Red flags

  • Registration lapsed
  • Possession 17 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 23 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
May 2025Possession promised17 months past this date
13 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 95%
2Complaints at MahaRERAon this registration
Jump to the 126 documents Report an error

Lifescapes Shubham is a Residential / Group Housing project by Rohan Developers Pvt Ltd in PRARTHNA SAMAJ, 400004, registered with MahaRERA as P51900002696 on 2 Aug 2017. Possession was promised by 31 May 2025 and is now 17 months past that date. The completion date has moved by 23 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameLifescapes Shubham
  • TypeResidential / Group Housing
  • Location
    • VP ROAD
    • PRARTHNA SAMAJ
    • 400004
  • Pincode400004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900002696
  • ReraGenie IDRG-MH-21146

Builder

  • NameRohan Developers Pvt Ltd
  • Entity typeCompany
  • Managing DirectorHarresh Navnitrai Mehta
  • Other registrations4 more →
  • Completed2 of 5
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

17 months past promisethis monthRegisteredAug 2017First promiseJun 2023Revised toMay 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Aug 2017
  • Promised completion31 May 2025
  • Revised completionRevised to 31 May 2025 (originally 30 Jun 2023)
  • Buildings3 building records
  • Documents filed126 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Lifescapes ShubhamNA360000
Lifescapes AmrutNA250000
Lifescapes Amrut AnnexNA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 26 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 95%.

Lifescapes Shubham70%
ActivityProgress
Excavation100%
Basement (if any)84%
Podiums (if any)84%
Plinth84%
Stilt Floor85%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Lifescapes Amrut91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Lifescapes Amrut Annex47%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed327

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots327
Closed/Covered327
BuildingClosed/CoveredTotal
Lifescapes Shubham302302
Lifescapes Amrut2525

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,273 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai
Permissible FSI31122.15
Proposed, not sanctioned31,122 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMaulana Shaukat Ali Road, Grant Road, Mumbai-7

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDesign Group
EngineerSuresh Appa Patil
Chartered AccountantAnand
Chartered AccountantA.K. Yadav & Associates
PartnerRole in project
Rohan Developers Private Limited-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900014016Jun 2023 → Jun 2024

Reason as filed by the promoterDue to Notification from Urban Development Department, Government of Maharashtra issued on 08th July 2021, additional FSI is granted for the project under DCPR regulation 33(7) and 33(9) to all the new as well as existing on going projects. Promoter has decided to take the benefit of additional incentive granted on the ongoing project i.e. Lifescapes Shubham to make the project financially viable. We have taken the consents for additional floors from the allottees and updated on the MAHARERA Portal at that time and have got the amended plans approved for additional 10 floors vide Amended Appro

EXT51900024196Jun 2023 → Dec 2024

Reason as filed by the promoterDue to some earlier delays in obtaining approvals from various regulatory authorities in the expected timelines, the project execution was already delayed. Construction activities had slowed down and had significantly impacted the project progress due to shortage of labour and material supply during Covid-19 Pandemic. During pandemic, the civil contractor demobilised majority of the labourers from the site. Later on, he was not able to remobilise the labour force as per site needs due to which the timelines for other activities of finishing, lift fitting, etc have been delayed accordingly. As

EXT51900027203Jun 2023 → May 2025

Reason as filed by the promoterRCC work of the project Lifescapes Shubham is fully completed and now finishing work and MEP activities are under process. Hence, we are seeking short extension of 5 months for the project Lifescapes Shubham. Construction activity of the project could not proceed as per the original plan due to various reasons and is expected to be completed within the next 5 months. The construction activity of the project got affected to the following reasons: The approach to the project is through a very narrow lanes, causing delays in movement of goods vehicle due to traffic congestions and there are furth

Litigation declared2

CaseCourtStatus
307/450/2003Small Causes Court at BombayMatter is part heard
520/2014Small Causes Court at BombayMatter is part heard

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12603688DHAIRYA VIJAY BHANSALIRohan Developers Private Limited15/06/2026
CC12603800SUJANSINGH SHERSINGH DEORARohan Developers Private Limited19/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed126

