Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
M M CITY is a Residential / Group Housing project by FINE CONSTRUCTION COMPANY in Thane, Maharashtra, registered with MahaRERA as P51700022075 on 25 Aug 2019. The registration is recorded completed; possession was promised by 30 Mar 2026.
At a glance
Project
- NameM M CITY
- TypeResidential / Group Housing
- Location
- OLD MUMBAI PUNE ROAD
- NEW SHILL
- Thane (M Corp.)
- Thane
- 400612
- Pincode400612
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700022075
- ReraGenie IDRG-MH-04419
Builder
- NameFINE CONSTRUCTION COMPANY
- Entity typePartnership
- Partnersadnan mohd Shaikh, mohammed hasan khan, Amirullah Khan, umair mohmmed shaikh, Abdul Salam Khan, Mohd Zahid Motani, Irshadahmed Khan, Abdul Kayyum Khan, Shameem Khan
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on25 Aug 2019
- Promised completion30 Mar 2026
- Revised completionNone
- Buildings3 building records
- Documents filed103 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1 | NA | 8 | 0 | 0 | 0 | 0 |
| A2 WING A | NA | 8 | 0 | 0 | 0 | 0 |
| A2 WING B | NA | 14 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 29 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
A185%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
A2 WING A84%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
A2 WING B84%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Progress on shared amenities15
As on 29 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A1 | 9 | 9 |
| A2 WING A | 4 | 4 |
| A2 WING B | 5 | 5 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| NEW SHEELL CO OP HOU SOC LTD | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAMEER S LOTKE ASSOCIATES |
| Engineer | SS CONS |
| Chartered Accountant | SHABBAR & ASSOCIATES |
| Chartered Accountant | AS SUTERWALA & CO |
| Partner | Role in project |
|---|---|
| FINE CONSTRUCTION COMPANY | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jul 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 25 Dec 2024
Documents filed103
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate FY 24-25-Q1.pdf | 29 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate FY 24-25-Q1.pdf | 29 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 24-25-Q1.pdf | 29 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory FY 24-25-Q1.pdf | 29 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory FY 24-5-Q1.pdf | 29 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf | 3 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality assurance.pdf | 3 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf | 25 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate FY 23-24-Q4.pdf | 29 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory FY 23-24-Q4.pdf | 29 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Audit Report - Fine Construction Co.pdf | 19 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: Non Encumbrance Legal.pdf | 13 Feb 2024 |
| Details of encumbrances concerned to LegalFile: Non Encumbrance Legal.pdf | 13 Feb 2024 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 13 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate FY 23-24-Q3.pdf | 13 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 23-24-Q3.pdf | 13 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory FY 23-24-Q3.pdf | 13 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate FY 23-24-Q3.pdf | 13 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Audit Declaration FY 2017-18.pdf | 13 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Audit Declaration FY 2018-19.pdf | 13 Feb 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration.pdf | 13 Feb 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Allotment Letter.pdf | 13 Feb 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Agreement for Sale.pdf | 13 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate FY 22-23-Q3.pdf | 30 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate FY 22-23-Q4.pdf | 30 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate FY 23-24-Q1.pdf | 30 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate FY 23-24-Q2.pdf | 30 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 22-23-Q4.pdf | 30 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 23-24-Q1.pdf | 30 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 23-24-Q2.pdf | 30 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QA Certificate FY 2022-23.pdf | 30 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory FY 22-23-Q4.pdf | 28 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory FY 23-24-Q1.pdf | 28 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory FY 23-24-Q2.pdf | 28 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate FY 22-23-Q4.pdf | 28 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate FY 23-24-Q1.pdf | 28 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate FY 23-24-Q2.pdf | 28 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Audit Report FY 22-23.pdf | 25 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Insurance Certificate 31-03-2022.pdf | 23 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Q3.pdf | 20 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold- Q3.pdf | 20 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate- Q3 Upload.pdf | 20 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventry.pdf | 14 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold- 30062022 Upload.pdf | 14 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Audit Report - Form 5.pdf | 6 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate.pdf | 14 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 14 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: quality assurance certificate sep-2022.pdf | 14 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca Certificate Fine.pdf | 14 Nov 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH CERTIFICATE.pdf | 18 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf | 18 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 18 Aug 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 31-03-2022.pdf | 29 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Insurance Certificate 31-03-2022.pdf | 29 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 Annual Report on Statement of Accounts.pdf | 9 Apr 2022 |
| Layout approvalFile: scan0028 LAYOUT PLAN (1).pdf | 12 Feb 2022 |
| Building plan approvalFile: scan0029 BLDG A1 GR 2 COMMERCIAL.pdf | 12 Feb 2022 |
| Building plan approvalFile: scan0030 BLDG A1 3RD TO 7TH RESIDENTIAL.pdf | 12 Feb 2022 |
| Building plan approvalFile: scan0032 BLDG A2 2ND TO 7TH RESIDENTIAL.pdf | 12 Feb 2022 |
| Building plan approvalFile: Scan0031 BLDG A2 GR 1ST COMMERCIAL.pdf | 12 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: scan0028 LAYOUT PLAN (1).pdf | 12 Feb 2022 |
| Building Plan Approval (IOD)File: scan0029 BLDG A1 GR 2 COMMERCIAL.pdf | 12 Feb 2022 |
| Building Plan Approval (IOD)File: scan0030 BLDG A1 3RD TO 7TH RESIDENTIAL.pdf | 12 Feb 2022 |
| Building Plan Approval (IOD)File: scan0032 BLDG A2 2ND TO 7TH RESIDENTIAL.pdf | 12 Feb 2022 |
| Building Plan Approval (IOD)File: Scan0031 BLDG A2 GR 1ST COMMERCIAL.pdf | 12 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf | 8 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE 31-12-2021.pdf | 8 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate.pdf | 8 Feb 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 1 Quality Assurance 31-12-2021.pdf | 8 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventry.pdf | 8 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 8 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate 30-09-2021.pdf | 29 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality assurance certificate.pdf | 29 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate fine construction.pdf | 29 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Upload.pdf | 23 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Upload.pdf | 23 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 15 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance.pdf | 15 Aug 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Upload.pdf | 15 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance 2019-20.pdf | 26 May 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 103 filed documents as one ZIP, foldered, with a manifest
Keep M M CITY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEW SHILL7,600+ in Thane
Filed coordinates, straight-line distance. 99 registered projects within 2 km.
DOSTI PLANET NORTH - SECTOR 3
CHALAMA INFRAPROPERTIES PRIVATE LIMITED
NICE WORLD 1
NICE BUILDERS
CENTRAL PARK
HARMAIN ENTERPRISES
MUKTA GHARONDA
SKYLARK INFRASTRUCTURES
Palm Riveria
YES REALTY
Trinity Paradise Phase 1
Trinity Builders
See every Thane project, with the district possession charts
Builder: FINE CONSTRUCTION COMPANY
FINE CONSTRUCTION COMPANY has 1 registration on MahaRERA, including M M CITY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if M M CITY is delayed beyond 30 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of M M CITY?
The registered promoter entity is FINE CONSTRUCTION COMPANY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in M M CITY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for M M CITY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at M M CITY?
The professionals named in the filing: Architect: SAMEER S LOTKE ASSOCIATES; Engineer: SS CONS; Chartered Accountant: SHABBAR & ASSOCIATES; Chartered Accountant: AS SUTERWALA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in M M CITY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback