Home / Browse projects / Pune, Maharashtra / Life Republic Sector R7- 7th Avenue- i Towers
Life Republic Sector R7- 7th Avenue- i Towers
By KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED
RG-MH-13111 · RERA P52100022154 · Last updated on MahaRERA portal: 21 Jan 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- Litigation declared, 15 cases
- 1 complaint at MahaRERA
Clear
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Life Republic Sector R7- 7th Avenue- i Towers is a Residential / Group Housing project by KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100022154 on 4 Sep 2019. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 1 complaint is on record with the regulator.
At a glance
Project
- NameLife Republic Sector R7- 7th Avenue- i Towers
- TypeResidential / Group Housing
- Location
- Survey no 74 hinjewadi-marunji-kasarsai road taluka mulshi
- Hinjewadi
- Hinjavadi (CT)
- Mulshi
- Pune
- 411057
- Pincode411057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100022154
- ReraGenie IDRG-MH-13111
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Sep 2019
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings3 building records
- Documents filed80 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building E | NA | 24 | 0 | 0 | 0 | 0 |
| Building G | NA | 24 | 0 | 0 | 0 | 0 |
| Parking Building | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 21 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 90%.
Building E73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 5% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
Building G73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 5% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
Parking Building51%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 90% |
| Plinth | 0% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 21 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 95% |
| Water Supply | Yes | 95% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | Yes | 90% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 80% |
| Energy managemcnt | Yes | 90% |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed352
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building E | 26 | 40 | 66 |
| Building G | 26 | 41 | 67 |
| Parking Building | 219 | 0 | 219 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Space Designer`s Syndicate |
| Engineer | Manish Narkhede |
| Engineer | Firoz Shaikh |
| Chartered Accountant | Nikita A Bajaj |
| Chartered Accountant | VIDHI S SHAH & ASSOCIATES CHARTERED ACCOUNTANTS |
| Partner | Role in project |
|---|---|
| KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | - |
Litigation declared15
| Case | Court | Status |
|---|---|---|
| SPL CS NO 265/2013/2013 | CCJD | Ongoing |
| RCS No 1487/2005/2005 | CCJD | Ongoing |
| SPL CS 2255/2009/2009 | CJSD | Ongoing |
| SPL CS 575/2015/2015 | CJSD | Ongoing |
| SLP CC NO 9467/2017/2017 | Supreme Court | Ongoing |
| SLP 9463/2017/2017 | Supreme Court | Ongoing |
| 421/2016/2016 | CJSD | Ongoing |
| WP 11697/2017/2017 | High court | Currently the matter is pending for admission |
| WP 11701/2017/2017 | High court | Currently the matter is pending for admission |
| WP 11702/2017/2017 | High court | Currently the matter is pending for admission |
| WPST 31252/2017/2017 | High Court | The matter is yet to come up for hearing before court Current stage is pre admission for circulation |
| RCS 1689/2021/2021 | CJJD | Currently the matter is posted for filing of written statement |
| Civil MA 372/2022/2022 | CJSD Pune | Appearance and Filing of Say |
| 7264/2022 | Bombay High Court | Admission |
| 7264/2022 | Bombay High Court | Ongoing |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12602625 | KALPESH NATUBHAI PATEL | KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | 05/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Aug 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Aug 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Aug 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 21 Jan 2025
Documents filed80
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: R7 - completion.pdf | 21 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4 - R7.pdf | 21 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: R7.pdf | 9 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: R7.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R7.pdf | 19 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: R7.pdf | 19 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R7 - i towers.pdf | 18 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R7-7th Avenue.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: R7.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R7 - i towers.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: LR R7-I.pdf | 29 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Life Republic Sector R7- 7th Avenue- i Towers.pdf | 20 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LR R7 itowers.pdf | 20 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LR R7.pdf | 17 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LR R7.pdf | 20 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R7EG.pdf | 20 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: R7 I Towers Final Inv Dec.pdf | 20 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: R7_compressed.pdf | 20 Apr 2023 |
| CERSAI detailsFile: Cersai File.pdf | 15 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R7_Q3 Form 2.pdf | 20 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Final R7 I Towers.pdf | 20 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA R7 ITowers.pdf | 20 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cer LR 7th Avenue.pdf | 19 Jan 2023 |
| CERSAI detailsFile: Final Cersai File.pdf | 16 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: LR 7th Avenue Itowers_compressed.pdf | 20 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_ R7 Sector.pdf | 20 Oct 2022 |
| CERSAI detailsFile: Cersai Report.pdf | 18 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SECTOR R 7 BLDG E G PARKING BLDG.pdf | 17 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: LR R7 7Avenue I Towers.pdf | 30 Sep 2022 |
| Other - FinanceFile: LR R7 7Avenue I Towers.pdf | 29 Sep 2022 |
| Details of encumbrancesFile: Update Encumbrances LR R7 I Towers.pdf | 18 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch - R7.pdf | 7 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R 7.pdf | 7 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Inventory Declaration I Towers.pdf | 7 Jul 2022 |
| CERSAI detailsFile: KPIT Cersai details.pdf | 4 Jul 2022 |
| Proforma of Allotment letterFile: AFS LR-R7_compressed.pdf | 30 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: R7 7 Avenue I towers.pdf | 18 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_LR R7.pdf | 12 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect_LR R7.pdf | 7 Apr 2022 |
| CERSAI detailsFile: KPIT Cersai.pdf | 6 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 I-Towers.pdf | 8 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 R-7 I-Towers.pdf | 8 Mar 2022 |
| Proforma of Allotment letterFile: Allotment letter and agreement for sale.pdf | 23 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Jambe Sector PMRDA Order - Scan.pdf | 16 Feb 2022 |
| Declaration about Commencement CertificateFile: Declaration Commencement revised sanction Sector R7.pdf | 16 Feb 2022 |
| Proforma of Allotment letterFile: AFS-LR- R7 -Building E and G-Title Report handover clause.pdf | 10 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate R7 I Towers.pdf | 20 Jan 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA ARCHITECTS CERTIFICATE JAMBE SECTOR- R_7.pdf | 18 Jan 2022 |
| CERSAI detailsFile: KPIT Cersai details.pdf | 7 Jan 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: R7 7TH AVENUE Compressed.pdf | 7 Jan 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_08_12_2021.pdf | 8 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: Declaration sold unsold inventory R 7 I TOWERS -30 Sep 21.pdf | 8 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: R 7_ Clarification NA annual report stat auditor previous years.pdf | 28 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: R 7_ Clarification NA annual report stat auditor previous years.pdf | 28 Oct 2021 |
| Proforma of Allotment letterFile: FINAL-Draft AFS-LR- R7 -Building E and G-22-10-2021.pdf | 28 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: R 7 Inventory sold declaration 30 sep 21_____.pdf | 21 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer quality assurance certificate_R7 Sep 21.pdf | 14 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 sep 21 R7.pdf | 8 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 SIGNED LR R7.pdf | 30 Sep 2021 |
| PAN CardFile: Self attested PAN.pdf | 22 Sep 2021 |
| Declaration about Commencement CertificateFile: R 7 Commencement declaration.pdf | 22 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer quality assurance certificate_R7.pdf | 22 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: R 7 E _ G bldg inventory declaration.pdf | 22 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Sector R7 E_G RERA Certificate FY 2019-20.pdf | 22 Sep 2021 |
| Proforma of Allotment letterFile: AFS-LR- R7 -Building E and G-20-07-2021.pdf | 22 Jul 2021 |
| Details of encumbrancesFile: Encumbrance R7 -7th avenue i towers signed copy.pdf | 17 Mar 2021 |
| Proforma of Allotment letterFile: FINAL-Draft AFS-LR- R7 -Building E and G-24-02-2021.pdf | 17 Mar 2021 |
| OtherFile: KPIT - LR-Sector R7 - EG RERA Certificate - FY 2019-20.pdf | 30 Sep 2020 |
| Proforma of Allotment letterFile: LR R7 Building E and G.pdf | 21 Jan 2020 |
| Proforma of Allotment letterFile: 15-12-2019-FINAL-Draft AFS-LR- R7 -Building E and G.pdf | 7 Jan 2020 |
| Layout approvalFile: sanction plan 1.pdf | 16 Aug 2019 |
| Building plan approvalFile: sanction plan 1.pdf | 16 Aug 2019 |
| Copy of the legal title reportFile: SEARCH TITLE REPORT.pdf | 16 Aug 2019 |
| Details of encumbrancesFile: encumbrances declaration.pdf | 16 Aug 2019 |
| Copy of Layout Approval (in case of layout)File: sanction plan 1.pdf | 16 Aug 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: sanction plan 1.pdf | 16 Aug 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf | 16 Aug 2019 |
| Declaration in FORM BFile: Declaration R7.pdf | 16 Aug 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 LR R7.pdf | 16 Aug 2019 |
| Proforma of Allotment letterFile: FINAL- 14-08-2019-Draft AFS-LR- R7 -Building E and G.pdf | 16 Aug 2019 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Life Republic Sector R4 | Marunji Hinjewadi Pune | 660 | Completed | Dec 2015 | Late, Dec 2016 |
| Life Republic Sector R2 Phase I | Marunji Hinjewadi Pune | 120 | Completed | Dec 2013 | Dec 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 11 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 80 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Life Republic Sector R7- 7th Avenue- i Tower on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Hinjewadi13,700+ in Pune
Filed coordinates, straight-line distance. 265 registered projects within 2 km.
Godrej Evergreen Square
Godrej Projects Development Limited
The Aqua Retreat at Godrej Park World
Maan-Hinje Township Developers Private Lim
The Gale at Godrej Park World
Maan-Hinje Township Developers LLP
VTP BELLISSIMO PHASE 1
MAGNITE DEVELOPERS PRIVATE LIMITED
Life Republic Sector R1 - 1st Avenue
KOLTE-PATIL DEVELOPERS LIMITED
The Greenfront at Godrej Park World
Maan Hinje Township Developers Private Lim
Builder: KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED
KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED has 12 registrations on MahaRERA, including Life Republic Sector R2 - 2nd Avenue and Life Republic Sector R16 - 16th Avenue. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Life Republic Sector R7- 7th Avenue- i Towers shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Life Republic Sector R7- 7th Avenue- i Towers is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Life Republic Sector R7- 7th Avenue- i Towers?
The registered promoter entity is KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Life Republic Sector R7- 7th Avenue- i Towers?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Life Republic Sector R7- 7th Avenue- i Towers?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Life Republic Sector R7- 7th Avenue- i Towers?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Life Republic Sector R7- 7th Avenue- i Towers?
The professionals named in the filing: Architect: Space Designer`s Syndicate; Engineer: Manish Narkhede; Engineer: Firoz Shaikh; Chartered Accountant: Nikita A Bajaj; Chartered Accountant: VIDHI S SHAH & ASSOCIATES CHARTERED ACCOUNTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Life Republic Sector R7- 7th Avenue- i Towers?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback