nov 2020)
  • Buildings2 building records
  • Documents filed71 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block No 17 B1NA90000
Block No 17B1NA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 28 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 95%.

Block No 17 B152%
ActivityProgress
Excavation95%
Basement (if any)95%
Podiums (if any)0%
Plinth95%
Stilt Floor95%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises27%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Block No 17B152%
ActivityProgress
Excavation95%
Basement (if any)95%
Podiums (if any)0%
Plinth95%
Stilt Floor95%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises27%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Closed/Covered9
Open Space13
BuildingClosed/CoveredOpen SpaceTotal
Block No 17 B18311
Block No 17B111011

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area435 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Sudesh Chandra Babulalji GuptaBokharaNagpur

Approvals and building plan

Permissible FSI2082.67
Proposed, not sanctioned843 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDharampeth, Nagpur

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Punit Gupta
ArchitectAr Saurabh Bhanarkar
ArchitectAr Abhishek Thakur
EngineerSkyline Consulting Engineer Pvt Ltd
EngineerSagar Wankhede
EngineerMr Pankaj Arya
Chartered AccountantK K S P & Company
Chartered AccountantBharat Singhal & Co
Chartered AccountantAtul Kumar & Associates
Chartered AccountantJ P Associates
PartnerRole in project
GRUHLAXMI LIFE SPACE PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500008702Nov 2020 → Nov 2021

Reason as filed by the promoterDear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies are observed in compliance which is under rectification. We feel regret for delay in execution of the project due to Pandemic COVID-19. With considering the Pandemic situation and shortfall in manpower we request you to kindly grant extension of one year due to force majeure and do the needful.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Feb 2023

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 ( Phase II) with annex.pdf28 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5- Phase 2- RERA.pdf7 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MLC_79 Unit.pdf3 Feb 2023
Certificates of CA (Form 5)File: Form 5- FY 20-21 Phase II.pdf2 Aug 2022
Certificates of CA (Form 5)File: Form 5- FY 20-21 Phase II.pdf2 Aug 2022
Certificates of CA (Form 5)File: Form 5- FY 20-21 Phase II f.pdf2 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5- FY 20-21 Phase II.pdf2 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5- FY 20-21 Phase II.pdf2 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1_Dec-20_P-II.pdf22 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1_June-21_P-II.pdf22 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1_March-20_P-II.pdf22 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1_Sep-20_P-II.pdf22 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_P-2_Dec-20.pdf22 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_P-3_Dec-20.pdf22 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2(Phase-II).pdf22 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_P-2_March-20.pdf22 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: From-2A_P-2_Dec-20.pdf22 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A(Phase-II).pdf22 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A_P-2_March-20.pdf22 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_P-2_Sep-20.pdf21 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A_P-2_Sep-20.pdf21 Aug 2021
Certificates of CA (Form 3)File: Form-3 (Phase-II).pdf21 Aug 2021
Certificates of CA (Form 3)File: Form-3 (Phase-II) 31-03.pdf21 Aug 2021
Certificates of CA (Form 3)File: Form-3 (Phase-II) 31-12.pdf21 Aug 2021
Certificates of CA (Form 3)File: CA P-II.pdf21 Aug 2021
Certificates of CA (Form 3)File: CA Phase-II.pdf17 Aug 2021
Declaration about Commencement CertificateFile: Declaration_RERA 1.pdf16 Aug 2021
Declaration about Commencement CertificateFile: Declaration_RERA 1.pdf16 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 (Phase-II).pdf16 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2(Phase-II).pdf16 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A(Phase-II).pdf16 Aug 2021
Disclosure of sold/ booked inventoryFile: Discosure Sold (Phase-II).pdf16 Aug 2021
Certificates of CA (Form 5)File: F5P2.pdf30 Sep 2020
Certificates of CA (Form 3)File: P2_Form3_31102019.pdf15 Apr 2020
Certificates of CA (Form 3)File: P2_Form3_31012020.pdf15 Apr 2020
OtherFile: PhaseiiBoMUnit list declaration311019.pdf3 Nov 2019
Certificates of CA (Form 5)File: P2F5.pdf10 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase2FORM1ArcQtr300419.pdf27 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: phase2Form2enggQ11920.pdf27 Jun 2019
Certificates of CA (Form 3)File: PHASE2Form3CAQ11920.pdf27 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate-Phase ii- Oct-18.pdf16 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate-Phase ii- Jan-19.pdf16 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Engineer Certificate-Phase ii-Oct-18.pdf16 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Engineer Certificate-Phase ii.pdf16 Apr 2019
Certificates of CA (Form 3)File: Form3phase231OCT18.pdf16 Apr 2019
Certificates of CA (Form 3)File: Form3phase231JAN19.pdf16 Apr 2019
OtherFile: Undertaking Information for Bank account.pdf16 Apr 2019
OtherFile: SoldunitstatustoBOM29032019.pdf16 Apr 2019
Certificates of CA (Form 5)File: MLC Form 5 phase 2.pdf30 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: Mahalaxmi Phase II - Commencement Certificate.pdf9 Apr 2018
Building plan approvalFile: Building Plan.pdf28 Jul 2017
Layout approvalFile: Sanction Layout 01.pdf28 Jul 2017
Layout approvalFile: Revised Layout.pdf28 Jul 2017
PAN CardFile: PAN of Company.pdf28 Jul 2017
PAN CardFile: Annexure A Certificate_of_Incorporation .PDF28 Jul 2017
Copy of the legal title reportFile: Legal Search Report.pdf28 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Sanction Layout 01.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Revised Layout.pdf28 Jul 2017
Building Plan Approval (IOD)File: Building Plan.pdf28 Jul 2017
Declaration in FORM BFile: Form B Phase II.pdf28 Jul 2017
Declaration in FORM BFile: Annexure (Bank of Maharashtra Consent for Release).pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase II.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E CertificateII.pdf28 Jul 2017
Certificates of CA (Form 3)File: FORM 3 PHASE II.pdf28 Jul 2017
Certificates of CA (Form 3)File: Annexure (Bank of Maharashtra Consent for Release).pdf28 Jul 2017
Proforma of Allotment letterFile: Allotment Letter Phase II.pdf28 Jul 2017
Proforma of Allotment letterFile: ATS Draft for RERA Phase II.pdf28 Jul 2017
OtherFile: Annexure (Bank of Maharashtra Consent for Release).pdf28 Jul 2017
OtherFile: Self Declaration Phase II.pdf28 Jul 2017
OtherFile: Phasewise Layout.pdf28 Jul 2017

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one moved by 18 months
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mahalaxmi City Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bokhara2,800+ in Nagpur

2 kmMahalaxmi City Phase IICompleted 10Lapsed / revoked 5Other 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 34 registered projects within 2 km.

Builder: GRUHLAXMI LIFE SPACE PRIVATE LIMITED

Gruhlaxmi Life Space Private LImited has 3 registrations on MahaRERA, including Mahalaxmi City Phase I and Mahalaxmi City Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Mahalaxmi City Phase II is delayed beyond 24 May 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mahalaxmi City Phase II?

The registered promoter entity is GRUHLAXMI LIFE SPACE PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mahalaxmi City Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mahalaxmi City Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mahalaxmi City Phase II?

The professionals named in the filing: Architect: Ar Punit Gupta; Architect: Ar Saurabh Bhanarkar; Architect: Ar Abhishek Thakur; Engineer: Skyline Consulting Engineer Pvt Ltd; Engineer: Sagar Wankhede; Engineer: Mr Pankaj Arya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mahalaxmi City Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mahalaxmi City Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mahalaxmi City Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.