Mahalaxmi City Phase I
By Gruhlaxmi Life Space Private LImited
RG-MH-00923 · RERA P50500002523 · Last updated on MahaRERA portal: 7 Feb 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 53 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mahalaxmi City Phase I is a Residential / Group Housing project by Gruhlaxmi Life Space Private LImited in Nagpur, Maharashtra, registered with MahaRERA as P50500002523 on 1 Aug 2017. Possession was promised by 29 May 2022 and is now 53 months past that date. The completion date has moved by 18 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameMahalaxmi City Phase I
- TypeResidential / Group Housing
- Location
- Koradi Road
- Koradi Road
- Bokhara
- Bokhara
- Nagpur (Rural)
- Nagpur
- 441111
- Pincode441111
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500002523
- ReraGenie IDRG-MH-00923
Builder
- NameGruhlaxmi Life Space Private LImited
- Entity typeCompany
- Managing DirectorDhirendra Kumar Gupta
- Other registrations2 more →
- Completed2 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Aug 2017
- Promised completion29 May 2022
- Revised completionRevised to 29 May 2022 (originally 30 Nov 2020)
- Buildings15 building records
- Documents filed80 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block 1 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 2 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 3 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 4 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 5 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 6 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 7 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 8 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 9 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 10 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 11 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 12 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 13 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 14 | NA | 2 | 0 | 0 | 0 | 0 |
| Block 15 | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building15
As on 7 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
61 of 165 construction stages are filed complete across 15 buildings. The stage furthest along is Basement (if any), at 98%.
Block 170%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 98% |
| Podiums (if any) | 0% |
| Plinth | 98% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Block 253%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 98% |
| Podiums (if any) | 0% |
| Plinth | 98% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 38% |
| Sanitary Fittings within the flats / premises | 38% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 38% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
Block 362%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 98% |
| Podiums (if any) | 0% |
| Plinth | 98% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 63% |
| Sanitary Fittings within the flats / premises | 63% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 13% |
Block 470%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 98% |
| Podiums (if any) | 0% |
| Plinth | 98% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 88% |
| Sanitary Fittings within the flats / premises | 88% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Block 541%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 50% |
| Podiums (if any) | 0% |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Block 647%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Block 744%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Block 843%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Block 942%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Block 1042%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Block 1167%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Block 1258%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 35% |
Block 1376%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 35% |
Block 1477%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Block 1581%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 98% |
| Podiums (if any) | 0% |
| Plinth | 98% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 7 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 80% |
| Street Lighting | Yes | 80% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed84
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| Block 1 | 16 | 16 |
| Block 2 | 16 | 16 |
| Block 3 | 16 | 16 |
| Block 4 | 8 | 8 |
| Block 5 | 8 | 8 |
| Block 6 | 2 | 2 |
| Block 7 | 2 | 2 |
| Block 8 | 2 | 2 |
| Block 9 | 2 | 2 |
| Block 10 | 2 | 2 |
| Block 11 | 2 | 2 |
| Block 12 | 2 | 2 |
| Block 13 | 2 | 2 |
| Block 14 | 2 | 2 |
| Block 15 | 2 | 2 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Sudesh Chandra Babulalji Gupta | Bokhara | Nagpur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners9
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar Punit Gupta |
| Architect | Ar Saurabh Bhanarkar |
| Architect | Ar Abhishek Thakur |
| Engineer | Skyline Consulting Engineers Pvt. Ltd. |
| Engineer | Mr Pankaj Arya |
| Engineer | Sagar Wankhede |
| Chartered Accountant | K K S P & Company |
| Chartered Accountant | Atul Kumar & Associates |
| Chartered Accountant | Bharat Singhal & Co |
| Partner | Role in project |
|---|---|
| Gruhlaxmi Life Space Private LImited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies are observed in compliance which is under rectification. We feel regret for the delay in execution of the project due to Pandemic COVID-19. With considering the Pandemic situation and shortfall in manpower we request you to kindly grant an extension of one year due to force majeure and do the needful.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC004000000030340 | MUKESH JIWATRAM BHAGTANI | SUDESHCHANDRA GUPTA | 25/06/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 Feb 2023
Documents filed80
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5- Phase 1- RERA.pdf | 7 Feb 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MLC_OC_61 unit.pdf | 3 Feb 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MLC_79 Unit.pdf | 3 Feb 2023 |
| Certificates of CA (Form 5)File: Form 5- FY 20-21 Phase I.pdf | 2 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5- FY 20-21 Phase I.pdf | 2 Aug 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1_Dec-20_P-I.pdf | 22 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1_June-21_P-I.pdf | 22 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1_March-20_P-I.pdf | 22 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1_Sep - 20_P-I.pdf | 22 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: From-2_P-1_Dec-20.pdf | 22 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-2A_P-1_Dec-20.pdf | 22 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2(Phase-I) (1).pdf | 21 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_P-1_Sep-20.pdf | 21 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A_P-1_Sep-20.pdf | 21 Aug 2021 |
| Certificates of CA (Form 3)File: CA P-I.pdf | 21 Aug 2021 |
| Certificates of CA (Form 3)File: CA P-I.pdf | 21 Aug 2021 |
| Certificates of CA (Form 3)File: CA P-I.pdf | 21 Aug 2021 |
| Certificates of CA (Form 3)File: CA P-I.pdf | 21 Aug 2021 |
| Certificates of CA (Form 3)File: CA Phase-I.pdf | 17 Aug 2021 |
| Declaration about Commencement CertificateFile: Declaration_RERA 1.pdf | 16 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 (Phase-I).pdf | 16 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2(Phase-I).pdf | 16 Aug 2021 |
| Form 2AFile: Form-2A(Phase-I).pdf | 16 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure Sold (Phase-I).pdf | 16 Aug 2021 |
| Certificates of CA (Form 5)File: F5P1.pdf | 30 Sep 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: P1_Form1_31102019.pdf | 15 Apr 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: P1_Form1_31012020.pdf | 15 Apr 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: P1_Form2_31102019.pdf | 15 Apr 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: P1_Form2_31012020.pdf | 15 Apr 2020 |
| Form 2AFile: P1_Form2A_31102019.pdf | 15 Apr 2020 |
| Form 2AFile: P1_Form2A_31012020.pdf | 15 Apr 2020 |
| Certificates of CA (Form 3)File: P1_Form3_31102019.pdf | 15 Apr 2020 |
| Certificates of CA (Form 3)File: P1_Form3_31012020.pdf | 15 Apr 2020 |
| OtherFile: PhaseIBoMUnit list declaration311019.pdf | 3 Nov 2019 |
| Certificates of CA (Form 5)File: P1F5.pdf | 10 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: P1Architect31072019.pdf | 1 Oct 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: P1FORM231072019.pdf | 1 Oct 2019 |
| Form 2AFile: P1FORM2A31072019.pdf | 1 Oct 2019 |
| Certificates of CA (Form 3)File: P3CA310072019.pdf | 1 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PhaseIForm1ArchcerQtr300419.pdf | 27 Jun 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PhaseIForm2QTR300419.pdf | 27 Jun 2019 |
| Form 2AFile: PhaseIForm2AQTR300419.pdf | 27 Jun 2019 |
| Certificates of CA (Form 3)File: PHASEIForm3CACertqtr30042019.pdf | 27 Jun 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate-Phase i- Jan-19.pdf | 16 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Engineer Certificate-Phase i.pdf | 16 Apr 2019 |
| Form 2AFile: Form 2A- Phase I- Jan-19.pdf | 16 Apr 2019 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate-QTR31JAN19.pdf | 16 Apr 2019 |
| OtherFile: Undertaking Information for Bank account.pdf | 16 Apr 2019 |
| OtherFile: SoldunitstatustoBOM29032019.pdf | 16 Apr 2019 |
| OtherFile: Declaration of Unit Sold to BoM.pdf | 15 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate-Phase i- Oct-18.pdf | 13 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Engineer Certificate-Phase i-Oct-18.pdf | 13 Apr 2019 |
| Certificates of CA (Form 3)File: Form 3- CA Certificate-Phase i- Oct-18.pdf | 13 Apr 2019 |
| Certificates of CA (Form 5)File: MLC-Form 5 Phase 1.pdf | 30 Sep 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Mahalaxmi Phase I - Commencement Certificate.pdf | 9 Apr 2018 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: ATS Draft for Phase I.pdf | 28 Jul 2017 |
| OtherFile: Self Declaration Phase I.pdf | 28 Jul 2017 |
| Layout approvalFile: Sanction Layout 01.pdf | 26 Jul 2017 |
| Layout approvalFile: Revised Layout.pdf | 26 Jul 2017 |
| Building plan approvalFile: Building Plan 01.pdf | 26 Jul 2017 |
| Building plan approvalFile: Building Plan 02.pdf | 26 Jul 2017 |
| Building plan approvalFile: Building Plan 03.pdf | 26 Jul 2017 |
| PAN CardFile: PAN of Company.pdf | 26 Jul 2017 |
| PAN CardFile: Annexure A Certificate_of_Incorporation .PDF | 26 Jul 2017 |
| Copy of the legal title reportFile: Legal Search Report.pdf | 26 Jul 2017 |
| Details of encumbrancesFile: Encumbrance Certificate.pdf | 26 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Sanction Layout 01.pdf | 26 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Revised Layout.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Building Plan 01.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Building Plan 02.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Building Plan 03.pdf | 26 Jul 2017 |
| Declaration in FORM BFile: Form B.pdf | 26 Jul 2017 |
| Declaration in FORM BFile: Annexure (Bank of Maharashtra Consent for Release).pdf | 26 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form I- Phase I.pdf | 26 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form II- Phase I.pdf | 26 Jul 2017 |
| Certificates of CA (Form 3)File: Form III- Phase I.pdf | 26 Jul 2017 |
| Certificates of CA (Form 3)File: Annexure (Bank of Maharashtra Consent for Release).pdf | 26 Jul 2017 |
| OtherFile: Phasewise Layout.pdf | 26 Jul 2017 |
| OtherFile: Annexure (Bank of Maharashtra Consent for Release).pdf | 26 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 80 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Mahalaxmi City Phase I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Koradi Road, Bokhara2,800+ in Nagpur
Filed coordinates, straight-line distance. 34 registered projects within 2 km.
Flamingo Residency 1
Hakimi Construction Private Limited
The Bellagio
DADA PROPERTIES PRIVATE LIMITED
Morya Park 3
Moreshwar Narayanrao Bhagat
SILVER VALLEY
JARRY INFRACON
IOSIS GOLD
IOSIS CAPITAL PRIVATE LIMITED
SARASWATI NAGARI - 2
S.S.S ASSOCIATES
See every Nagpur project, with the district possession charts
Builder: Gruhlaxmi Life Space Private LImited
Gruhlaxmi Life Space Private LImited has 3 registrations on MahaRERA, including Mahalaxmi City Phase I and Mahalaxmi City Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What does it mean that Mahalaxmi City Phase I shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Mahalaxmi City Phase I is delayed beyond 29 May 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mahalaxmi City Phase I?
The registered promoter entity is Gruhlaxmi Life Space Private LImited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mahalaxmi City Phase I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Mahalaxmi City Phase I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Mahalaxmi City Phase I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mahalaxmi City Phase I?
The professionals named in the filing: Architect: Ar Punit Gupta; Architect: Ar Saurabh Bhanarkar; Architect: Ar Abhishek Thakur; Engineer: Skyline Consulting Engineers Pvt. Ltd.; Engineer: Mr Pankaj Arya; Engineer: Sagar Wankhede. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mahalaxmi City Phase I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.