Home / Browse projects / Thane, Maharashtra / LODHA AMARA - TOWER 1 - 5, 7 - 19

Completed No litigation declared Residential / Group Housing project

LODHA AMARA - TOWER 1 - 5, 7 - 19

By MACROTECH DEVELOPERS LIMITED

RG-MH-10636 · RERA P51700001065 · Last updated on MahaRERA portal: 28 May 2024

Source: official MahaRERA filing

Red flags

  • 24 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Nov 2019Possession promisedregistration recorded completed
162 of 198Construction stages doneacross 18 buildings; furthest along: Podiums (if any), 0%
24Complaints at MahaRERAon this registration
Jump to the 148 documents Report an error

LODHA AMARA - TOWER 1 - 5, 7 - 19 is a Residential / Group Housing project by MACROTECH DEVELOPERS LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700001065 on 25 Jul 2017. The registration is recorded completed; possession was promised by 30 Nov 2019. 24 complaints are on record with the regulator.

At a glance

Project

  • NameLODHA AMARA - TOWER 1 - 5, 7 - 19
  • TypeResidential / Group Housing
  • Location
    • .
    • Thane (M Corp.)
    • Thane
    • 400607
  • Pincode400607
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700001065
  • ReraGenie IDRG-MH-10636

Builder

  • NameMACROTECH DEVELOPERS LIMITED
  • Entity typeCompany
  • CINL45200MH1995PLC093041
  • GSTIN27AAACL1490J1ZG
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsRajendra Lodha, Rajendra Lodha, Rajendra Lodha, Rajendra Lodha, Rajendra Lodha, Rajendra Lodha, Rajendra Lodha, Rajendra Lodha, Rajendra Lodha, Rajendra Lodha, Rajendra Lodha, Rajendra Lodha and 1 more
  • Other registrations140 more →
  • Completed126 of 141
  • No longer live13 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

this monthRegisteredJul 2017PromisedNov 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on25 Jul 2017
  • Promised completion30 Nov 2019
  • Revised completionNone
  • Buildings18 building records
  • Documents filed148 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 1NA280000
TOWER 2NA280000
TOWER 3NA280000
TOWER 4NA280000
TOWER 5NA280000
TOWER 7NA280000
TOWER 8NA280000
TOWER 9NA280000
TOWER 10NA280000
TOWER 11NA280000
TOWER 12NA280000
TOWER 13NA280000
TOWER 14NA280000
TOWER 15NA280000
TOWER 16NA280000
TOWER 17NA300000
TOWER 18NA300000
TOWER 19NA300000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building18

As on 28 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

162 of 198 construction stages are filed complete across 18 buildings. The stage furthest along is Podiums (if any), at 0%.

TOWER 182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 582%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 782%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 982%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 1082%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 1182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 1282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 1382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 1482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 1582%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 1682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 1782%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 1882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 1982%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed2761

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2,761
Closed/Covered2,761
BuildingClosed/CoveredTotal
TOWER 1160160
TOWER 2162162
TOWER 3161161
TOWER 4162162
TOWER 5162162
TOWER 7159159
TOWER 8162162
TOWER 9162162
TOWER 10161161
TOWER 11160160
TOWER 12159159
TOWER 13162162
TOWER 14161161
TOWER 15162162
TOWER 16162162
TOWER 18173173
TOWER 19171171

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area27,998 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI161120.41
Proposed, not sanctioned161,120 sq m
Buildings approved18
Buildings sanctioned18

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchIndustrial Finance Branch, Union Bank Bhavan, Nariman point , Mumbai-400021

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
LODHA DEVELOPERS LIMITED-

Litigation declared2

CaseCourtStatus
290/2016Bombay High CourtPre Admission
1737/2016Bombay High CourtPre Admission

Complaints filed with MahaRERA24

Case no.ComplainantRespondentFiled
CC006000000000663SANJAY SAWANTLodha developrs thane pvt ltd02/10/2017
CC006000000000670SACHIN DANDEKARLODHA DEVELOPERS THANE PVT LTD20/09/2017
CC006000000000713Surendra V RawoolLodha Amara05/11/2017
CC006000000000750Linal Prasenjit MohitePratik Maurya31/12/2017
CC006000000079343Swapnil KambleMacrotech Developers Limited22/05/2019
CC006000000100363Nilesh Sadashiv SonawaneMacrotech developers limited01/08/2019
CC006000000100367Vipin D RatnaparkhiMacrotech developers Limited01/08/2019
CC006000000100368SANJIV P. CHAUDHARYMacrotech developers limted01/08/2019
CC006000000100373Dhiroj K BaradMacrotech Developers limited02/08/2019
CC006000000100377Vaibhav NarkarMacrotech developers limited02/08/2019
CC006000000192699Rohil JulaniyaMacrotech Developers ltd.21/02/2020
CC006000000012749CHINMAYA MOHANTYLODHA08/01/2018
CC006000000044449Dipti Rishabh ArjariaLODHA GROUP11/05/2018
CC006000000055764Surendra Ramchandra GuravIshwer Realty and Technologies pvt ltd14/09/2018
CC006000000056148SRINIVAS G DASARIANKIT CHANDAK23/09/2018
CC006000000057576Sureshkumar SinghLodha Developers Limited07/01/2019
CC006000000057313Nutan LohiyaBellismo Developers Pvt Ltd14/12/2018
CC006000000057315NUTAN LOHIYABellissmo Developers Thane Pvt Ltd14/12/2018
CC006000000195952CASA FRESCO F TO J CO-OPERATIVE HOUSING SOCIETY LIMITEDMACROTECH DEVELOPERS LIMITED11/02/2021
CC006000000057829PRASHANT MANElodha developer25/01/2019
CC006000000058097CHANDAN PREMCHANDANIBELLISSIMO DEVELOPERS THANE PRIVATE LIMITED (earlier known as LODHA DEVELOPERS THANE PRIVATE LIMITED14/02/2019
CC006000000354329Casa Fresco A to E Co-operative Housing SocietyMacrotech Developers Limited erstwhile name Lodha Developers Ltd.20/02/2023
CC006000000171517Casa Fresco A to E Co-operative Housing Society LtdMacrotech Developers Limited14/11/2019
CC12501481Hitesh AgarwalMACROTECH DEVELOPERS LIMITED02/05/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 May 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Nov 2021

Documents filed148

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 148 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: LODHA AMARA - TOWER 1 - 5, 7 - 19 - P51700001065 - March 24.pdf28 May 2024
Disclosure of sold/ booked inventoryFile: Lodha Amara W1-W5,W7-W19 - P51700001065 - Sep23.pdf21 Dec 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate-Fresco A to E.pdf13 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Cer 7 T0 11.pdf13 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 12 TO 16.pdf13 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 17 TO 21.pdf13 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Amara W1 to W5 W7 to W16 MLCP.pdf19 Nov 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Amara W17,18,19 and MLCP.pdf19 Nov 2021
Form 2AFile: Lodha Amara 1 to 5 7 to 19.pdf3 Sep 2020
Certificates of CA (Form 5)File: Lodha Amara Twr 1 to 5 7 19.pdf7 Oct 2019
Form 2AFile: AMARA 18 BLGDGS.pdf17 Jun 2019
Certificates of Architect (Form 4)File: AMARA 1 TO 5 7 TO 19.pdf13 Jun 2019
OtherFile: LDL to MDL.pdf28 May 2019
Details of encumbrancesFile: Amara 1 to 5 7 to 19.pdf25 Feb 2019
Details of encumbrancesFile: Lodha Amara 1 to 5 7 to 19.pdf19 Nov 2018
Certificates of CA (Form 5)File: LODHA AMARA 1-5 7-19.pdf1 Oct 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Amara Casa Fresco A to E_Wing 1 to 5.pdf21 Aug 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Amara Casa Fresco F to J CHS_Wing 7 to 11.pdf21 Aug 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Amara Casa Serono A to E_Wing 12 to 16.pdf21 Aug 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Amara Casa Vista A B Sereno F G H_Wing 17 to 21.pdf21 Aug 2018
Details of encumbrancesFile: Amara T 1 to 5 and 7 to 19.pdf11 Aug 2018
Copy of the legal title reportFile: Amara all TR merged.pdf16 May 2018
Details of encumbrancesFile: AMARA 1-5 7-19.pdf30 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: Permission C C dated 20 01 2018.pdf30 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: CC_100817.pdf19 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: CC_120417.pdf19 Jan 2018
Proforma of Allotment letterFile: ATS (Amara)_v4_2 November 2017.pdf6 Nov 2017
Building plan approvalFile: W2A.pdf20 Jul 2017
Building plan approvalFile: W16 B.pdf20 Jul 2017
Building plan approvalFile: W2,W4,W13,W15.pdf20 Jul 2017
Building plan approvalFile: W1B.pdf20 Jul 2017
Building plan approvalFile: W1,W3,W5,W14,W16.pdf20 Jul 2017
Building plan approvalFile: W 7 AA (R).pdf20 Jul 2017
Building plan approvalFile: W 5 new (R).pdf20 Jul 2017
Building plan approvalFile: W 9 AA (R).pdf20 Jul 2017
Building plan approvalFile: W 14 BB (R).pdf20 Jul 2017
Building plan approvalFile: W 16AA (R).pdf20 Jul 2017
Building plan approvalFile: W 4A.pdf20 Jul 2017
Building plan approvalFile: W4.pdf20 Jul 2017
Building plan approvalFile: W3A.pdf20 Jul 2017
Building plan approvalFile: W2B.pdf20 Jul 2017
Building plan approvalFile: W 11 new (R).pdf20 Jul 2017
Building plan approvalFile: W 3 new (R).pdf20 Jul 2017
Building plan approvalFile: W 2 new (R).pdf20 Jul 2017
Building plan approvalFile: W 1 AA (R).pdf20 Jul 2017
Building plan approvalFile: W 8 (R).pdf20 Jul 2017
Building plan approvalFile: W 7 (R).pdf20 Jul 2017
Building plan approvalFile: W 12 AA (R).pdf20 Jul 2017
Building plan approvalFile: W 10C (R).pdf20 Jul 2017
Building plan approvalFile: W 8B (R).pdf20 Jul 2017
Building plan approvalFile: W 8A (R).pdf20 Jul 2017
Building plan approvalFile: W 8A (R).pdf20 Jul 2017
Building plan approvalFile: W16.pdf20 Jul 2017
Building plan approvalFile: W 11A (R).pdf20 Jul 2017
Building plan approvalFile: W 10B (R).pdf20 Jul 2017
Building plan approvalFile: W 10A (R).pdf20 Jul 2017
Building plan approvalFile: W 10 (R).pdf20 Jul 2017
Building plan approvalFile: W 9B (R).pdf20 Jul 2017
Building plan approvalFile: W 4B (R).pdf20 Jul 2017
Building plan approvalFile: W 5A (R).pdf20 Jul 2017
Building plan approvalFile: W 7B (R).pdf20 Jul 2017
Building plan approvalFile: W 9 (R).pdf20 Jul 2017
Building plan approvalFile: W 11B (R).pdf20 Jul 2017
Building plan approvalFile: W 11 C (R).pdf20 Jul 2017
Building plan approvalFile: W 12 (R).pdf20 Jul 2017
Building plan approvalFile: W 13A (R).pdf20 Jul 2017
Building plan approvalFile: W 13B (R).pdf20 Jul 2017
Building plan approvalFile: W 13 (R).pdf20 Jul 2017
Building plan approvalFile: W 14 (R).pdf20 Jul 2017
Building plan approvalFile: W 14A (R).pdf20 Jul 2017
Building plan approvalFile: W 15A (R).pdf20 Jul 2017
Building plan approvalFile: W 15B (R).pdf20 Jul 2017
Building plan approvalFile: W 15 (R).pdf20 Jul 2017
Building plan approvalFile: W 17R A (R).pdf20 Jul 2017
Building plan approvalFile: W 17R B (R).pdf20 Jul 2017
Building plan approvalFile: W 17R (R).pdf20 Jul 2017
Building plan approvalFile: W 18R A (R).pdf20 Jul 2017
Building plan approvalFile: W 18R B (R).pdf20 Jul 2017
Building plan approvalFile: W 18R (R).pdf20 Jul 2017
Building plan approvalFile: W 19R B (R).pdf20 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Liana BP51700033964Dombivali, Thane140Mar 2022CompletedFeb 2026Jun 2024

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LODHA AMARA - TOWER 1 - 5, 7 - 19 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near .7,600+ in Thane

2 kmLODHA AMARA - TOWER 1 - Completed 96Lapsed / revoked 19Other 58Dot size: filed unitsN

Filed coordinates, straight-line distance. 173 registered projects within 2 km.

Builder: MACROTECH DEVELOPERS LIMITED

Macrotech Developers Limited has 141 registrations on MahaRERA, including LODHA BELMONDO ASHBRIDGE D, E and LODHA BELMONDO AUGUSTA B. Its filings disclose 6 earlier MahaRERA projects: declares 5 of 6 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if LODHA AMARA - TOWER 1 - 5, 7 - 19 is delayed beyond 30 Nov 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LODHA AMARA - TOWER 1 - 5, 7 - 19?

The registered promoter entity is MACROTECH DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200MH1995PLC093041 and GSTIN 27AAACL1490J1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LODHA AMARA - TOWER 1 - 5, 7 - 19?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against LODHA AMARA - TOWER 1 - 5, 7 - 19?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for LODHA AMARA - TOWER 1 - 5, 7 - 19?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in LODHA AMARA - TOWER 1 - 5, 7 - 19?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LODHA AMARA - TOWER 1 - 5, 7 - 19. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LODHA AMARA - TOWER 1 - 5, 7 - 19 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.