Home / Browse projects / Lifescapes Shubham
Lifescapes Shubham
RG-MH-21146 · RERA P51900002696 · Last updated on MahaRERA portal: 26 Dec 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 17 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 23 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Lifescapes Shubham is a Residential / Group Housing project by Rohan Developers Pvt Ltd in PRARTHNA SAMAJ, 400004, registered with MahaRERA as P51900002696 on 2 Aug 2017. Possession was promised by 31 May 2025 and is now 17 months past that date. The completion date has moved by 23 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameLifescapes Shubham
- TypeResidential / Group Housing
- Location
- VP ROAD
- PRARTHNA SAMAJ
- 400004
- Pincode400004
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900002696
- ReraGenie IDRG-MH-21146
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on2 Aug 2017
- Promised completion31 May 2025
- Revised completionRevised to 31 May 2025 (originally 30 Jun 2023)
- Buildings3 building records
- Documents filed126 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Lifescapes Shubham | NA | 36 | 0 | 0 | 0 | 0 |
| Lifescapes Amrut | NA | 25 | 0 | 0 | 0 | 0 |
| Lifescapes Amrut Annex | NA | 1 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 26 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
13 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 95%.
Lifescapes Shubham70%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 84% |
| Podiums (if any) | 84% |
| Plinth | 84% |
| Stilt Floor | 85% |
| Slabs of Super Structure | 95% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Lifescapes Amrut91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Lifescapes Amrut Annex47%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 26 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed327
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Lifescapes Shubham | 302 | 302 |
| Lifescapes Amrut | 25 | 25 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Design Group |
| Engineer | Suresh Appa Patil |
| Chartered Accountant | Anand |
| Chartered Accountant | A.K. Yadav & Associates |
| Partner | Role in project |
|---|---|
| Rohan Developers Private Limited | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Notification from Urban Development Department, Government of Maharashtra issued on 08th July 2021, additional FSI is granted for the project under DCPR regulation 33(7) and 33(9) to all the new as well as existing on going projects. Promoter has decided to take the benefit of additional incentive granted on the ongoing project i.e. Lifescapes Shubham to make the project financially viable. We have taken the consents for additional floors from the allottees and updated on the MAHARERA Portal at that time and have got the amended plans approved for additional 10 floors vide Amended Appro
Reason as filed by the promoterDue to some earlier delays in obtaining approvals from various regulatory authorities in the expected timelines, the project execution was already delayed. Construction activities had slowed down and had significantly impacted the project progress due to shortage of labour and material supply during Covid-19 Pandemic. During pandemic, the civil contractor demobilised majority of the labourers from the site. Later on, he was not able to remobilise the labour force as per site needs due to which the timelines for other activities of finishing, lift fitting, etc have been delayed accordingly. As
Reason as filed by the promoterRCC work of the project Lifescapes Shubham is fully completed and now finishing work and MEP activities are under process. Hence, we are seeking short extension of 5 months for the project Lifescapes Shubham. Construction activity of the project could not proceed as per the original plan due to various reasons and is expected to be completed within the next 5 months. The construction activity of the project got affected to the following reasons: The approach to the project is through a very narrow lanes, causing delays in movement of goods vehicle due to traffic congestions and there are furth
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 307/450/2003 | Small Causes Court at Bombay | Matter is part heard |
| 520/2014 | Small Causes Court at Bombay | Matter is part heard |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12603688 | DHAIRYA VIJAY BHANSALI | Rohan Developers Private Limited | 15/06/2026 |
| CC12603800 | SUJANSINGH SHERSINGH DEORA | Rohan Developers Private Limited | 19/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jan 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed126
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: Form 2A_Shubham FY 24-25_Signed.pdf | 26 Dec 2025 |
| Form 5 (FY 2024-2025)File: Form 5_Shubham_FY 2024-25_Portal signed.pdf | 14 Nov 2025 |
| Form 1File: Shubham -Form 1 Q-1- 25-26.pdf | 30 Oct 2025 |
| Form 2File: FORM 2 - Shubham - Q1 25-26.pdf | 30 Oct 2025 |
| Form 3File: Shubham_RERA_Form 3_Q1 FY 2025-26.pdf | 30 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Shubham Inventory Disclosure_Q1 FY 25-26.pdf | 30 Oct 2025 |
| Form 1File: Shubham -Form 1 Q-4_24-25.pdf | 19 Jun 2025 |
| Form 2File: FORM 2 - Shubham - Q4 24-25.pdf | 19 Jun 2025 |
| Form 3File: Shubham_RERA_Form 3_Q4 FY 2024-25.pdf | 19 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Disclosure Shubham Q4 FY 24-25.pdf | 19 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q3 24-25.pdf | 24 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham -Form 1 Q-3- 24-25.pdf | 20 Jan 2025 |
| Declaration in FORM BFile: Form B Shubham_17012025.pdf | 18 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3_Shubham_Q3 FY 24-25.pdf | 17 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Shubham Inventory Disclosure Q3 FY 24-25.pdf | 17 Jan 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Shubham_Declaration of RERA bank account.pdf | 17 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest_HNM.pdf | 17 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest_MHM.pdf | 17 Jan 2025 |
| Certificates of CA (Form 3)File: Shubham RERA Form 3 Q2 FY 2024-25.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure Q2 24-25 Shubham.pdf | 13 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham -Form 1 Q-2- 24-25.pdf | 2 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q2 24-25.pdf | 2 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-Lifescapes Shubham-FY 23-24.pdf | 2 Jan 2025 |
| Certificates of CA (Form 3)File: Shubham_Form 3_Q1 FY 24-25.pdf | 11 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure Q1 24-25 Shubham.pdf | 11 Nov 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: Appointment Letter - GRO - Shubham.pdf | 2 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham_Form 1_Q 1_FY 24-25.pdf | 16 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_Shubham_Q1 FY 24-25.pdf | 16 Jul 2024 |
| Declaration about Commencement CertificateFile: Format D - Declaration about CC_Shubham.pdf | 29 Jun 2024 |
| Declaration in FORM BFile: New Notarised Form B Declaration - Shubham - 28062024.pdf | 29 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham -Form 1 Q-4- 23-24.pdf | 21 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q4 23-24.pdf | 21 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A - Shubham - 2023-2024.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Shubham_Inventory Disclosure_Q4 FY 23-24.pdf | 17 Jun 2024 |
| Certificates of CA (Form 3)File: FORM-3-LIFESCAPES SHUBHAM-Q 4-2023-24.pdf | 11 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham -Form 1 Q-3 - 23-24.pdf | 19 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Shubham Inventory Disclosure Q3 FY 23-24_compressed (1).pdf | 15 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q2 23-24.pdf | 13 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q3 23-24.pdf | 13 Mar 2024 |
| Certificates of CA (Form 3)File: FORM 3 - Shubham - Q3 23-24.pdf | 13 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Shubham Inventory Disclosure Q2.pdf | 23 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham -Form 1 Q-2 - 23-24.pdf | 21 Feb 2024 |
| Certificates of CA (Form 3)File: FORM 3-Lifescapes Shubham-Q 2.pdf | 21 Feb 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Shubham_Revalidation Letter.pdf | 6 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Shubham Inventory Disclosure Q1 23-24.pdf | 6 Feb 2024 |
| Certificates of CA (Form 3)File: FORM 3-LIFESCAPES SHUBHAM-Q 1 FY 2023-24.pdf | 6 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q1 23-24.pdf | 4 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham_Form 1_ Q1 FY 23-24.pdf | 5 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure Shubham 31032023 - Q4.pdf | 17 Aug 2023 |
| Certificates of CA (Form 3)File: FORM 3-LIFESCAPES SHUBHAM-Q 4 - FY-22-23.pdf | 3 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-SHUBHAM -2022-23.pdf | 3 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lifescapes Shubham -Form 1 Q-1 22-23.pdf | 31 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lifescapes Shubham -Form 1 Q-2 22-23.pdf | 31 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lifescapes Shubham -Form 1 Q-4 22-23.pdf | 31 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Shubham - Q1 22-23.pdf | 31 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q2 22-23.pdf | 31 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q4 22-23.pdf | 31 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - Shubham - 2022-2023.pdf | 31 Jul 2023 |
| Certificates of CA (Form 3)File: Lifescapes Shubham_FY_22-23_Q 1.pdf | 21 Jun 2023 |
| Certificates of CA (Form 3)File: RERA_Form 3_Shubham_Q3 FY 22-23.pdf | 21 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Shubham Form 5.pdf | 24 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2122 Shubham.pdf | 14 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lifescapes Shubham -Form 1 Q-3 22-23.pdf | 10 Mar 2023 |
| Certificates of CA (Form 3)File: Form 3 SHUBHAM Q2 22-23.pdf | 9 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Shubham - Q3 22-23.pdf | 2 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Shubham Disclosure.pdf | 17 Feb 2023 |
| Building plan approvalFile: 1.pdf | 27 Jan 2022 |
| Building plan approvalFile: 2.pdf | 27 Jan 2022 |
| Building plan approvalFile: 1.pdf | 27 Jan 2022 |
| Building plan approvalFile: 3.pdf | 27 Jan 2022 |
| Building plan approvalFile: 4.pdf | 27 Jan 2022 |
| Building Plan Approval (IOD)File: 1.pdf | 27 Jan 2022 |
| Building Plan Approval (IOD)File: 2.pdf | 27 Jan 2022 |
| Building Plan Approval (IOD)File: 1.pdf | 27 Jan 2022 |
| Building Plan Approval (IOD)File: 3.pdf | 27 Jan 2022 |
| Building Plan Approval (IOD)File: 4.pdf | 27 Jan 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 27 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: Shubham disclosure 2022 (1).pdf | 27 Jan 2022 |
| Declaration about Commencement CertificateFile: Declaration about CC20-01-2022.pdf | 20 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Shubham- Form 2A- 2019-20 (1).pdf | 20 Jan 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Lifescapes Aashiana | Nepean Sea Road | 41 | Completed | Dec 2014 | Late, Jun 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 126 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Lifescapes Shubham on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PRARTHNA SAMAJ
SHREEPATI CASTLE
SHREEPATI CASTLE
Meadows
Celestial Globe (A.O.P.)
SHREEPATI BAYVIEW
SHREEPATI BUILD INFRA INVESTMENT LIMITED
NAKODA MEHTA SUNSHINE HEIGHTS A AND C WINGS
CHANDULAL JORAVARMALJI MEHTA
Earth Enclave
Earth Graphics
Chandan Signature
PAVAN KUMAR BACHHRAJ CHANDAN
Builder: Rohan Developers Pvt Ltd
Rohan Developers Pvt. Ltd. has 5 registrations on MahaRERA, including Lifescapes Mirage and 7 Hughes. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record.
Frequently asked questions
What does it mean that Lifescapes Shubham shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Lifescapes Shubham is delayed beyond 31 May 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Lifescapes Shubham?
The registered promoter entity is Rohan Developers Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Lifescapes Shubham?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Lifescapes Shubham?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Lifescapes Shubham?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Lifescapes Shubham?
The professionals named in the filing: Architect: Design Group; Engineer: Suresh Appa Patil; Chartered Accountant: Anand; Chartered Accountant: A.K. Yadav & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Lifescapes Shubham?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback