Home / Browse projects / Pune, Maharashtra / LIVMO PHASE II

Registration lapsed No litigation declared Residential / Group Housing project

LIVMO PHASE II

By PRIYANKA BUILDERS

RG-MH-34565 · RERA P52100049773 · Last updated on MahaRERA portal: 11 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
14 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 94%
46 of 196Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 110 documents Report an error

LIVMO PHASE II is a Residential / Group Housing project by PRIYANKA BUILDERS in Pune, Maharashtra, registered with MahaRERA as P52100049773 on 24 Feb 2023. Possession was promised by 27 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 150 of the 196 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameLIVMO PHASE II
  • TypeResidential / Group Housing
  • Location
    • MIDC Main road
    • Hinjewadi Phase III
    • Bhoirwadi
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100049773
  • ReraGenie IDRG-MH-34565

Builder

  • NamePRIYANKA BUILDERS
  • Entity typePartnership
  • PartnersJITENDRA SUNDERDAS PANJABI, RAJU RAM PANJABI, NARESH RAM PANJABI
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredFeb 2023First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Feb 2023
  • Promised completion27 Dec 2025
  • Revised completionRevised to 27 Dec 2025 (originally 31 Dec 2024)
  • Buildings2 building records
  • Documents filed110 files

Current status

77%150 of 196 units booked
100.0%Work done, per cost certificate

Figures as on 11 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building BNA181484084
Building ANA18141120112

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 11 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 94%.

Building B80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.94%
Building A80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.94%

Progress on shared amenities15

As on 11 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsYes90%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes95%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes75%
Open ParkingYes95%

Parking filed87

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots87
Open Space87
BuildingOpen SpaceTotal
Building B4444
Building A4343

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area8,781 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Sep 2025

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI12150.0
Proposed, not sanctioned11,576 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMaratha Chambers, Plot no 2, SDC Sector 25, Bhel Chowk Road, Nigdi, Pune 411044
Estimated costRs 45.46 cr
Cost incurredRs 45.46 cr
Work done100.0%
BuildingWingEstimatedIncurred
Building ANARs 19.27 crRs 19.27 cr
Building BNARs 17.09 crRs 17.09 cr
-NARs 9.09 crRs 9.09 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVka Architecture
EngineerAkshay Nigade
EngineerYogesh Suresh Tamke
Chartered AccountantMadhusudan Jhanwar
Chartered AccountantL. B. Laddha & Co
PartnerRole in project
PRIYANKA BUILDERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025550Dec 2024 → Dec 2025

Reason as filed by the promoterDue to the unavoidable circumstances beyond our control, we are few months behind the planned schedule for completion of the above said project

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC12501343Ananya MaitiPRIYANKA BUILDERS22/04/2025
CC12501596Saswat Ranjan RayPRIYANKA BUILDERS14/05/2025
CC12501800Prateek SenapatiPRIYANKA BUILDERS01/06/2025
CC12501741Madhusmita SamantarayPRIYANKA BUILDERS27/05/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed110

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5 - F Y 2024-25 - Livmo Ph-II.pdf11 May 2026
Form 2A (FY 2025-2026)File: Livmo Ph-II - Form 2A (signed).pdf5 May 2026
Withdrawal Update Form 1File: Livmo Ph-II - Form 1 (signed).pdf15 Jan 2026
Withdrawal Update Form 2File: Livmo Ph-II - Form 2 (signed).pdf15 Jan 2026
Withdrawal Update Form 3File: Livmo Ph-II - Form 3 (signed).pdf15 Jan 2026
Withdrawal Update Form 1File: Livmo Ph-II - Form 1 (signed).pdf20 Oct 2025
Withdrawal Update Form 2File: Livmo Ph-II - Form 2 (signed).pdf20 Oct 2025
Withdrawal Update Form 3File: Livmo Ph-II - Form 3 (signed).pdf20 Oct 2025
Withdrawal Update Form 1File: Livmo Ph-II - Form 1 (signed).pdf17 Sep 2025
Withdrawal Update Form 2File: Livmo Ph-II - Form 2 (signed).pdf17 Sep 2025
Withdrawal Update Form 3File: Livmo Ph-II - Form 3 (signed).pdf17 Sep 2025
Form 2A (FY 2024-2025)File: Livmo Ph-II - Form 2A (signed).pdf17 Sep 2025
Form 1File: LivmoPh-II.pdf10 Sep 2025
Form 2File: Livmo Ph-II.pdf10 Sep 2025
Form 3File: Livmo Ph-II.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: Livmo Ph-II.pdf10 Sep 2025
Form 5 (FY 2023-2024)File: Form 5 - F Y 2023-24 - Livmo Ph-II.pdf10 Sep 2025
Disclosure of sold/ booked inventoryFile: Livmo Ph-II - Inventory Disclosure.pdf20 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Livmo Ph-II - Form 2A (signed).pdf20 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Livmo Ph-II - Form 1.pdf17 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Livmo Ph-II - Form 3 (signed).pdf17 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Livmo Ph-II - Form 2 (signed).pdf17 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Livmo Ph-II - Form 2A.pdf17 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Livmo Ph-II.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LivmoPh-II.pdf14 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Livmo Ph-II.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Livmo Ph-II.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Livmo Ph-II.pdf11 Jan 2025
Disclosure of sold/ booked inventoryFile: Livmo Ph-II.pdf9 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - F Y 2023-24 - Livmo Ph-II.pdf25 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Livmo Ph-II.pdf23 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Livmo Ph-II.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Livmo Ph-II.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Livmo Ph-II.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LivMo Ph-II.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LivMo Ph-II.pdf16 Jul 2024
Disclosure of sold/ booked inventoryFile: LivMo Ph-II.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LivMo Ph-II.pdf13 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A LIVMO PH-II.pdf13 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LivMo Ph-II.pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LivMo Ph-II.pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LivMo Ph-II.pdf12 Apr 2024
Disclosure of sold/ booked inventoryFile: LivMo Ph-II.pdf11 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A LIVMO PH-II.pdf5 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Livmo Phase II.pdf24 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Livmo Phase II.pdf23 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Livmo Phase II.pdf22 Jan 2024
Disclosure of sold/ booked inventoryFile: Livmo Ph-II.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Livmo Ph-II.pdf16 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 LIVMO PH-II 1 APRIL 2022 TO 31 MARCH 2023.pdf9 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 LIVMO PH-II SEP-23_11zon.pdf30 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A LivMO Ph-II SEPTEMBER-23.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 LivMO Ph-II SEPTEMBER-23.pdf18 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 LivMO Ph-II SEPTEMBER-23.pdf13 Oct 2023
Disclosure of sold/ booked inventoryFile: LIVMO PH-II Inventory.pdf12 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 LivMO Ph-II.pdf8 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 LIVMO PH-II 070723.pdf20 Jul 2023
Proforma of Agreement for saleFile: LivMO Ph-II Proforma of Agreement for sale for RERA.pdf5 Jul 2023
Other - TechnicalFile: Declaration About Commencement Certificate Form D Priyanka Builders.pdf20 Feb 2023
Other - TechnicalFile: Letter about survye no change Livmo.pdf20 Feb 2023
Other - TechnicalFile: Livmo all 7_12 extract.pdf20 Feb 2023
Other - TechnicalFile: Bhoirwadi 370 RTS Dtd 080322.pdf20 Feb 2023
Other - TechnicalFile: 3-19_11zon.pdf20 Feb 2023
Other - TechnicalFile: 4-19_11zon.pdf20 Feb 2023
Other - TechnicalFile: 5-19_11zon.pdf20 Feb 2023
Other - TechnicalFile: 6-19_11zon.pdf20 Feb 2023
Other - TechnicalFile: 7-19_11zon.pdf20 Feb 2023
Other - TechnicalFile: 8-19_11zon.pdf20 Feb 2023
Other - TechnicalFile: 9-19_11zon.pdf20 Feb 2023
Other - TechnicalFile: 10-19_11zon.pdf20 Feb 2023
Other - TechnicalFile: 11-19_11zon.pdf20 Feb 2023
Other - TechnicalFile: 12-19_11zon.pdf20 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Livmo Ph II Form 1_11zon.pdf7 Feb 2023
Proforma of Agreement for saleFile: LIVMO PHASE II_agreement RERA 2023.pdf21 Jan 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report LIVMO PH II_compressed.pdf18 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest Livmo Ph II.pdf17 Jan 2023
Details of encumbrances concerned to FinanceFile: encumbrances concerned to Legal.pdf16 Jan 2023
Details of encumbrances concerned to LegalFile: encumbrances concerned to Legal.pdf16 Jan 2023
Proforma of Allotment letterFile: Allotment letter LIVMO II.pdf6 Jan 2023
Copy of the legal title reportFile: Flow of the Title .pdf4 Jan 2023

How this compares with Pune

77%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LIVMO PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Hinjewadi Phase III13,700+ in Pune

2 kmLIVMO PHASE IICompleted 3Lapsed / revoked 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: PRIYANKA BUILDERS

PRIYANKA BUILDERS has 2 registrations on MahaRERA, including LIVMO PHASE I and LIVMO PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that LIVMO PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if LIVMO PHASE II is delayed beyond 27 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LIVMO PHASE II?

The registered promoter entity is PRIYANKA BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LIVMO PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against LIVMO PHASE II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for LIVMO PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LIVMO PHASE II?

The professionals named in the filing: Architect: Vka Architecture; Engineer: Akshay Nigade; Engineer: Yogesh Suresh Tamke; Chartered Accountant: Madhusudan Jhanwar; Chartered Accountant: L. B. Laddha & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LIVMO PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LIVMO PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LIVMO PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.