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A_Shubham FY 24-25_Signed.pdf26 Dec 2025
Form 5 (FY 2024-2025)File: Form 5_Shubham_FY 2024-25_Portal signed.pdf14 Nov 2025
Form 1File: Shubham -Form 1 Q-1- 25-26.pdf30 Oct 2025
Form 2File: FORM 2 - Shubham - Q1 25-26.pdf30 Oct 2025
Form 3File: Shubham_RERA_Form 3_Q1 FY 2025-26.pdf30 Oct 2025
Disclosure of Sold and Booked InventoryFile: Shubham Inventory Disclosure_Q1 FY 25-26.pdf30 Oct 2025
Form 1File: Shubham -Form 1 Q-4_24-25.pdf19 Jun 2025
Form 2File: FORM 2 - Shubham - Q4 24-25.pdf19 Jun 2025
Form 3File: Shubham_RERA_Form 3_Q4 FY 2024-25.pdf19 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure Shubham Q4 FY 24-25.pdf19 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q3 24-25.pdf24 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham -Form 1 Q-3- 24-25.pdf20 Jan 2025
Declaration in FORM BFile: Form B Shubham_17012025.pdf18 Jan 2025
Certificates of CA (Form 3)File: Form 3_Shubham_Q3 FY 24-25.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: Shubham Inventory Disclosure Q3 FY 24-25.pdf17 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Shubham_Declaration of RERA bank account.pdf17 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest_HNM.pdf17 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest_MHM.pdf17 Jan 2025
Certificates of CA (Form 3)File: Shubham RERA Form 3 Q2 FY 2024-25.pdf13 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory Disclosure Q2 24-25 Shubham.pdf13 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham -Form 1 Q-2- 24-25.pdf2 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q2 24-25.pdf2 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-Lifescapes Shubham-FY 23-24.pdf2 Jan 2025
Certificates of CA (Form 3)File: Shubham_Form 3_Q1 FY 24-25.pdf11 Nov 2024
Disclosure of sold/ booked inventoryFile: Inventory Disclosure Q1 24-25 Shubham.pdf11 Nov 2024
Home Buyer /Allottee Grievance Redressal CellFile: Appointment Letter - GRO - Shubham.pdf2 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham_Form 1_Q 1_FY 24-25.pdf16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_Shubham_Q1 FY 24-25.pdf16 Jul 2024
Declaration about Commencement CertificateFile: Format D - Declaration about CC_Shubham.pdf29 Jun 2024
Declaration in FORM BFile: New Notarised Form B Declaration - Shubham - 28062024.pdf29 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham -Form 1 Q-4- 23-24.pdf21 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q4 23-24.pdf21 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A - Shubham - 2023-2024.pdf21 Jun 2024
Disclosure of sold/ booked inventoryFile: Shubham_Inventory Disclosure_Q4 FY 23-24.pdf17 Jun 2024
Certificates of CA (Form 3)File: FORM-3-LIFESCAPES SHUBHAM-Q 4-2023-24.pdf11 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham -Form 1 Q-3 - 23-24.pdf19 Mar 2024
Disclosure of sold/ booked inventoryFile: Shubham Inventory Disclosure Q3 FY 23-24_compressed (1).pdf15 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q2 23-24.pdf13 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q3 23-24.pdf13 Mar 2024
Certificates of CA (Form 3)File: FORM 3 - Shubham - Q3 23-24.pdf13 Mar 2024
Disclosure of sold/ booked inventoryFile: Shubham Inventory Disclosure Q2.pdf23 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham -Form 1 Q-2 - 23-24.pdf21 Feb 2024
Certificates of CA (Form 3)File: FORM 3-Lifescapes Shubham-Q 2.pdf21 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Shubham_Revalidation Letter.pdf6 Feb 2024
Disclosure of sold/ booked inventoryFile: Shubham Inventory Disclosure Q1 23-24.pdf6 Feb 2024
Certificates of CA (Form 3)File: FORM 3-LIFESCAPES SHUBHAM-Q 1 FY 2023-24.pdf6 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q1 23-24.pdf4 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham_Form 1_ Q1 FY 23-24.pdf5 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure Shubham 31032023 - Q4.pdf17 Aug 2023
Certificates of CA (Form 3)File: FORM 3-LIFESCAPES SHUBHAM-Q 4 - FY-22-23.pdf3 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-SHUBHAM -2022-23.pdf3 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lifescapes Shubham -Form 1 Q-1 22-23.pdf31 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lifescapes Shubham -Form 1 Q-2 22-23.pdf31 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lifescapes Shubham -Form 1 Q-4 22-23.pdf31 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Shubham - Q1 22-23.pdf31 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q2 22-23.pdf31 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q4 22-23.pdf31 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - Shubham - 2022-2023.pdf31 Jul 2023
Certificates of CA (Form 3)File: Lifescapes Shubham_FY_22-23_Q 1.pdf21 Jun 2023
Certificates of CA (Form 3)File: RERA_Form 3_Shubham_Q3 FY 22-23.pdf21 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Shubham Form 5.pdf24 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2122 Shubham.pdf14 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lifescapes Shubham -Form 1 Q-3 22-23.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 SHUBHAM Q2 22-23.pdf9 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q3 22-23.pdf2 Mar 2023
Disclosure of sold/ booked inventoryFile: Shubham Disclosure.pdf17 Feb 2023
Building plan approvalFile: 1.pdf27 Jan 2022
Building plan approvalFile: 2.pdf27 Jan 2022
Building plan approvalFile: 1.pdf27 Jan 2022
Building plan approvalFile: 3.pdf27 Jan 2022
Building plan approvalFile: 4.pdf27 Jan 2022
Building Plan Approval (IOD)File: 1.pdf27 Jan 2022
Building Plan Approval (IOD)File: 2.pdf27 Jan 2022
Building Plan Approval (IOD)File: 1.pdf27 Jan 2022
Building Plan Approval (IOD)File: 3.pdf27 Jan 2022
Building Plan Approval (IOD)File: 4.pdf27 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf27 Jan 2022
Disclosure of sold/ booked inventoryFile: Shubham disclosure 2022 (1).pdf27 Jan 2022
Declaration about Commencement CertificateFile: Declaration about CC20-01-2022.pdf20 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Shubham- Form 2A- 2019-20 (1).pdf20 Jan 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Lifescapes AashianaNepean Sea Road41CompletedDec 2014Late, Jun 2016

Keep Lifescapes Shubham on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PRARTHNA SAMAJ

Builder: Rohan Developers Pvt Ltd

Rohan Developers Pvt. Ltd. has 5 registrations on MahaRERA, including Lifescapes Mirage and 7 Hughes. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record.

Frequently asked questions

What does it mean that Lifescapes Shubham shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Lifescapes Shubham is delayed beyond 31 May 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Lifescapes Shubham?

The registered promoter entity is Rohan Developers Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Lifescapes Shubham?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Lifescapes Shubham?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Lifescapes Shubham?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Lifescapes Shubham?

The professionals named in the filing: Architect: Design Group; Engineer: Suresh Appa Patil; Chartered Accountant: Anand; Chartered Accountant: A.K. Yadav & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Lifescapes Shubham?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Lifescapes Shubham. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Lifescapes Shubham to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.