Home / Browse projects / Satara, Maharashtra / MADHUSHREE PARK - CHINAR AND MANDAR

Registration lapsed No litigation declared Residential / Group Housing project

MADHUSHREE PARK - CHINAR AND MANDAR

By M/s Parshwa Associates

RG-MH-25343 · RERA P52700011838 · Last updated on MahaRERA portal: 7 Jul 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 69 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
10 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 70%
2Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

MADHUSHREE PARK - CHINAR AND MANDAR is a Residential / Group Housing project by M/s Parshwa Associates in Satara, Maharashtra, registered with MahaRERA as P52700011838 on 31 Aug 2017. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 69 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameMADHUSHREE PARK - CHINAR AND MANDAR
  • TypeResidential / Group Housing
  • Location
    • Wadhe
    • Satara
    • 415011
  • Pincode415011
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700011838
  • ReraGenie IDRG-MH-25343

Builder

  • NameM/s Parshwa Associates
  • Entity typePartnership
  • PartnerSUNIL DAMODAR NAIK

Key dates

34 months past promisethis monthRegisteredAug 2017First promiseMar 2018Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 31 Mar 2018)
  • Buildings2 building records
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CHINARNA90000
MANDARNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 7 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 70%.

CHINAR65%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
MANDAR64%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes25%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered24
BuildingClosed/CoveredTotal
CHINAR1212
MANDAR1212

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,775 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHREE BALAJI ENTERPRISESKurlaMumbai Suburban

Approvals and building plan

Permissible FSI7591.3
Proposed, not sanctioned7,591 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUTTEKAR ARCADE BOMBAY RESTAURANT CHOWK, KRISHNA NAGAR NH4, SATARA 415003

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHIJEET R TILE
PartnerRole in project
M/s Parshwa Associates-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52700000226Mar 2018 → Dec 2021

Reason as filed by the promoterTo, The Concerned Officer, Maharashtra Real Estate Regulatory Authority (MahaRERA) Bandra, Mumbai Subject - Self Declaration for extension of due date for the project registered with MahaRERA vide registration Number P52700011838 dated 31/08/2017. Sir, We have Real Estate project registered with MahaRERA authority with name “Madhushree Park - Chinar & Mandar” vide Certificate No. P52700011838 dated 31/08/2017. Due date for the completion of the project as estimated at the time of the registration is 31/03/2018. We seek extension of one year for due date of completion of the project that is 31/

EXT52700005917Mar 2018 → Dec 2021

Reason as filed by the promoterTo, The Technical Head, MahaRERA, Bandra Mumbai Subject - Consent of the allotees in the project for mutual extension of the “End date” of the project under Section 7(3) of The Real Estate (Regulation and development) Act,2016 for the project registered as “Madhushree Park - Chinar And Mandar” vide Registration Number “P52700011838” Sir, Attached is the consent taken on record of all the Twelve allottees in the project. We request you to kindly process Extension as soon as possible upto 31st December 2021. Date - 11-03-2020 Place - MUMBAI PARTNER PARSHWA ASSOCIATES

EXT52700013436Mar 2018 → Apr 2023

Reason as filed by the promoterIt is evident from the Form 1 dated 21/12/2022 provided by the Architect that all the work with respect to completion of the Building is completed. Some finishing work like water proofing, window grill in passages, common amenities and society formation is pending. Once these pending works are completed, the application for Occupancy Certificate shall be submitted by us and the project will get completed.

EXT52700017070Mar 2018 → Dec 2023

Reason as filed by the promoterWe are in process of Society formation and Conveyance in favour of society. Also, some of the Agreement to sale is pending for registration. In this light we have applied for a short extension, kindly grant us the extension.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000198110Sushil Anandrao SableM/s Parshwa Associaties14/01/2023
CC005000000258854Sushil Anandrao SableParshwa Associates13/05/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 parshwa Mar 23.pdf7 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Parshwa Form 2 Dec 2022.pdf7 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Parshwa Form 2 Apr 2023.pdf7 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: parshwa form 2a Mar 23.pdf7 Jul 2023
Disclosure of sold/ booked inventoryFile: Parshwa Disclosure of Sold Inventory.pdf7 Jul 2023
Disclosure of sold/ booked inventoryFile: Parshwa_Diclosure of Sold_Booked Inventory.pdf6 Feb 2023
Declaration about Commencement CertificateFile: Declaration for Commencement Certificate.pdf18 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: P Form 5 2018.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: P Form 5 2019.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: P Form 5 2020.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: P Form 5 2021.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: P Form 5 2022.pdf5 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Parshwa Associates Form 1.pdf31 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Parshwa Associates.pdf31 Dec 2022
Certificates of CA (Form 3)File: Parshwa Form 3 30-09-2022.pdf31 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Parshwa Form 2A - Mar 20.pdf29 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Parshwa Form 2A - Mar 21.pdf29 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Parshwa Form 2A - Mar 22.pdf29 Dec 2022
Certificates of CA (Form 3)File: Form 3 Parshwa march 2019.pdf4 Mar 2020
Layout approvalFile: Layout_Total.pdf16 Aug 2017
Layout approvalFile: Layout 2 by 6.pdf16 Aug 2017
Layout approvalFile: Layout 3 by 6.pdf16 Aug 2017
Copy of Layout Approval (in case of layout)File: Layout 2 by 6.pdf16 Aug 2017
Copy of Layout Approval (in case of layout)File: Layout 3 by 6.pdf16 Aug 2017
Copy of Layout Approval (in case of layout)File: Layout_Total.pdf16 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cerificate.pdf16 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Parshwa_compressed.pdf16 Aug 2017
Certificates of CA (Form 3)File: Form 3_Parshwa.pdf16 Aug 2017
Building plan approvalFile: NA Order.pdf15 Aug 2017
PAN CardFile: Parshwa PAN.pdf15 Aug 2017
Copy of the legal title reportFile: Title Report 1.pdf15 Aug 2017
Copy of the legal title reportFile: Title Report 2.pdf15 Aug 2017
Copy of the legal title reportFile: Title Report 3.pdf15 Aug 2017
Details of encumbrancesFile: Non Encumbrance_Parshwa.pdf15 Aug 2017
Building Plan Approval (IOD)File: NA Order.pdf15 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf15 Aug 2017
Declaration in FORM BFile: Form B_Parshwa.pdf15 Aug 2017
Proforma of Allotment letterFile: parshwa_declaration allotment letter.pdf15 Aug 2017

How this compares with Satara

16%of Satara projects moved their completion datethis one moved by 69 months
35%of Satara registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep MADHUSHREE PARK - CHINAR AND MANDAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wadhe1,100+ in Satara

2 kmMADHUSHREE PARK - CHINARCompleted 2Lapsed / revoked 6Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: M/s Parshwa Associates

M/s Parshwa Associates has 1 registration on MahaRERA, including MADHUSHREE PARK - CHINAR AND MANDAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What does it mean that MADHUSHREE PARK - CHINAR AND MANDAR shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MADHUSHREE PARK - CHINAR AND MANDAR is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MADHUSHREE PARK - CHINAR AND MANDAR?

The registered promoter entity is M/s Parshwa Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MADHUSHREE PARK - CHINAR AND MANDAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MADHUSHREE PARK - CHINAR AND MANDAR?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MADHUSHREE PARK - CHINAR AND MANDAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MADHUSHREE PARK - CHINAR AND MANDAR?

The professionals named in the filing: Architect: ABHIJEET R TILE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MADHUSHREE PARK - CHINAR AND MANDAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MADHUSHREE PARK - CHINAR AND MANDAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MADHUSHREE PARK - CHINAR AND MANDAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.