Home / Browse projects / Thane, Maharashtra / Lodha Amara Tower 47 and 48

Registered No litigation declared Residential / Group Housing project

Lodha Amara Tower 47 and 48

By LODHA DEVELOPERS LIMITED

RG-MH-02950 · RERA P51700020151 · Last updated on MahaRERA portal: 18 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 45 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2029Possession promisedmoved 45 months from the original
7 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 74%
247 of 378Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 128 documents Report an error

Lodha Amara Tower 47 and 48 is a Residential / Group Housing project by LODHA DEVELOPERS LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700020151 on 29 Mar 2019. Possession is promised by 30 Jun 2029. The completion date has moved by 45 months from the original filing. 131 of the 378 units on this registration are recorded sold or booked, and 7 of 22 construction stages are filed complete.

At a glance

Project

  • NameLodha Amara Tower 47 and 48
  • TypeResidential / Group Housing
  • Location
    • Kolshet Road
    • Kolshet
    • Thane (M Corp.)
    • Thane
    • 400607
  • Pincode400607
  • RERA no.P51700020151
  • ReraGenie IDRG-MH-02950

Builder

  • NameLODHA DEVELOPERS LIMITED
  • Entity typeCompany
  • CINL45200MH1995PLC093041
  • GSTIN27AAACL1490J1ZG
  • MdAbhishek Mangalprabhat Lodha
  • Other registrations178 more →
  • Completed16 of 179
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date3
  • Declared earlier projects22 →

Key dates

this monthRegisteredMar 2019First promiseSep 2025Revised toJun 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Mar 2019
  • Promised completion30 Jun 2029
  • Revised completionRevised to 30 Jun 2029 (originally 30 Sep 2025)
  • Buildings2 building records
  • Documents filed128 files

Current status

35%131 of 378 units booked
28.7%Work done, per cost certificate

Figures as on 18 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 47NA39391910191
Tower 48NA39391870187

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 74%.

Tower 4745%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks13%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 4835%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure74%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises8%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes40%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes40%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes0%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,695 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 Sep 2025

Approvals and building plan

Sanctioning authorityThane Municipal Corporation , Thane
Permissible FSI16492.19
Proposed, not sanctioned800 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMittal Court
Estimated costRs 159.62 cr
Cost incurredRs 45.84 cr
Work done28.72%
BuildingWingEstimatedIncurred
-NARs 55.87 crRs 16.05 cr
Tower 47NARs 51.88 crRs 14.90 cr
Tower 48NARs 51.88 crRs 14.90 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVini
ArchitectPradeep Kamble
EngineerSandeep Patil
EngineerMEHUL KAIVANT SHAH
Chartered AccountantChirag Sarvaiya
Chartered AccountantM S K A & Associates
PartnerRole in project
LODHA DEVELOPERS LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700011142Sep 2025 → Jun 2029

Reason as filed by the promoterDelay in Launch

Litigation declared2

CaseCourtStatus
290/2016Bombay High CourtPre Admission
1737/2016Bombay High CourtPre Admission

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jul 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jul 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jul 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2029

Documents filed128

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 128 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: Layout Plan for W47.pdf18 Jul 2026
Layout approvalFile: Layout plan for W48.pdf18 Jul 2026
Commencement certificateFile: CC for W47 -27-09-24.pdf18 Jul 2026
Commencement certificateFile: Commencement Cetificate for W48.pdf18 Jul 2026
Building plan approvalFile: Building plan for W47-1.pdf18 Jul 2026
Building plan approvalFile: Building plan for W47-2.pdf18 Jul 2026
Building plan approvalFile: Building plan for W47-3.pdf18 Jul 2026
Building plan approvalFile: Building Plan for W48.pdf18 Jul 2026
Withdrawal Update Form 1File: Form 1 - jUNE 26.pdf18 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf18 Jul 2026
Withdrawal Update Form 3File: Form 3.pdf18 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A - Lodha Amara Tower 47 and 48 - P51700020151.pdf24 Jun 2026
Withdrawal Update Form 1File: Form1 - Lodha Amara 47 48 - P51700020151- Mar-26.pdf22 Apr 2026
Withdrawal Update Form 2File: Form-2 Mar-26.pdf22 Apr 2026
Withdrawal Update Form 3File: Form-3 Mar-26.pdf22 Apr 2026
Withdrawal Update Form 1File: Form-1 Amara 47 and 48 Dec-25.pdf24 Jan 2026
Withdrawal Update Form 2File: LODHA AMARA - TOWER 47- 48 Form 2 Dec 25.pdf24 Jan 2026
Withdrawal Update Form 3File: LODHA AMARA - TOWER 47 - 48 Form 3 Dec 25.pdf24 Jan 2026
Layout approvalFile: Layout Plan for Lodha Amara W47 & W48.pdf7 Nov 2025
Building plan approvalFile: Building Plan _ W47 _ 2_1.pdf7 Nov 2025
Building plan approvalFile: Building Plan _ W47 _1_2.pdf7 Nov 2025
Building plan approvalFile: Section _ W47 _ 3_1.pdf7 Nov 2025
Building plan approvalFile: Building Plan _ W48 _ 1_1.pdf7 Nov 2025
Building plan approvalFile: Building Plan _ W48 _ 2_1.pdf7 Nov 2025
Withdrawal Update Form 1File: Form1 - P51700020151 - Lodha Amara 47 48.pdf25 Oct 2025
Withdrawal Update Form 2File: Lodha Amara 47 48_Form 2.pdf25 Oct 2025
Withdrawal Update Form 3File: Lodha Amara 47 48_Form 3.pdf25 Oct 2025
Form 5 (FY 2024-2025)File: Amara 47 48.pdf13 Oct 2025
Form 2A (FY 2024-2025)File: Lodha Amara 47 48 - P51700020151 - Form 2A.pdf25 Jul 2025
OthersFile: Updated CC.pdf18 Jul 2025
Self-declaration of Quarterly ProgressFile: Layout Lodha Amara W47 & W48.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold amara tower 47-48- June-25.pdf18 Jul 2025
Form 1File: Form -1 Amara Tower 47 48 - Form1 - June 25.pdf18 Jul 2025
Form 2File: form 2 amara tower 47-48 - June-25.pdf18 Jul 2025
Form 3File: Form 3 amara tower 47-48- June-25.pdf18 Jul 2025
Form 1File: Lodha Amara Tower 47 and 48.pdf30 May 2025
Form 2File: Form 2 - LODHA AMARA - TOWER 47 & 48 - Mar 25.pdf30 May 2025
Form 3File: Amara 47-48 Mar-25 Form 3.pdf30 May 2025
Disclosure of Sold and Booked InventoryFile: Amara 47-48_Sold&Unsold Mar-25.pdf30 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Lodha Amara Tower 47 and 48.pdf2 May 2025
Certificates of CA (Form 3)File: Amara 47-48 Form-3 Dec-24 Signed.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - LODHA AMARA - TOWER 47 and 48.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Amara 47-48 Sold Unsold Signed.pdf3 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Lodha Amara Tower 47 and 48.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Signed Form-2 Amara -47 48 -Sept-24.pdf31 Dec 2024
Disclosure of sold/ booked inventoryFile: Signed Sold Unsold Amara 47 48 - Sept-24.pdf31 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: amara 47 48.pdf4 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: P51700020151 - Lodha Amara - Tower 47 48.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Lodha Amara 47 48 - P51700020151.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Lodha Amara 47 48 - P51700020151 - June24.pdf10 Aug 2024
Disclosure of sold/ booked inventoryFile: Lodha Amara 47 48 - P51700020151 - June24.pdf7 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold - Lodha Amara 47 48 - P51700020151 - March 24.pdf28 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Lodha Amara 47 48 - P51700020151 - March 24.pdf7 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 - Lodha Amara 47 48 - P51700020151 - Dec23.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold - Lodha Amara 47 48 - P51700020151 - Dec23.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: Lodha Amara Tower 47 and 48 - P51700020151.pdf6 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Lodha Amara 47-48 - Form1 - Sep23.pdf21 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Lodha Amara - Tower 47 48.pdf17 Oct 2023
Layout approvalFile: 4 - Layout - C - Amended CC Plan (1).pdf2 Aug 2023
Building plan approvalFile: 70 -W47 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Building plan approvalFile: 71 -W48 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Building plan approvalFile: 72 -W48 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Layout approvalFile: 68 -W47 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Building plan approvalFile: 68 -W47 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Building plan approvalFile: 69 -W47 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Copy of Layout Approval (in case of layout)File: 4 - Layout - C - Amended CC Plan (1).pdf2 Aug 2023
Copy of Layout Approval (in case of layout)File: 68 -W47 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Building Plan Approval (IOD)File: 68 -W47 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Building Plan Approval (IOD)File: 69 -W47 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Building Plan Approval (IOD)File: 70 -W47 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Building Plan Approval (IOD)File: 71 -W48 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Building Plan Approval (IOD)File: 72 -W48 - Plot - C - Amended CC Plan.pdf2 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: Amara CC.pdf17 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold_Amara W47 W48.pdf25 May 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold_Amara W47 W48.pdf21 Mar 2023
Details of encumbrancesFile: Lodha Amara 47-48.pdf20 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 72 LODHA AMARA - TOWER 47 48.pdf12 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Amara 47,48.pdf29 Aug 2022
Certificates of CA (Form 3)File: 72 LODHA AMARA - TOWER 47 , 48.pdf10 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 72 LODHA AMARA - TOWER 47 n 48-1.pdf29 Jun 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Liana BP51700033964Dombivali, Thane140Mar 2022CompletedFeb 2026Jun 2024

How this compares with Thane

35%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 45 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Lodha Amara Tower 47 and 48 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kolshet7,600+ in Thane

Builder: LODHA DEVELOPERS LIMITED

LODHA DEVELOPERS LIMITED has 179 registrations on MahaRERA, including Lodha Adrina and Mhatre Compound. Its filings disclose 22 earlier MahaRERA projects: declares 9 of 10 past projects completed on time. Litigation is declared on 39 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Lodha Amara Tower 47 and 48 is delayed beyond 30 Jun 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Lodha Amara Tower 47 and 48?

The registered promoter entity is LODHA DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200MH1995PLC093041 and GSTIN 27AAACL1490J1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Lodha Amara Tower 47 and 48?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Lodha Amara Tower 47 and 48?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Lodha Amara Tower 47 and 48?

The professionals named in the filing: Architect: Vini; Architect: Pradeep Kamble; Engineer: Sandeep Patil; Engineer: MEHUL KAIVANT SHAH; Chartered Accountant: Chirag Sarvaiya; Chartered Accountant: M S K A & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Lodha Amara Tower 47 and 48?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Lodha Amara Tower 47 and 48. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Lodha Amara Tower 47 and 48 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.