ReraGenieLog inGet a buyer report

Home / Browse projects / Dadra & Nagar Haveli / M.J. HEIGHTS

Completed No litigation declared Residential / Group Housing project

M.J. HEIGHTS

By SHREE KRISHNA BUILDCON

RG-MH-90486 · RERA P49600000140 · Last updated on MahaRERA portal: 21 Jan 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Dadra & Nagar Haveli registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
30 of 63Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

M.J. HEIGHTS is a Residential / Group Housing project by SHREE KRISHNA BUILDCON in Dadra & Nagar Haveli, registered with MahaRERA as P49600000140 on 26 Sep 2022. The registration is recorded completed; possession was promised by 31 Dec 2027. 33 of the 63 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameM.J. HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • SURVEY NO. 475/1/1
    • VILLAGE - AMLI
    • Others
    • Dadra & Nagar Haveli
    • 396230
  • Pincode396230
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P49600000140
  • ReraGenie IDRG-MH-90486

Builder

  • NameSHREE KRISHNA BUILDCON
  • Entity typePartnership
  • PartnersKUSHANG JAYESH PRAJAPATI, HIRENKUMAR HITENDRA SINH SOLANKI, NIRAV ISHVARSINH PARMAR, VARISKHAN NAVAZKHAN PATHAN
  • Other registrations3 more →
  • Completed2 of 4

Key dates

this monthRegisteredSep 2022PromisedDec 2027Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on26 Sep 2022
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed67 files

Current status

52%33 of 63 units booked
123.2%Work done, per cost certificate

Figures as on 21 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MJ HEIGHTSNA10063063

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

MJ HEIGHTS: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed46

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots46
Closed/Covered15
Open Space31

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,415 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Jul 2025
LandownerVillageDistrict
SURESH MANGALBHAI PATEL-Dadra & Nagar Haveli

Approvals and building plan

Sanctioning authorityDADRA AND NAGAR HAVELI PLANNING & DEVELOPMENT AUTHORITY
Permissible FSI2961.42
Proposed, not sanctioned2,820 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSILVASSA
Estimated costRs 5.34 cr
Cost incurredRs 6.58 cr
Work done123.24%
BuildingWingEstimatedIncurred
MJ HEIGHTSNARs 4.92 crRs 5.73 cr
-NARs 42.25 lakhRs 85.36 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANTHAN BHANDARI
EngineerKRUNAL MISTRY
Chartered AccountantKUNAL B SHAH
Chartered AccountantPRATIKA CHAWLA
PartnerRole in project
SHREE KRISHNA BUILDCON-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: OC.pdf21 Jan 2026
Withdrawal Update Form 1File: FORM 1 SEPT 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: FORM 1 DEC 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: FORM 2 SEPT 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: FORM 2 DEC 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: FORM 3 SEPT 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: FORM 3 DEC 2025.pdf20 Jan 2026
Form 5 (FY 2024-2025)File: FORM 5 AS ON MAR 2025 (2).pdf20 Jan 2026
Withdrawal Update Form 1File: FORM 1 JUNE 2025.pdf20 Jul 2025
Withdrawal Update Form 2File: FORM 2 JUNE 2025.pdf20 Jul 2025
Withdrawal Update Form 3File: FORM 3 JUNE 2025.pdf20 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 MAR 2025.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 MAR 2025_compressed.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 MAR 2025.pdf17 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 Shree krishna buildcon.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: Rera to Shreekrishna Buildcon 31 March 2024.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 JUNE 2024.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 SEPT 2024.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 DEC 2024.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 DEC 2023.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 SEPT 2024.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 DEC 2024.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 JUNE 2024.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 MAR 2024.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 DEC 2023.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 DEC 2023.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Rera Form 2 to Shreekrishna Buildcon 31 March 2024.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 JUNE 2024.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 SEPT 2024.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 DEC 2024.pdf18 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A)File: FORM 2A AS ON MAR 2024.pdf18 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Shree Krishna.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: DORM 1 SEPT 2022.pdf6 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 DEC 2022.pdf6 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: Form 1 march2023.pdf6 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 JUNE 2023.pdf6 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 SEPT 2023.pdf6 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 SEPT 2022.pdf6 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 DEC 2022.pdf6 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 MAR 23.pdf6 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 JUNE 2023.pdf6 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 SEPT 2023.pdf6 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 SEPT 2022_compressed.pdf6 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: form 3 DEC 2022_compressed.pdf6 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 MAR 2023_compressed.pdf6 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 JUNE 2023_compressed.pdf6 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 SEPT 2023_compressed.pdf6 Dec 2023
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE.pdf16 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 (SHREE KRISHNA BUILDCON).pdf13 Sep 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DELCARATION ABOUT BANK.pdf13 Sep 2022
Layout approvalFile: LAYOUT 1.pdf3 Aug 2022
Building plan approvalFile: LAYOUT 3 .pdf3 Aug 2022
PAN CardFile: FIRM PAN.pdf3 Aug 2022
Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf3 Aug 2022
Details of encumbrances concerned to FinanceFile: SELF DECLARATION ON NO ENCUMBRANCE.pdf3 Aug 2022
Copy of Layout Approval (in case of layout)File: LAYOUT 1.pdf3 Aug 2022
Building Plan Approval (IOD)File: LAYOUT 3 .pdf3 Aug 2022
Commencement CertificatesFile: CC.pdf3 Aug 2022
Declaration in FORM BFile: FORM B (FIRM).pdf3 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1.pdf3 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2.pdf3 Aug 2022
CERSAI detailsFile: CERSAI REPORT.pdf3 Aug 2022
Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: AUDITED FINANCIAL STATEMENT NOT APPLICABLE.pdf3 Aug 2022
Proforma of Allotment letterFile: Proforma Letter And AFS.pdf3 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A)File: FORM 2A.pdf3 Aug 2022
Deviation Report with respect to Allotment letterFile: NOT APPLICABLE.pdf3 Aug 2022
Deviation Report with respect to model copy of AgreementFile: NOT APPLICABLE.pdf3 Aug 2022

How this compares with Dadra & Nagar Haveli

52%of this project is bookeddistrict median 30%
10%of Dadra & Nagar Haveli projects moved their completion datethis one has not
28%of Dadra & Nagar Haveli registrations have lapsed or been cancelledthis one is completed

Computed across the 210+ Dadra & Nagar Haveli projects on ReraGenie, from their own filings.

Keep M.J. HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILLAGE - AMLI210+ in Dadra & Nagar Haveli

2 kmM.J. HEIGHTSCompleted 21Lapsed / revoked 18Other 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 65 registered projects within 2 km.

Builder: SHREE KRISHNA BUILDCON

SHREE KRISHNA BUILDCON has 4 registrations on MahaRERA, including M.J. HEIGHTS and AAWAS DEEP. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Dadra & Nagar Haveli district page.

Frequently asked questions

What are my rights if M.J. HEIGHTS is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of M.J. HEIGHTS?

The registered promoter entity is SHREE KRISHNA BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in M.J. HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for M.J. HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at M.J. HEIGHTS?

The professionals named in the filing: Architect: MANTHAN BHANDARI; Engineer: KRUNAL MISTRY; Chartered Accountant: KUNAL B SHAH; Chartered Accountant: PRATIKA CHAWLA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in M.J. HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About M.J. HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save M.J. HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.