LEELAS RESIDENCY

By OM NAVKAAR DEVELOPERS

RG-MH-30123 · RERA P51800029915 · Last updated on MahaRERA portal: 13 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
8 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

LEELAS RESIDENCY is a Residential / Group Housing project by OM NAVKAAR DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029915 on 15 Jul 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameLEELAS RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • MAMLATDAR WADI
    • MALAD WEST
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • RERA no.P51800029915
  • ReraGenie IDRG-MH-30123

Builder

  • NameOM NAVKAAR DEVELOPERS
  • Entity typePartnership
  • PartnersNILESH JAIN, LEELADEVI JAIN

Key dates

10 months past promisethis monthRegisteredJul 2021First promiseDec 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 Jul 2021
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2023)
  • Buildings1 building record
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LEELAS RESIDENCYNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

LEELAS RESIDENCY: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area428 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SURENDRA KUMAR SOLANKIBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI1152.22
Proposed, not sanctioned172 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGOREGAON WEST MUMBAI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHEMANT AND ASSOCIATES
EngineerK H SHAH
Chartered AccountantCA MEENESHSHETTY
PartnerRole in project
OM NAVKAAR DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800023010Dec 2023 → Dec 2024

Reason as filed by the promoterContractor unable to complete the projects on the given date .

EXT51800027416Dec 2023 → Dec 2025

Reason as filed by the promoterDUE TO LABOUR ISSUE & DELAY IN MATREIALS SUPPLY .BUT PROJECT IS READY NOW AND WE HAVE APPLIED FOR OCCUPENCY CERTIFICATE

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A 22-23.pdf13 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A 23-24.pdf13 Mar 2025
Declaration in FORM BFile: AFFDIVAT.pdf12 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q1.pdf3 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q2.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: INVENTROY.pdf3 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23.pdf3 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 23-24.pdf3 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 (1).pdf28 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22-23.pdf28 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1.pdf28 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q1.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q2.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q3.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FOMR 3Q1.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q2.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q3.pdf4 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q1.pdf4 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q2.pdf4 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q3.pdf4 Feb 2025
Declaration in FORM BFile: RERA APPLICATION.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31-03-2023.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30-06-2023.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30-09-2023.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31-12-2023.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31-03-2024.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA CER-02-04-2023.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA CER-5-7-2023 (3).pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA CER-12-10-2023.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA CER 12-01-2024.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA CER-12-04-2024.pdf13 Jun 2024
Disclosure of sold/ booked inventoryFile: CIRCULER NO 29.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3march 23.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3june 23.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3sep 23.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3dec 23.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DocScanner 13 Jun 2024 6-17 pm.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE (Q 4 2021 -2022).pdf31 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE (Q 1 2022 - 2023).pdf31 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE (Q 2 2022 - 2023).pdf31 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE (Q 3 2022 - 2023).pdf31 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 .pdf31 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 21-22 engineer report.pdf31 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: enginer report 2A Q1 22-23 .pdf31 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2 engineer report .pdf31 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3 engineers report .pdf31 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: OM NAVKAAR 2A.pdf31 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 compressed.pdf31 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: rera form 3 om navkar 30,6,22.pdf31 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 om navkar compressed.pdf31 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 om navkar.pdf31 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: om navkar new_compressed.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 21-22.pdf31 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FORM 3 UPDATED.pdf10 Jul 2021
Layout approvalFile: OID PLAN_2.pdf9 Jul 2021
Building plan approvalFile: OID PLAN_2.pdf9 Jul 2021
Building plan approvalFile: IOD.pdf9 Jul 2021
Copy of Layout Approval (in case of layout)File: OID PLAN_2.pdf9 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: OID PLAN_2.pdf9 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: IOD.pdf9 Jul 2021
Declaration about Commencement CertificateFile: CC DECLARATION.pdf5 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: 2280745_FirstCC_signed.pdf28 Jun 2021
Copy of the legal title reportFile: Legal Tiltle Report.pdf18 Jun 2021
Declaration in FORM BFile: Form B - Nilesh Jain.pdf18 Jun 2021
PAN CardFile: Pan Card046.pdf16 Jun 2021
Details of encumbrancesFile: NO ENCUMBRANCE.pdf16 Jun 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf16 Jun 2021
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf16 Jun 2021
Proforma of Allotment letterFile: SALE AGREEMENT.pdf16 Jun 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LEELAS RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MALAD WEST6,700+ in Mumbai Suburban

Builder: OM NAVKAAR DEVELOPERS

OM NAVKAAR DEVELOPERS has 1 registration on MahaRERA, including LEELAS RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that LEELAS RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if LEELAS RESIDENCY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LEELAS RESIDENCY?

The registered promoter entity is OM NAVKAAR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LEELAS RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LEELAS RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LEELAS RESIDENCY?

The professionals named in the filing: Architect: HEMANT AND ASSOCIATES; Engineer: K H SHAH; Chartered Accountant: CA MEENESHSHETTY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LEELAS RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LEELAS RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LEELAS RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.