Home / Browse projects / Pune, Maharashtra / Life Republic Sector R16 - 16th Avenue Arezo
Life Republic Sector R16 - 16th Avenue Arezo
By KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED
RG-MH-34091 · RERA P52100018539 · Last updated on MahaRERA portal: 9 Oct 2024
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 11 other registrations.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Life Republic Sector R16 - 16th Avenue Arezo is a Others project by KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100018539 on 13 Nov 2018. The registration is recorded completed; possession was promised by 30 Dec 2023.
At a glance
Project
- NameLife Republic Sector R16 - 16th Avenue Arezo
- TypeOthers
- Location
- Hinjewadi-Marunji-Kasarsai ROad
- Hinjewadi
- Jambe
- Mulshi
- Pune
- 411057
- Pincode411057
- RERA no.P52100018539
- ReraGenie IDRG-MH-34091
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on13 Nov 2018
- Promised completion30 Dec 2023
- Revised completionNone
- Buildings4 building records
- Documents filed85 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 24 | 0 | 0 | 0 | 0 |
| Building B | NA | 24 | 0 | 0 | 0 | 0 |
| Building C | NA | 24 | 0 | 0 | 0 | 0 |
| Building E Shops | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 9 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
40 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.
Building A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building E Shops91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 9 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed519
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building A | 136 | 37 | 173 |
| Building B | 136 | 37 | 173 |
| Building C | 136 | 37 | 173 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SPACE DESIGNERS’ SYNDICATE |
| Engineer | JW Consultant LLP |
| Chartered Accountant | VIDHI S SHAH & ASSOCIATES CHARTERED ACCOUNTANTS |
| Partner | Role in project |
|---|---|
| KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | - |
Litigation declared14
| Case | Court | Status |
|---|---|---|
| SLP CC No 9463/2017/2017 | Supreme Court | disposed off |
| 421/2016/2016 | CJSD Pune | Currently the suit is pending for withdrawal or dismissal |
| 11697/2017/2017 | High Court | Currently the matter is pending for admission |
| 11701/2017/2017 | High Court | Currently the matter is pending for admission |
| 11702/2017/2017 | High Court | Currently the matter is pending for admission |
| SPL CS 2255/2009/2009 | CJSD | The matter is pending adjudication and is currently fixed for framing additional issues |
| SPL CS 575/2015/2015 | CJSD | disposed off |
| SLP CC No 9467/2017/2017 | Supreme Court | disposed off |
| SPL CS No 265/2013/2013 | CJJD | The matter is pending adjudication and is pending at evidence stage |
| RCS No 1487/2005/2005 | CJJD | The matter is pending adjudication and is currently fixed for evidence |
| WPST 31252/2017/2017 | High Court | The matter is yet to come up for hearing before court Current stage is pre admission for circulation |
| RCS 1689/2021/2021 | CJJD | Currently the matter is posted for filing of written statement |
| Civil MA 372/2022/2022 | CJSD Pune | Appearance and Filing of Say |
| 7264/2022 | Bombay High Court | Admission |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Nov 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Nov 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Nov 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 17 Jan 2024
Documents filed85
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: R16 ABC.pdf | 9 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: R16 ABC.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R16 ABC-Form 2.pdf | 19 Jan 2024 |
| Certificates of CA (Form 3)File: R16 ABC-Form 3.pdf | 19 Jan 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: R16 E shop completion.pdf | 17 Jan 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: R16 A,B,C completion certificate.pdf | 17 Jan 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4_R16.pdf | 17 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R16-16th Avenue-Arezo ABC.pdf | 20 Oct 2023 |
| Certificates of CA (Form 3)File: R16-16th Avenue Arezo.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R16 Arezo.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: LR R16-ABC.pdf | 29 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Life Republic Sector R16 - 16th Avenue Arezo ABC.pdf | 20 Jul 2023 |
| Certificates of CA (Form 3)File: R16 ABC.pdf | 20 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LR R16 ABCE.pdf | 17 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LR R16.pdf | 20 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R16 Arezo ABC.pdf | 20 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: LR 16 Avenue Arezo Final Inv Dec.pdf | 20 Apr 2023 |
| Certificates of CA (Form 3)File: R16 Arezo Form 3.pdf | 20 Apr 2023 |
| CERSAI detailsFile: Cersai File.pdf | 15 Apr 2023 |
| Proforma of Agreement for saleFile: AFS R16 Avenue Arezo.pdf | 28 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R16ABC_Q3 Form 2.pdf | 20 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Final R16 Arezo.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: CA 16 Arezo.pdf | 20 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cer LR R16.pdf | 19 Jan 2023 |
| CERSAI detailsFile: Final Cersai File.pdf | 16 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: LR R16 Avenue Arezo.pdf | 20 Oct 2022 |
| Certificates of CA (Form 3)File: FORM 3_R16 ABC _compressed ___.pdf | 20 Oct 2022 |
| CERSAI detailsFile: Cersai Report.pdf | 18 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SECTOR R 16 BLDG ABCE.pdf | 17 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: LR R16Avenue Arezo ABC.pdf | 30 Sep 2022 |
| Other - FinanceFile: LR R16Avenue Arezo ABC.pdf | 29 Sep 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch - R16 Arezo.pdf | 7 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R 16.pdf | 7 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Inventory Declaration 16 Avenue Arezo.pdf | 7 Jul 2022 |
| Certificates of CA (Form 3)File: CA - R16 Arezo_compressed.pdf | 7 Jul 2022 |
| CERSAI detailsFile: KPIT Cersai details.pdf | 4 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: R16 16 Avenue Arezo_compressed.pdf | 18 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_LR Arezo.pdf | 12 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect_R16 Arezo.pdf | 7 Apr 2022 |
| Certificates of CA (Form 3)File: CA_LR R16 Arezo_compressed.pdf | 7 Apr 2022 |
| CERSAI detailsFile: KPIT Cersai.pdf | 6 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Arezo.pdf | 8 Mar 2022 |
| Certificates of CA (Form 3)File: Form 3 R-16 Avenue Arezo.pdf | 8 Mar 2022 |
| Proforma of Allotment letterFile: AFS-R16-Project 2-Arezo- AFS-Title Report handover clause _16 feb-compressed.pdf | 17 Feb 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Sector R16- Society Registration Certificate-10-02-2022 (2).pdf | 16 Feb 2022 |
| Proforma of Allotment letterFile: AFS_R16_Project 2_Arezo_compressed.pdf | 10 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate LR R16 Avenue Arezo.pdf | 20 Jan 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA ARCHITECTS CERTIFICATE JAMBE SECTOR-R-16, BLDG-A,B,C,E.pdf | 18 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: LR R 16 A to C BUILDING.pdf | 12 Jan 2022 |
| Certificates of CA (Form 3)File: R16 Arezo-compressed.pdf | 7 Jan 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_08_12_2021.pdf | 8 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: Declaration sold unsold inventory R16 ABC Arezo.pdf | 8 Dec 2021 |
| Proforma of Allotment letterFile: Final Draft AFS LR R16 Arezo Project 2 POST OC 04 12 2021.pdf | 7 Dec 2021 |
| Proforma of Allotment letterFile: FINAL-Draft AFS-R16-Project 2-Arezo- AFS-29-10-2021-compressed.pdf | 30 Oct 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf | 28 Oct 2021 |
| Proforma of Allotment letterFile: AFS_R16_Project 2Arezo-compressed.pdf | 28 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: R 16 ABC inventory declaration 30 sep 21.pdf | 21 Oct 2021 |
| Certificates of CA (Form 3)File: Form 3 sep 21 R 16 ABC.pdf | 13 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 SIGNED LR R16 ABC 2020-21.pdf | 30 Sep 2021 |
| PAN CardFile: Self attested PAN.pdf | 22 Sep 2021 |
| Declaration about Commencement CertificateFile: R 16 Arezo Commencement declaration.pdf | 22 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: R 16 Arezo Declaration NA quality assurance.pdf | 22 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: R 16 Arezo Declaration NA quality assurance.pdf | 22 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: R 16 Arezo A,B,C , E bldg inventory declaration.pdf | 22 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Sector R16 Arezo Form 5 Nov 18-March 19.pdf | 22 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Sector R16 - A,B,C RERA Certificate - FY 2019-20.pdf | 22 Sep 2021 |
| Proforma of Allotment letterFile: AFS-R16-Project 2-Arezo- AFS-20-07-2021_compressed.pdf | 22 Jul 2021 |
| Details of encumbrancesFile: Encumbrance update july R16 arezo.pdf | 7 Jul 2021 |
| Proforma of Allotment letterFile: FINAL-Draft AFS-R16-Project 2-Arezo- AFS-30-06-2021_compressed.pdf | 1 Jul 2021 |
| Proforma of Allotment letterFile: FINAL-Draft AFS-R16-Project 2-Arezo- AFS-Rera Upload.pdf | 29 Apr 2021 |
| Annual Audit Report of Statutory CA (Form 5)File: 12071 KPIT - LR-Sector R16 - ABC RERA Certificate - FY 2019-20.pdf | 30 Sep 2020 |
| Proforma of Allotment letterFile: FINAL-R16-Project 2-Arezo- AFS-13-01-2020.pdf | 21 Jan 2020 |
| Annual Audit Report of Statutory CA (Form 5)File: Signed Certificate R16 Arezo March 19.pdf | 29 Sep 2019 |
| Proforma of Allotment letterFile: FINAL AFS R16 Project 2 Arezo 05022019.pdf | 5 Feb 2019 |
| Details of encumbrancesFile: Self Declartion Encumbrances Life Republic 16th Avenue Arezo.pdf | 3 Nov 2018 |
| Declaration in FORM BFile: Affidavit cum Declaration.pdf | 3 Nov 2018 |
| Proforma of Allotment letterFile: Agreement R16 Arezo.pdf | 3 Nov 2018 |
| OtherFile: Allotment Letter Life Republic 16th Avenue Arezo.pdf | 3 Nov 2018 |
| Building plan approvalFile: Layout R16.pdf | 1 Nov 2018 |
| Layout approvalFile: Layout R16.pdf | 1 Nov 2018 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Life Republic Sector R4 | Marunji Hinjewadi Pune | 660 | Completed | Dec 2015 | Late, Dec 2016 |
| Life Republic Sector R2 Phase I | Marunji Hinjewadi Pune | 120 | Completed | Dec 2013 | Dec 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 11 other registrations, which the RERA portal never shows together
- All 85 filed documents as one ZIP, foldered, with a manifest
Keep Life Republic Sector R16 - 16th Avenue Arezo on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Hinjewadi13,700+ in Pune
Godrej Evergreen Square
Godrej Projects Development Limited
The Aqua Retreat at Godrej Park World
Maan-Hinje Township Developers Private Lim
The Gale at Godrej Park World
Maan-Hinje Township Developers LLP
VTP BELLISSIMO PHASE 1
MAGNITE DEVELOPERS PRIVATE LIMITED
Life Republic Sector R1 - 1st Avenue
KOLTE-PATIL DEVELOPERS LIMITED
The Greenfront at Godrej Park World
Maan Hinje Township Developers Private Lim
Builder: KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED
KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED has 12 registrations on MahaRERA, including Life Republic Sector R2 - 2nd Avenue and Life Republic Sector R16 - 16th Avenue. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Life Republic Sector R16 - 16th Avenue Arezo is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Life Republic Sector R16 - 16th Avenue Arezo?
The registered promoter entity is KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Life Republic Sector R16 - 16th Avenue Arezo?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Life Republic Sector R16 - 16th Avenue Arezo?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Life Republic Sector R16 - 16th Avenue Arezo?
The professionals named in the filing: Architect: SPACE DESIGNERS’ SYNDICATE; Engineer: JW Consultant LLP; Chartered Accountant: VIDHI S SHAH & ASSOCIATES CHARTERED ACCOUNTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Life Republic Sector R16 - 16th Avenue Arezo?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback