Home / Browse projects / Pune, Maharashtra / Legacy Milestone
Legacy Milestone
RG-MH-19002 · RERA P52100077968 · Last updated on MahaRERA portal: 22 Oct 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Rs 100.00 crore secured on the land, in favour of Aditya Birla Capital Ltd, Aditya Birla Finance Ltd
Clear
- No litigation declared
- No complaints on record
- No extension sought by the promoter; the date moved only under MahaRERA's automatic 4-month extension
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Legacy Milestone is a Residential / Group Housing project by Infinity Associates in Pune, Maharashtra, registered with MahaRERA as P52100077968 on 14 Nov 2024. Possession is promised by 30 Apr 2030. The completion date has moved by 4 months under MahaRERA's automatic 4-month extension for the West Asia conflict, which the promoter did not apply for. 262 of the 806 units on this registration are recorded sold or booked, and 16 of 63 construction stages are filed complete.
At a glance
Project
- NameLegacy Milestone
- TypeResidential / Group Housing
- Location
- Kate Wasti
- Punawale
- Mulshi
- Pune
- 411033
- Pincode411033
- RERA no.P52100077968
- ReraGenie IDRG-MH-19002
Builder
- NameInfinity Associates
- Entity typePartnership
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Nov 2024
- Promised completion30 Apr 2030
- Revised completionRevised to 30 Apr 2030 (originally 31 Dec 2029)
- Buildings7 building records
- Documents filed191 files
Current status
Figures as on 22 Oct 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | A | 25 | 23 | 92 | 0 | 92 |
| Building B | B | 25 | 23 | 111 | 0 | 111 |
| Building C | C | 25 | 23 | 138 | 0 | 138 |
| Building D | D | 25 | 23 | 88 | 0 | 88 |
| Building E | E | 25 | 23 | 138 | 0 | 138 |
| Building F | F | 25 | 23 | 92 | 0 | 92 |
| Building G | G | 23 | 21 | 147 | 0 | 147 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building7
As on 22 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is Plinth, at 50%.
Building A · wing A38%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 41% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building B · wing B36%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 24% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building C · wing C31%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 50% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 32% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building D · wing D35%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 12% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building E · wing E35%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 16% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building F · wing F11%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building G · wing G11%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 22 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed1910
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Stilt / Ground | Basement | Total |
|---|---|---|---|---|---|
| Building A A | 118 | 0 | 0 | 0 | 118 |
| Building B B | 132 | 16 | 0 | 0 | 148 |
| Building C C | 180 | 0 | 0 | 0 | 180 |
| Building D D | 120 | 0 | 0 | 0 | 120 |
| Building E E | 142 | 0 | 0 | 0 | 142 |
| Building F F | 0 | 0 | 180 | 414 | 594 |
| Building G G | 0 | 0 | 238 | 370 | 608 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building G | G | Rs 51.25 cr | Rs 2.24 cr |
| - | NA | Rs 39.43 cr | Rs 11.11 cr |
| Building C | C | Rs 36.94 cr | Rs 14.94 cr |
| Building E | E | Rs 36.94 cr | Rs 10.24 cr |
| Building F | F | Rs 34.02 cr | Rs 2.24 cr |
| Building A | A | Rs 33.61 cr | Rs 15.40 cr |
| Building B | B | Rs 30.13 cr | Rs 9.52 cr |
| Building D | D | Rs 25.19 cr | Rs 8.90 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mehul Shah |
| Engineer | Rupesh Mahamuni |
| Chartered Accountant | Pravin Pise and associates |
| Chartered Accountant | G M Achhara And Associates |
| Partner | Role in project |
|---|---|
| Infinity Associates | - |
Extensions1
A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.
Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Oct 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Oct 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Oct 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Oct 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Apr 2030
Documents filed191
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 191 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Engineers Certificate Form-2A 05-06-2026.pdf | 22 Oct 2026 |
| Layout approvalFile: 01-20 Lay Out_compressed.pdf | 19 Oct 2026 |
| Building plan approvalFile: 02-20 Parking Floor Plan_compressed.pdf | 19 Oct 2026 |
| Building plan approvalFile: 03-20 Parking and Club House Plan_compressed.pdf | 19 Oct 2026 |
| Building plan approvalFile: 04-20 A-Bldg Floor Plan.pdf | 19 Oct 2026 |
| Building plan approvalFile: 05-20 A-Bldg Elevation.pdf | 19 Oct 2026 |
| Building plan approvalFile: 06-20 B-Bldg Floor Plan_compressed.pdf | 19 Oct 2026 |
| Building plan approvalFile: 07-20 B-Bldg Elevation.pdf | 19 Oct 2026 |
| Building plan approvalFile: 08-20 C-Bldg Floor Plan_compressed.pdf | 19 Oct 2026 |
| Building plan approvalFile: 09-20 C-Bldg Section.pdf | 19 Oct 2026 |
| Building plan approvalFile: 10-20 C-Bldg Terrace Floor Plan.pdf | 19 Oct 2026 |
| Building plan approvalFile: 11-20 D-Bldg Floor Plan.pdf | 19 Oct 2026 |
| Building plan approvalFile: 12-20 D-Bldg Terrace Floor Plan.pdf | 19 Oct 2026 |
| Building plan approvalFile: 13-20 E-Bldg Floor Plan.pdf | 19 Oct 2026 |
| Building plan approvalFile: 14-20 E-Bldg Section.pdf | 19 Oct 2026 |
| Building plan approvalFile: 15-20 E-Bldg Terrace Floor Plan.pdf | 19 Oct 2026 |
| Building plan approvalFile: 16-20 F-Bldg Floor Plan.pdf | 19 Oct 2026 |
| Building plan approvalFile: 17-20 F-Bldg Section.pdf | 19 Oct 2026 |
| Building plan approvalFile: 18-20 G-Bldg Floor Plan.pdf | 19 Oct 2026 |
| Building plan approvalFile: 19-20 G-Bldg Elevation.pdf | 19 Oct 2026 |
| Building plan approvalFile: 20-20 G-Bldg Section.pdf | 19 Oct 2026 |
| Commencement certificateFile: Milestone Commencement.pdf | 19 Oct 2026 |
| Withdrawal Update Form 1File: Q 2 Form 1- Architects Certificate 01-10-2026.pdf | 19 Oct 2026 |
| Withdrawal Update Form 2File: Form-2 Milestone- Q2-FY-2026-27.pdf | 19 Oct 2026 |
| Withdrawal Update Form 3File: Form-3 Legacy Milestone_compressed.pdf | 19 Oct 2026 |
| Withdrawal Update Form 1File: Form 1 - Legacy Milestone -02-07-2026.pdf | 21 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 - Legacy Milestone -02-07-2026.pdf | 21 Jul 2026 |
| Withdrawal Update Form 2File: Form-2 Legacy Milestone 07-07-2026.pdf | 21 Jul 2026 |
| Withdrawal Update Form 2File: Form-2 Legacy Milestone 07-07-2026.pdf | 21 Jul 2026 |
| Withdrawal Update Form 3File: Form-3 Legacy Milestone 13-07-2026_compressed.pdf | 21 Jul 2026 |
| Withdrawal Update Form 3File: Form-3 Legacy Milestone 13-07-2026_compressed.pdf | 21 Jul 2026 |
| Form 5 (FY 2025-2026)File: Form 5 FY-25-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 1File: Architects Certificate 21-03-2026.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: Q4 Milestone .pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: Q4 Fprm 3 Milestone _compressed.pdf | 18 Apr 2026 |
| Layout approvalFile: 01-18 Layout_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 02-18 Parking Floor Plan_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 03-18 Parking Floor and Club house.pdf | 31 Mar 2026 |
| Building plan approvalFile: 04-18 A Building Floor Plan_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 05-18 A Building Section and Elevation_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 06-18 B Building_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 07-18 B Building Section and Elevation_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 08-18 C Building Floor Plan_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 09-18 C Building Section and Elevation_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 10-18 D Building_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 11-18 D Building Section and Elevation_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 12-18 E Building Floor Plan_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 13-18 E Building Section and Elevation_compressed.pdf | 31 Mar 2026 |
| Building plan approvalFile: 14-18 F Building Floor Plan.pdf | 31 Mar 2026 |
| Building plan approvalFile: 15-18 F Building Section and Elevation.pdf | 31 Mar 2026 |
| Building plan approvalFile: 16-18 G Building.pdf | 31 Mar 2026 |
| Building plan approvalFile: 17-18 G Building Section and Elevation.pdf | 31 Mar 2026 |
| Building plan approvalFile: 18-18 G Building Section.pdf | 31 Mar 2026 |
| Withdrawal Update Form 1File: Q3- Architects Certificate 06-01-2026.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: Form-2 Engineers Certificate 07-01-2026.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: CA Certificate 07-01-2026.pdf | 27 Jan 2026 |
| Withdrawal Update Form 1File: Q2 - Form 1 - Milestone - 2025-2026.pdf | 13 Jan 2026 |
| Withdrawal Update Form 2File: Form-2 Engineers Certificate 07-01-2026.pdf | 13 Jan 2026 |
| Withdrawal Update Form 3File: Q3 CA Certificate Legacy Milestone 07-01-2026.pdf | 13 Jan 2026 |
| Withdrawal Update Form 1File: Q2 - Form 1 - Milestone - 2025-2026.pdf | 27 Oct 2025 |
| Withdrawal Update Form 1File: Q2 - Form 1 - Milestone - 2025-2026.pdf | 27 Oct 2025 |
| Withdrawal Update Form 2File: Q2 - Form 2 - Milestone - 2025-2026.pdf | 27 Oct 2025 |
| Withdrawal Update Form 2File: Q2 - Form 2 - Milestone - 2025-2026.pdf | 27 Oct 2025 |
| Withdrawal Update Form 3File: Form - 3.pdf | 27 Oct 2025 |
| Withdrawal Update Form 3File: Q2 - Form 3 - Milestone - 2025-2026_compressed.pdf | 27 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form2-A 2025 Legacy Milestone.pdf | 16 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Infinity Associates -FY-24-25.pdf | 30 Sep 2025 |
| Building plan approvalFile: 04-17.pdf | 20 Sep 2025 |
| Layout approvalFile: 01-17 Layout.pdf | 20 Aug 2025 |
| Building plan approvalFile: 02-17.pdf | 20 Aug 2025 |
| Building plan approvalFile: 03-17.pdf | 20 Aug 2025 |
| Building plan approvalFile: 05-17.pdf | 20 Aug 2025 |
| Building plan approvalFile: 06-17.pdf | 20 Aug 2025 |
| Building plan approvalFile: 07-17.pdf | 20 Aug 2025 |
| Building plan approvalFile: 08-17.pdf | 20 Aug 2025 |
| Building plan approvalFile: 09-17.pdf | 20 Aug 2025 |
| Building plan approvalFile: 10-17.pdf | 20 Aug 2025 |
| Building plan approvalFile: 11-17.pdf | 20 Aug 2025 |
| Building plan approvalFile: 12-17.pdf | 20 Aug 2025 |
| Building plan approvalFile: 13-17.pdf | 20 Aug 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 191 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Legacy Milestone on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Punawale14,000+ in Pune
Construction of 24 LIG, 768 MIG and commercial
Pune Housing & Area Development Board
Kohinoor Avantara
Intofinity Promoters Private Limited
AISHWARYAM INSIGNIA
VIKSAK VINODE INFRATECH LLP
KOHINOOR UPTOWN AVENUE
MOONSTONE REALINFRA PRIVATE LIMITED
LUSH RESIDENCES
LUSH RESIDENCES LLP
RENUKA PANCHATATTVA
Renuka Realty Private Limited
Builder: Infinity Associates
Infinity Associates has 2 registrations on MahaRERA, including Infinity Residences and Legacy Milestone. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Legacy Milestone is delayed beyond 30 Apr 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Legacy Milestone?
The registered promoter entity is Infinity Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Legacy Milestone?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Legacy Milestone?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Legacy Milestone?
The professionals named in the filing: Architect: Mehul Shah; Engineer: Rupesh Mahamuni; Chartered Accountant: Pravin Pise and associates; Chartered Accountant: G M Achhara And Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Legacy Milestone?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback